Stromberg Sheet Metal Works, Inc. v. Washington Gas Energy Systems, Inc.

448 F. Supp. 2d 64, 2006 U.S. Dist. LEXIS 59036, 2006 WL 2419107
CourtDistrict Court, District of Columbia
DecidedAugust 23, 2006
DocketCivil Action 04-1936 (RMU)
StatusPublished
Cited by11 cases

This text of 448 F. Supp. 2d 64 (Stromberg Sheet Metal Works, Inc. v. Washington Gas Energy Systems, Inc.) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stromberg Sheet Metal Works, Inc. v. Washington Gas Energy Systems, Inc., 448 F. Supp. 2d 64, 2006 U.S. Dist. LEXIS 59036, 2006 WL 2419107 (D.D.C. 2006).

Opinion

MEMORANDUM OPINION

URBINA, District Judge.

Granting the Third-Party Plaintiff’s Motion to Compel Arbitration

I. INTRODUCTION

This breach of contract dispute is before the court on Washington Gas and Light Company’s (“WGL”) motion to compel arbitration. WGL, a defendant and the third-party plaintiff in this case, seeks a court order requiring Thermal Engineering Group (“TEG”), the third-party defendant, to submit to arbitration with Stromberg Sheet Metal Works, Inc. (“Stromberg”), the plaintiff. At issue in WGL’s motion is whether the arbitration clause in the contract between WGL and TEG is assignable. Because the arbitration clause is assignable and because the contract between defendant WGL and TEG states that all disputes are to be settled by arbitration, the court grants WGL’s motion to compel arbitration.

II. BACKGROUND

A. Factual Background

In 1996, the federal government awarded a contract to design and build a heating and chilling facility (“the project”) to WGL. Compl. ¶ 5. WGL entered into two subcontracts to complete the project, one with TEG to design the project, and one with defendant Washington Gas Energy Systems (‘WGES”) to serve as manager and general contractor for the project. Id. ¶ 19; Def. WGES’ Counterclaim ¶4. As project manager, WGES subcontracted with Stromberg for construction and manufacturing services. Id.

In February 2003, WGES issued a work order for Stromberg to fabricate and install combustion air intake ducts and turbine exhaust ducts. Compl. ¶ 9. Strom-berg alleges that WGES still owes $183,370 of the original $743,900 contract price. Id. ¶ 32. Stromberg also alleges that WGES requested changes to the work order with a total cost of $636,663. Id. According to Stromberg, the changes that WGES requested were necessary to fix TEG’s design defect. Id. In addition, Stromberg estimates that the cost of refa-brication due to the design defect was $284,655. Id. Consequently, Stromberg filed a complaint alleging that WGL and WGES owe it damages for unpaid work and for work that it was required to do as a result of TEG’s alleged design defect. Id. ¶¶ 22, 34; see also WGES’ Consent Mot. to Join WGL as Def. ¶ 2.

In response to Stromberg’s suit, WGES filed a counterclaim asserting that TEG’s design was not defective and that the additional costs incurred by Stromberg were a result of Stromberg’s own failure to properly fabricate, man, manage, install, and correct its work. Def. WGES’ Counterclaim ¶41. WGES alleges these failures caused a ten month delay. Id. ¶ 35. WGES’ counterclaim seeks $1,016,255 for *67 total damages due to the failures and subsequent ten-month delay. Id. ¶ 44.

Key to the motion before the court, WGES’ co-defendant, WGL, filed a third-party complaint alleging that TEG is liable for the damages resulting from any design defects. WGL’s Third-Party Compl. ¶ 16; see also Mem. of P. & A. in Supp. of Mot. to Stay Proceedings and Compel Arbitration (“WGL’s Mot. to Compel”) at 2. Because the subcontract between WGL and TEG contains a dispute resolution provision requiring mediation and arbitration instead of litigation, WGL now seeks to submit its claims against TEG to arbitration. Id.

B. Procedural Background

In September 2005, all parties submitted to a two-day mediation. WGL’s Mot. to Compel at 2. Although unable to reach a global settlement, Stromberg, WGL, and WGES agreed to dismiss, without prejudice, their disputes against each other. Id. As a part of this dismissal, WGL assigned its claims against TEG to Stromberg. Id. WGL requests, “for the use and benefit of Stromberg,” that this matter be stayed and referred to arbitration. 1 Id. The court now turns to WGL’s motion to compel arbitration.

III. ANALYSIS

A. Legal Standard for Motion to Dismiss and Compel Arbitration

The Federal Arbitration Act (“FAA”) provides that “a written provision in ... a contract to settle by arbitration a controversy thereafter arising out of such contract ... shall be valid, irrevocable, and enforceable save upon any grounds as exist at law or in equity for the revocation of any contract.” 9 U.S.C. § 2. The FAA creates a strong presumption in favor of enforcing arbitration agreements and “[a]ny doubts concerning the scope of arbitrable issues should be resolved in favor of arbitration.” Shearson/Am. Express, Inc. v. McMahon, 482 U.S. 220, 226-27, 107 S.Ct. 2332, 96 L.Ed.2d 185 (1987) (stating that arbitration agreements must be rigorously enforced); Moses H. Cone Mem’l Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 24-25, 103 S.Ct. 927, 74 L.Ed.2d 765 (1983) (noting that federal policy favors arbitration). Nevertheless, parties cannot be forced into arbitration unless they have agreed to do so. AT & T Techs. Inc. v. Commc’ns Workers, 475 U.S. 643, 648-49, 106 S.Ct. 1415, 89 L.Ed.2d 648 (1986). Moreover, the authority of arbitrators to resolve disputes is derived from the agreement of parties to engage in arbitration. Equal Employment Opportunity Comm’n v. Waffle House, Inc., 534 U.S. 279, 294, 122 S.Ct. 754, 151 L.Ed.2d 755 (2002). Because arbitration provisions are in essence a matter of contract between the parties, it is for the courts to decide whether the parties are bound by a given arbitration clause. Howsam v. Dean Witter Reynolds, Inc., 537 U.S. 79, 84, 123 S.Ct. 588, 154 L.Ed.2d 491 (2002) (holding that “a gateway dispute about whether the parties are bound by a given arbitration clause raises a question of arbitrability for a court to decide”) (internal quotation omitted).

Such questions of arbitrability are typically brought before the court pursuant to section 4 of the FAA, which permits a party to petition any United States district court which would otherwise have *68 subject-matter jurisdiction “for an order directing that such arbitration proceed in the manner provided for in such agreement.” 9 U.S.C. § 4. When presented with a motion to compel arbitration, a district court must “determine the enforceability of the agreement [to arbitrate] and decide whether arbitration should be compelled.” Nelson v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
448 F. Supp. 2d 64, 2006 U.S. Dist. LEXIS 59036, 2006 WL 2419107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stromberg-sheet-metal-works-inc-v-washington-gas-energy-systems-inc-dcd-2006.