The Cincinnati Gas & Electric Company and the Dayton Power and Light Company v. Benjamin F. Shaw Company

706 F.2d 155, 1983 U.S. App. LEXIS 28499
CourtCourt of Appeals for the Sixth Circuit
DecidedApril 27, 1983
Docket82-3038
StatusPublished
Cited by50 cases

This text of 706 F.2d 155 (The Cincinnati Gas & Electric Company and the Dayton Power and Light Company v. Benjamin F. Shaw Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Cincinnati Gas & Electric Company and the Dayton Power and Light Company v. Benjamin F. Shaw Company, 706 F.2d 155, 1983 U.S. App. LEXIS 28499 (6th Cir. 1983).

Opinion

LIVELY, Circuit Judge.

This case involves a dispute between two parties to a contract for the construction of an electrical generating plant. The question is whether this dispute is subject to arbitration provisions of the contract.

I.

The plaintiffs, Cincinnati Gas & Electric Company and Dayton Power and Light (hereafter CG & E) contracted with the defendant, The Benjamin F. Shaw Company (hereafter Shaw) to fabricate and install piping and instrumentation for a coal burning electrical generating plant known as East Bend No. 2. The contract contained a broad arbitration clause (No. 34) which provided, in part:

Any controversy or claim arising out of this Agreement or the refusal by either party thereto to perform the whole or any part thereof, shall be determined by arbitration . ..

The same clause contained a limitation on the mandatory arbitration provision:

No arbitration shall, however, include any claim or any defense to any claim that in any way denies, or challenges, or is inconsistent with the validity of any provision of this Agreement.

After some correspondence in which it sought additional compensation, on July 18, 1981 Shaw served on CG & E a demand for arbitration seeking $6,000,000 for additional work, “delays, disruptions, and resultant costs” arising from the contract. An attachment to the demand stated that the original completion date of Shaw’s work under the contract had been extended 13 months for reasons beyond Shaw’s control, specifically, by the release to Shaw of original design information four months late and some engineering information 26 months late. The attachment listed numerous categories in which Shaw’s costs had been increased due to the “resulting delays and inefficiencies.”

On July 23, 1981 CG & E filed a declaratory judgment action in the district court based on diversity of citizenship. Contend *157 ing that the claim of Shaw “is inconsistent with the validity of the entire Agreement between plaintiffs and Shaw in that it seeks by quantum meruit to substitute a new contract price for that set forth in the Agreement ],” CG & E sought a declaration that Shaw’s claim is not subject to arbitration. CG & E based its assertion of non-ar-bitrability on its contention that Shaw’s claim is inconsistent with provisions of the contract which limit recovery for “all job overhead costs” resulting from extension of Shaw’s schedule for reasons beyond its control to a maximum of $30,000 per month. The claim of $6,000,000 far exceeds $30,000 per month. It also relied upon a provision which states that dates are not guaranteed, and sought a further declaration that CG & E had no liability to Shaw on the claim. In addition the prayer of the complaint asked that Shaw be enjoined from invoking the arbitration provision of the contract.

Shaw responded to the complaint with a motion for a stay of proceedings pursuant to Section 3 of the United States Arbitration Act, 9 U.S.C. § 3 1 and for an order compelling CG & E to submit to arbitration pursuant to Section 4 of the Act, 9 U.S.C. § 4. 2 After the parties had briefed the issues the district court filed an order in which it determined that Shaw’s claim is for breach of contract, that it arose out of the agreement with CG & E and that “it does not deny, challenge nor is it inconsistent with any provision of the agreement .... ” The district court granted both of Shaw’s motions. It ordered the parties to submit the dispute to arbitration and it stayed the action for five months pending determination by the arbitrator. CG & E made a motion to amend the order to show a denial of its request for an injunction and to add a certification pursuant to 28 U.S.C. § 1292(b) that the order involves a controlling question of law as to which there is a substantial ground for difference of opinion. The district court denied the motion to amend and CG & E filed a notice of appeal.

II.

Shaw challenges the jurisdiction of this court, contending that the order of the district court is neither a final decision appeal-able under 28 U.S.C. § 1291 nor an interlocutory order made appealable by any of the provisions of 28 U.S.C. § 1292. The parties have briefed this question fully and it is clear that there is a split of authority. Though the Supreme Court has ruled on the appealability of orders compelling arbitration and orders staying actions pending arbitration in cases arising under § 301 of the Labor Management Relations Act of 1947 3 and eases in admiralty, 4 it appears not to have decided the issue in a case such as the present one arising under the Arbitration Act outside a maritime setting.

If Shaw had commenced this action in the district court and sought only an order compelling arbitration pursuant to § 4, an order either granting or denying that relief would have been appealable as a final decision pursuant to 28 U.S.C. § 1291. In reality, such an order would have disposed of *158 the entire case even though jurisdiction was retained by the district court. See University Life Insurance Co. v. Unimarc, Ltd., 699 F.2d 846 (7th Cir.1983). However, Shaw argues that since CG & E sought a declaratory judgment and other relief, the district court order was an interlocutory one made in the course of continuing litigation, and thus not appealable under § 1291. This is the rule in the Second Circuit, where an order compelling arbitration is appealable if made in an independent proceeding under § 4, but not if made in ongoing litigation. See Chatham Shipping Co. v. Fertex Steamship Corp., 352 F.2d 291, 294 (2d Cir.1965); Wilson Bros v. Textile Workers, 224 F.2d 176 (2d Cir.), cert. denied, 350 U.S. 834, 76 S.Ct. 70, 100 L.Ed. 745 (1955); cf. Tradex Limited v. Holendrecht, 550 F.2d 1337 (2d Cir.1977); Compania Espanola de PET., S.A. v. Nereus Shipping, 527 F.2d 966 (2d Cir.1975), cert. denied, 426 U.S. 936, 96 S.Ct. 2650, 49 L.Ed.2d 387 (1976).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
706 F.2d 155, 1983 U.S. App. LEXIS 28499, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-cincinnati-gas-electric-company-and-the-dayton-power-and-light-ca6-1983.