Sierra Club v. Marsh

744 F. Supp. 352, 1989 U.S. Dist. LEXIS 17235, 1989 WL 223103
District Court, D. Maine·Decided November 1, 1989·No. Civ. 88-0116-B·Published·Cited by 4 cases

Opinion

MEMORANDUM OPINION AND ORDER ON CROSS-MOTIONS FOR SUMMARY JUDGMENT ON NEPA CLAIMS

CYR, Chief Judge.

The plaintiffs, Sierra Club and two of its members, request declaratory and injunc-tive relief suspending federal permits issued for the construction of a marine dry cargo terminal on Sears Island in Penob-scot Bay. Plaintiffs contend that permits issued by the United States Army Corps of Engineers [the Corps] and by the United *354 States Coast Guard [the Coast Guard], as well as Federal Highway Administration [FHwA] funding, must be suspended due to failure to comply with the Clean Water Act [CWA], 33 U.S.C. § 1251 et seq., the National Environmental Policy Act [NEPA], 42 U.S.C. § 4321 et seq., and section 9 of the Rivers and Harbors Act of 1899, 33 U.S.C. § 401. The court now considers the cross-motions for summary judgment on the NEPA claims.

I. BACKGROUND

The Maine Department of Transportation [MDOT] proposal to develop a marine dry cargo terminal on Sears Island has been the subject of protracted litigation. 1 The court observed the most recent installment in the litigation on May 10, 1989, by granting plaintiffs’ motion for preliminary in-junctive relief on the basis of three of their NEPA claims. See Sierra Club v. Marsh, 714 F.Supp. 539 (D.Me.1989) [Sierra Club IV]. The court found a likelihood of irreparable injury from inadequate compliance with the NEPA requirements relating to the analysis of “secondary impacts,” the analysis of “reasonable alternatives,” and the preparation of a supplemental environmental impact statement [EIS]. See id. at 582-587. The court found that the balance of harms favored the plaintiffs and that the public interest would be better served by maintaining the status quo pending agency recourse to the NEPA process. Id. at 591— 93. The court enjoined the permitting, funding and construction of the project pending further order, or pending compliance by the FHwA and the Corps with

a) the NEPA requirement of an adequate evaluation of all reasonably foreseeable secondary impacts of developing a cargo terminal on Sears Island;
b) the NEPA requirement of evaluation of all reasonable alternatives to the proposed project; and
c) the NEPA requirement that all new information be assessed with a view to determining whether its environmental significance requires preparation of a supplemental EIS.

Order Amendment Preliminary Injunction, June 1, 1989, at 2.

On July 6, 1989, the court granted the federal defendants’ unopposed motion to supplement the record. The court now considers the cross-motions for summary judgment on the three NEPA claims in light of the supplemented record.

II. DISCUSSION

1. “Secondary Impact” Analysis

NEPA regulations require that an EIS discuss both the direct and indirect (or secondary) impacts of a proposed project. See 40 C.F.R. § 1502.16. Indirect impacts are those “caused by the action [that] are later in time or farther removed in distance [than the direct impacts], but are still reasonably foreseeable.” 2 Id. at § 1508.8 (emphasis added). Whether a particular impact is to be regarded as “definite enough to take into account, or too specu *355 lative to warrant consideration, reflects several different factors.” Sierra Club 1, 769 F.2d at 878. In determining whether an agency decision not to discuss particular impacts is “arbitrary and capricious,” 3 the court is to consider—

With what confidence can one say that the impacts are likely to occur? Can one describe them ‘now’ with sufficient specificity to make their consideration useful? If the decisionmaker does not take them into account ‘now,’ will the decisionmaker be able to take account of them before the agency is so firmly committed to the project that further environmental knowledge, as a practical matter, will prove irrelevant to the government’s decision?

Id. (citing Commonwealth of Massachusetts v. Watt, 716 F.2d 946, 952-53 (1st Cir.1983)).

The final EIS [FEIS] devotes 47 pages to an analysis of reasonably foreseeable secondary impacts of the Sears Island project. FEIS, Vol. I, at 4-108 — 4-154. The analysis is based on the assumption that the only reasonably foreseeable tenants of the planned industrial park are manufacturers of fabricated metal products, non-electrical machinery and equipment, electrical and electronic machinery and equipment, and transportation equipment. 4 See FEIS, Vol. I, at 4-109, 4-110. The FEIS assumes that these industries will have no significant air or water impacts. See id. at 4-117, 4-120. These industries were selected for secondary impact analysis because

the targeted industries have been proposed for attraction by both public officials and the property owners (and are, therefore, reasonably foreseeable), and would not likely occur on Sears Island or Mack Point without the proposed action (and would, therefore, be attributable to it).

Id. at 4-111.

Plaintiffs argue that the agency decision to restrict the secondary impact analysis to *356 these four target industries was “arbitrary and capricious,” because there is evidence in the administrative record that “heavy” industries, with significant air and/or water impacts, are foreseeable tenants of the industrial park. The court ruled that the record did not evidence FHwA consideration of the prospect that industries other than the “light-dry” type targeted in the Mallar Report might locate in the industrial park.

Although it is conceivable that a careful consideration of all available information could have enabled the FHwA rationally to conclude that the Mallar Report presented a logical basis for determining which industries were “reasonably foreseeable” and could be attributable to the Sears Island port project, the court cannot determine from the record that any such FHwA decision was “founded on a reasoned evaluation of the relevant information.” Oregon Natural Resources Council, 490 U.S. at-, 109 S.Ct. at 1865.

Free access — add to your briefcase to read the full text and ask questions with AI

Sierra Club v. Marsh, 744 F. Supp. 352, 1989 U.S. Dist. LEXIS 17235, 1989 WL 223103 (D. Me. 1989).

744 F. Supp. 352 (Sierra Club v. Marsh) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Northwest Bypass Group v. U.S. Army Corps of Engineers
552 F. Supp. 2d 97 (D. New Hampshire, 2008)
Hodges v. Abraham
253 F. Supp. 2d 846 (D. South Carolina, 2002)
Sierra Club v. Marsh
First Circuit, 1992