United Association of Journeymen and Apprentices of the Plumbing and Pipe Fitting Industry of the United States and Canada v. Gemma Power Systems, LLC

CourtDistrict Court, District of Columbia
DecidedJuly 15, 2022
DocketCivil Action No. 2021-0922
StatusPublished

This text of United Association of Journeymen and Apprentices of the Plumbing and Pipe Fitting Industry of the United States and Canada v. Gemma Power Systems, LLC (United Association of Journeymen and Apprentices of the Plumbing and Pipe Fitting Industry of the United States and Canada v. Gemma Power Systems, LLC) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Association of Journeymen and Apprentices of the Plumbing and Pipe Fitting Industry of the United States and Canada v. Gemma Power Systems, LLC, (D.D.C. 2022).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

UNITED ASSOCIATION OF JOURNEYMEN AND APPRENTICES OF THE PLUMBING AND PIPE FITTING INDUSTRY OF THE UNITED STATES AND CANADA, Petitioner, Civil Action No. 21-0922 (CKK)

v.

GEMMA POWER SYSTEMS, LLC, Defendant.

MEMORANDUM OPINION (July 15, 2022)

Petitioner United Association of Journeyman and Apprentices of the Plumbing and Pipe

Fitting Industry of the United States and Canada (“Petitioner” or “Plumbers”) has instituted this

action pursuant to section 301(a) of the Labor Management Relations Act (“LMRA”), 29 U.S.C.

§ 185, seeking to enforce an arbitral award dated February 25, 2021 by the Plan for the Settlement

of Jurisdictional Disputes in the Construction Industry (“Plan”). The Plan is, among other things,

an agreement among a number of North American labor unions involved in the construction trade

to settle disputes about work assignments through arbitration conducted by the Plan’s appointed

arbitrator. ECF No. 11-3 at 3.

Petitioner argues that Gemma agreed to settle work disputes under the Plan, and that,

having bound itself, impermissibly assigned work to rival unions during the construction of a

power plant in Ohio. Respondent Gemma Power Systems, LLC (“Respondent” or “Gemma”), a

construction company, has cross-moved to vacate the arbitral award for lack of jurisdiction,

arguing that it has never agreed to be bound to the Plan. As the parties have not identified any

1 contractual instrument binding Gemma to the Plan, and upon consideration of the briefing, 1 the

relevant authorities, and the entire record, the Court GRANTS IN PART AND HOLDS IN

ABEYANCE IN PART Respondent’s [11] Motion to Dismiss the Petition and DENIES

Petitioner’s [16] Cross-Motion for Summary Judgment.

I. BACKGROUND

The parties agree as to all material facts. See Resp’t’s Repl. at 2. The labor dispute here

arises from construction work that Gemma hired the International Brotherhood of Boilermakers,

Iron Ship Builders, Blacksmiths, Forgers and Helpers, AFL-CIO (“Boilermakers”) and the

International Association of Bridge, Structural, Ornamental and Reinforcing Iron Workers, AFL-

CIO (“Iron Workers”) to perform during the construction of a power plant in Guernsey, Ohio.

ECF No. 16-3 at 2-3. Initially, Gemma proposed a work agreement to the Plumbers, which the

Plumbers rejected. ECF No. 11-1 at 5, ECF No. 11-2 at 3. Rather, Gemma hired the Boilermakers

and Iron Workers, executing “Job Compliance Understanding[s]” (“JCU”), on April 15, 2020 and

January 23, 2020, respectively. To date, Gemma has never executed any agreement with the

Plumbers, although one of Gemma’s contractors appears to have subcontracted work to the

1 The Court’s consideration has focused on the following documents: • Petitioner’s Petition to Confirm Arbitration Award, ECF No. 1 (“Pet.”); • Respondent’s Memorandum in Support of Motion to Dismiss Petition to Confirm Arbitration Award, ECF No. 11-1 (“Resp’t’s Mot.”); • Petitioner’s Memorandum of Points and Authorities in Opposition to respondent’s Motion to Dismiss and Memorandum of Points and Authorities in Support of Petitioner’s Cross-Motion for Summary Judgment, ECF No. 15 (“Pet’r’s Mot.”); • Respondent’s Reply Memorandum in Support of its Motion to Dismiss the Petition and in Opposition to Petitioner’s Cross-Motion for Summary Judgment, ECF No. 20 (“Resp’t’s Repl.”); and • Petitioner’s Reply Memorandum in Support of Petitioner’s Cross-Motion for Summary Judgment (“Pet’r’s Repl.”). In an exercise of its discretion, the Court finds that holding oral argument would not be of assistance in rendering a decision. See LCvR 7(f). 2 Plumbers at some point during the project. ECF No. 11-1 at 5; ECF 11-2 at 3. Although Gemma

never signed a contract agreeing to arbitrate with the Plumbers (or even hire the Plumbers), the

