Sierra Club v. Flowers

423 F. Supp. 2d 1273, 62 ERC (BNA) 1265, 2006 U.S. Dist. LEXIS 12579, 2006 WL 760489
CourtDistrict Court, S.D. Florida
DecidedMarch 22, 2006
Docket0323427CIV
StatusPublished
Cited by11 cases

This text of 423 F. Supp. 2d 1273 (Sierra Club v. Flowers) is published on Counsel Stack Legal Research, covering District Court, S.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sierra Club v. Flowers, 423 F. Supp. 2d 1273, 62 ERC (BNA) 1265, 2006 U.S. Dist. LEXIS 12579, 2006 WL 760489 (S.D. Fla. 2006).

Opinion

ORDER ON MOTIONS FOR SUMMARY JUDGMENT

HOEVELER, Senior District Judge.

THIS CAUSE comes before the Court on the parties’ various motions for sum *1278 mary judgment. 1 This Court heard argument on October 22, 2004, and additional argument was heard on September 30, 2005. The following briefly summarizes the most salient facts of this case, all of which will be addressed in greater detail below.

In 1991 the limestone mining industry approached federal, state, and local government regulators with a sixty-year plan for mining in wetlands in southeastern Florida, in an area described by the industry as the “ “Lake Belt,” near Everglades National Park (“ENP”) and related water conservation areas in western Miami-Dade County. The mining plan included significant new areas of mining as well as continued mining in areas previously permitted, and required the destruction of tens of thousands of acres of wetlands located above the Biscayne Aquifer (the County’s sole source of drinking water) in order to reach the limestone rock below. The following year, the Florida Legislature established a Lake Belt committee to develop a plan that would “enhance the water supply for Dade County and the Everglades” as well as “maximize efficient recovery of limestone while promoting the social and economic welfare of the community and protecting the environment.” Fla. Stat. § 373.4149. Later that same year, in anticipation of new permit applications and requests to extend previously issued permits, the United States Army Corps of Engineers (“Corps”) announced its intention to prepare an Environmental Impact Statement (“EIS”) for limestone mining which could impact approximately 54,000 acres of wetlands by the year 2050 in northwest Dade County.” AR65. 2

Over the next several years a number of issues were raised for discussion and analysis by interagency groups and other committees, e.g., risks to protected species, extent of need for locally-produced limestone products, potential contamination of the Aquifer, and threats of additional inverse condemnation lawsuits (one of the mining companies, Florida Rock, had successfully sued the United States in the mid-1980s on a claim that the denial of permits for mining in this area was an unconstitutional taking of property, recovering $21 million for 1,560 acres 3 ). Analysis of these issues revealed that while the Lake Belt area contains large quantities of limestone, the mining would directly destroy wetlands, potentially contaminating millions of gallons of drinking water drawn daily from the Aquifer, and that the large *1279 deep pits which remain after mining would negatively affect groundwater seepage rates in and out of surrounding water areas, e.g., ENP; also, the remnant mining pits might compromise the larger program of Everglades restoration.

The Corps issued a final EIS in June 2000, AR614, which addressed the issuance of mining permits of fifty years each, for a total of 14,300 acres to be mined in the Lake Belt, including new and existing areas. The permit period later was reduced by the Corps to ten years, as an apparent compromise between the mining industry’s urgent demands that new permits (approx. 8,400 acres) be issued concurrently with extensions of soon-to-expire existing permits (approx. 5,900 acres), and the objections to the mining plan that were being raised by federal and state agencies, local government, private organizations, and individuals. 4 The Corps issued a Record of Decision (“ROD”) in April 2002, AR1028, collectively approving the new limestone mining permit applications and extending the term of the previously-issued permits, for a total of approximately 5,400 acres of mining to take place in ten years. 5 - The new permits had an initial three year review period, after which the permits could be modified, if necessary. 6

Plaintiffs allege that the Corps erred in issuing the ROD and awarding the permits 7 to members of the limestone mining industry to conduct mining activities for ten years on 5,400 acres without, inter alia, updating the EIS that had been issued two years earlier. Further, they allege that the United States Fish and Wildlife Service (“FWS”) failed in its duty to protect the wood stork, and other species whose habitats may be affected by the mining, by determining that the Corps’ actions were “not likely to adversely af- *1280 feet” those species — without FWS conducting its own full assessment of the situation. Plaintiffs have alleged violations of the Administrative Procedures Act (“APA”), 5 U.S.C. § 706; the Endangered Species Act (“ESA”), 16 U.S.C. § 1531 et seq.; the Clean Water Act (“CWA”), 33 U.S.C. § 1251 et seq.; and the National Environmental Policy Act (“NEPA”), 42 U.S.C. § 4321 et seq.

The Corps and FWS (“Federal Defendants”) argue that the permitting process was handled correctly, over a multiple year period, with the involvement and subsequent concurrence of all major federal, state, and local agencies, and that deference ultimately must be shown to the federal agencies. They offer as evidence of their deliberative process that they ultimately reduced the originally requested permit period from fifty years to ten years, required that the permitted activities be evaluated after the first three years, and also imposed additional conditions in response to concerns raised by objectors. The members of the limestone mining industry (“Industry Defendants”), who were permitted to intervene in this action because of their economic interests in the subject of this litigation, argue that the permits were issued legally, with sufficient analysis of environmental impacts, and that a failure to permit this mining would result in an improper restriction on private property interests.

PROCEDURAL BACKGROUND

Plaintiffs initially filed their Complaint on August 20, 2002, in the United States District Court for the District of Columbia. The Federal Defendants filed an Answer and moved to transfer the action to this district, and members of the limestone mining industry filed a request to intervene as defendants. 8 On August 4, 2003, the Federal Defendants’ motion to transfer was granted, and on December 30, 2003, this case was assigned to this Court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sierra Club v. Van Antwerp
709 F. Supp. 2d 1254 (S.D. Florida, 2009)
Sierra Club v. Van Antwerp
526 F.3d 1353 (Eleventh Circuit, 2008)
Miccosukee Tribe of Indians of Florida v. United States
528 F. Supp. 2d 1317 (S.D. Florida, 2007)
Sierra Club v. Strock
495 F. Supp. 2d 1188 (S.D. Florida, 2007)
BEECHWOOD RESTORATIVE CARE CENTER v. Thompson
494 F. Supp. 2d 181 (W.D. New York, 2007)
Sierra Club v. United States Army Corps of Engineers
464 F. Supp. 2d 1171 (M.D. Florida, 2006)
Miccosukee Tribe of Indians of Fla. v. United States
430 F. Supp. 2d 1328 (S.D. Florida, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
423 F. Supp. 2d 1273, 62 ERC (BNA) 1265, 2006 U.S. Dist. LEXIS 12579, 2006 WL 760489, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sierra-club-v-flowers-flsd-2006.