Sierra Club v. Marsh

701 F. Supp. 886, 19 Envtl. L. Rep. (Envtl. Law Inst.) 20692, 1988 U.S. Dist. LEXIS 13531, 1988 WL 118046
CourtDistrict Court, D. Maine
DecidedNovember 7, 1988
DocketCiv. 88-0116-B
StatusPublished
Cited by9 cases

This text of 701 F. Supp. 886 (Sierra Club v. Marsh) is published on Counsel Stack Legal Research, covering District Court, D. Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sierra Club v. Marsh, 701 F. Supp. 886, 19 Envtl. L. Rep. (Envtl. Law Inst.) 20692, 1988 U.S. Dist. LEXIS 13531, 1988 WL 118046 (D. Me. 1988).

Opinion

MEMORANDUM DECISION ON MOTION FOR PRELIMINARY INJUNCTION

CYR, Chief Judge.

This is the third round of litigation over the proposed development of a marine dry cargo terminal on Sears Island in Penob-scot Bay. The plaintiffs, Sierra Club and two of its members, seek declaratory and injunctive relief suspending the permits recently issued for the Sears Island project by the United States Army Corps of Engineers [the Corps] and the United States Coast Guard [the Coast Guard], and enjoining funding of the project by the Federal Highway Administration [FHWA]. In addition to the federal defendants, plaintiffs join the Maine Department of Transportation [MDOT], the proponent of the project, as a defendant.

*890 I. BACKGROUND

Sears Island is an uninhabited, undeveloped, and mostly forested 940-acre island located in upper Penobscot Bay, near Searsport, Maine. The island is connected to the mainland by a gravel bar which is submerged except at low tide and is covered by no more than four feet of water at high tide. Pursuant to a Port Planning and Development Program established in 1976, MDOT targeted the Searsport area for potential development of a modern seaport facility capable of competing with new port facilities outside Maine. 1

The proposed MDOT Sears Island marine dry cargo terminal itself would involve the development of approximately 50 acres near the western shore of the island. 2 The overall project includes provisions for the development of a 160-acre industrial park adjacent to the terminal. The preferred design envisions a 27-acre marginal wharf with two ship berths, having the potential for future expansion to 35 acres and 6 berths. Access to the mainland would require construction of a 2.3 mile-long, two-lane highway, including a 1,200' causeway and a 1.5 mile railroad spur along the length of the gravel bar connecting the island and the mainland.

MDOT considered alternative sites for the proposed port, including two sites on nearby Mack Point, near the mainland end of the proposed Sears Island causeway. Unlike Sears Island, Mack Point is already 50% developed, and further development of Mack Point would require working around existing industrial and port facilities. MDOT rejected both of the alternative sites on Mack Point as impracticable in light of the overall project purposes. The configurations of the Mack Point alternatives and the preferred Sears Island site are depicted in Appendix A.

Plaintiff Sierra Club has commenced two previous actions relating to the proposed Sears Island port development. In Sierra Club v. Marsh, 769 F.2d 868, 877-78 (1st Cir.1985) (Sierra Club I), the First Circuit held that the federal defendants — the Corps and FHWA — erred in finding that the project would have no significant environmental impacts necessitating the preparation of an environmental impact statement [EIS] pursuant to the National Environmental Policy Act [NEPA], 42 U.S.C. § 4332. The First Circuit concluded that the combined impacts resulting from the construction of the causeway and the port (which the Corps and FHWA had addressed) and the likely industrial development which the port facility would attract (which was not adequately considered) were significant enough to require preparation of an EIS. Consequently, further construction and funding of the project were enjoined, but not before substantial clearing and grading had been done at the proposed Sears Island terminal site and approximately 303,000 cubic yards of dredged material (approximately 60% of the total required to complete the initial one-berth terminal called for in phase I of the proposed project) had been removed. See Final EIS, at iv.

In Sierra Club v. Secretary of Transportation, 779 F.2d 776 (1st Cir.1985) (Sierra Club II), the First Circuit held that the Coast Guard had acted arbitrarily and capriciously in issuing a permit under the General Bridge Act of 1946, 33 U.S.C. § 525(b), for construction of a “bridge” along the 1,200' gravel bar between Sears Island and the mainland. The court ruled that by including a 2-foot diameter pipe through the planned causeway MDOT had not transformed the “causeway,” for which *891 the permitting process is more searching, 3 into a “bridge.” Thus, the permit under the General Bridge Act was found to be invalid. The First Circuit expressed no opinion as to whether Sierra Club would have a private right of action to challenge a causeway permit issued by the Coast Guard under the proper statute, i.e., section 9 of the River and Harbors Appropriation Act of 1899, 83 U.S.C. § 401. 4

In response to these First Circuit decisions, the federal defendants commenced the preparation of an EIS. FHWA was designated the lead agency in the EIS process. See 40 C.F.R. §§ 1501.5 & 1508.16. Other federal agencies participating in the EIS process were funding agencies, such as the Economic Development Administration [EDA] and the Federal Rail Administration [FRA]; permitting agencies, such as the Corps and the Coast Guard; and environmental or resource agencies, such as the Environmental Protection Agency [EPA], the Fish and Wildlife Service [FWS], and the National Marine Fisheries Service [NMFS], FHWA delegated its responsibility for preparation of the EIS to MDOT, which in turn engaged two private consultants, Normandeau Associates, Inc., and Economic Research Associates. 5

Pursuant to 40 C.F.R. § 1507, FHWA published a notice of intent to prepare an EIS for the Sears Island project, see 50 Fed.Reg. 35400 (Sept. 4, 1985), and Nor-mandeau Associates prepared a “scoping” document preliminarily identifying the subject matter of the EIS. On December 5, 1985, a scoping meeting was held among all agencies participating in the EIS process. A second meeting was held on February 12, 1986, at which the participating agencies discussed the scope of the EIS treatment of the purpose and need of a cargo terminal, alternatives to the Sears Island site, the affected environment, the environmental consequences of alternatives, and mitigation measures.

A preliminary draft EIS [DEIS] was distributed among the cooperating agencies on April 23,1986, in preparation for an EIS progress report meeting on May 12, 1986, at which there was criticism of the MDOT decision to reject both Mack Point sites as impracticable alternative sites for the project. It was suggested that the Mack Point alternatives be carried through the full impact analysis, at the same level as the Sears Island site.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sierra Club v. Flowers
423 F. Supp. 2d 1273 (S.D. Florida, 2006)
Sierra Club v. Marsh
First Circuit, 1992
Club v. Marsh
772 F. Supp. 13 (D. Maine, 1991)
Sierra Club v. John O. Marsh, Jr., Etc.
907 F.2d 210 (First Circuit, 1990)
Flag Fables, Inc. v. Jean Ann's Country Flags & Crafts, Inc.
730 F. Supp. 1165 (D. Massachusetts, 1990)
Sierra Club v. Marsh
744 F. Supp. 352 (D. Maine, 1989)
Sierra Club v. John O. Marsh, Jr.
872 F.2d 497 (First Circuit, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
701 F. Supp. 886, 19 Envtl. L. Rep. (Envtl. Law Inst.) 20692, 1988 U.S. Dist. LEXIS 13531, 1988 WL 118046, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sierra-club-v-marsh-med-1988.