Plumbers argue that Gemma nevertheless agreed to arbitrate all subsequent labor disputes with

any union as to the Guernsey project under the JCUs executed with the Plumbers’ rival unions. In

that regard, four provisions in the JCUs are of note.

First, the JCUs “exclude work subcontracted by [Gemma] to others or self-performed by

[Gemma] and procured from sources other than [the Boilermakers or the Iron Workers], including

but not limited to work within the work jurisdiction of the [Boilermakers or Iron Workers].” ECF

No. 11-3 at 10, 20. In other words, the terms of the JCUs apply only to Gemma’s relationship with

the Iron Workers and Boilermakers and do not apply to Gemma’s relationship with any other

union.

Second, the JCUs contain an integration clause. That clause provides that the JCUs are

“the sole agreement[s] between [Gemma, the Boilermakers, and the Iron Workers], [and] the

employer shall not be bound by any other . . . agreements to which [the Boilermakers or the Iron

Workers] are [] party.” Id. at 11, 21. Accordingly, through this integration clause, Gemma has

agreed to bind itself only to the terms of the JCUs, and the terms of no other agreement are

incorporated into the JCUs unless otherwise stated in the JCUs.

Third, the JCUs include an arbitration clause. The clause provides that “[a]ll disputes over

the meaning of, and the rights and obligations contained in th[e] JCUs” shall, if necessary, be

resolved by an arbitrator “with the American Arbitration Association.” Id. at 14-15, 25-56. This

association is distinct from arbitration through the Plan.

Fourth and most saliently, the JCUs include an addendum entitled “JURISDICTIONAL

DISPUTES.” This addendum is the only portion of the JCUs that mention the Plan and its arbitral

3 provisions. First,

[a]ll jurisdictional disputes between or among the [Boilermakers and the Iron Workers] and other unions who have signed agreements with [Gemma] or any subcontractor governing the performance of work [assigned in the JCUs], and who have agreed to be bound to the procedures provided in [the Plan] shall be settled and adjusted according to [the Plan]. The assignments of [Gemma] or a subcontractor (where applicable) shall be followed until the dispute is resolved in accordance with the Plan. Decisions rendered under the plan shall be binding and conclusive on [the Boilermakers and Iron Workers] or other affected unions.

Id. at 17, 27 (emphasis added). The addendum also states that

“[n]othing herein shall affect the right of [Gemma] to determine the work jurisdiction of [employees or contractors sourced outside the Boilermakers and Ironworkers] who are not represented by a Union, and the Plan shall not be empowered to affect work assignments of such [employees or contractors sourced outside the Boilermakers and Ironworkers]. [Gemma] retains the sole right to control and assign the jurisdictional duties for all work.

Id. at 17, 27 (emphasis added). Together, these provisions explain what disputes must be settled

under the Plan and which parties are subject to the Plan’s arbitral decisions.

When Gemma refused to reassign the work to the Plumbers after informal demands, the

Plumbers instituted an arbitration action against Gemma under the Plan. Pet. ¶ 27. Two arbitral

decisions resulted. In the first, the arbitrator concluded that the Plan conferred no authority to

grant the disputed work to the Plumbers because Gemma never executed any agreement with the

Plumbers. ECF No. 11-3 at 38. The Plumbers complained to the Plan that the first arbitrator did

not issue their decision within the time required by the plan, and the Plan vacated the award and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
United Association of Journeymen and Apprentices of the Plumbing and Pipe Fitting Industry of the United States and Canada v. Gemma Power Systems, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-association-of-journeymen-and-apprentices-of-the-plumbing-and-pipe-dcd-2022.