PER CURIAM:
Six environmental organizations object to the issuance by the U.S. Army Corps of Engineers of six individual permits allowing private landowners to clear and convert to agriculture approximately 5200 acres of bottomland hardwood wetlands. They also oppose the construction of the Sicily Island Area Levee Project (the Project), a federal flood control project to abate backwater flooding in a 75,000 acre area of Catahoula Parish, Louisiana, without an additional Environmental Impact Statement (EIS) to supplement the Corps’ 1981 EIS. As to the six individual permits, we agree with the district court that the Corps properly followed both the National Environmental Policy Act (NEPA), and the Environmental Protection Agency’s regulatory guidelines in making its determination. As to the construction of the Project, however, we hold that the Corps failed to give adequate consideration to the question of whether the 1981 EIS must be revised in light of our decision in Avoyelles III.1 Consequently, we vacate that part of the district court’s opinion which dealt with this issue and remand to the district court for the purposes of requiring the Corps to perform an adequate analysis of whether a supplemental EIS is required.
The district court opinion efficiently distilled a voluminous record and described in detail both the nature of the Sicily Island Project and the physical characteristics of the six tracts affected by the permit applications.2 We, therefore, do not attempt to repeat the factual background of this case.
I.
The six permits granted by the Corps authorize the agricultural conversion of 5200 acres of wetlands. For environmental protection purposes, such wetlands are denominated “special aquatic sites.”3 Both the Environmental Protection Agency’s Guidelines and the Corps of Engineers’ regulations treat all special aquatic sites as worthy of extra protection, and state as “[t]he guiding principle ... that degradation or destruction of special sites may [1047]*1047represent an irreversible loss of valuable aquatic resources.”4
Such heightened solicitude for wetlands is manifest in the regulations stating the considerations that must be taken into account when evaluating a proposed alteration to wetlands acreage. When a discharge of dredged or fill material is proposed, the Corps’ Guidelines prohibit issuance of a permit if there is a “practicable alternative that would have less adverse impact on the aquatic ecosystem____”5 A “practicable alternative,” in turn, is defined as one that is, “available and capable of being done after taking into consideration cost, existing technology, and logistics in light of overall project purposes.”6 With respect to wetlands, however, the Guidelines specify:
[wjhere the activity associated with a discharge which is proposed for a special aquatic site ... does not require access or proximity to or siting within the special aquatic site in question to fulfill the basic purpose (i.e. is not ‘water dependent’), practicable alternatives that do not involve special aquatic sites are presumed to be available, unless clearly demonstrated otherwise.7
“Thus, the guidelines couple a general presumption against all discharges into aquatic ecosystems with a specific presumption that practicable alternatives to the fill of wetlands exist.” 8
In each of the six permit-application proceedings, the Corps characterized the applicant’s basic purpose for the project as being, “to increase soybean production or to increase net return on assets owned by the company.”9 It is undisputed that soybean production is a non-water dependent activity. As shown above, this fact “necessitate[s] a more persuasive showing than otherwise concerning the lack of alternatives.” 10
The environmental protection organizations argue on appeal that the applicants failed to make the required showing, and that the Corps erroneously granted them permits by interpreting “practicable alternatives” to mean “profit-maximizing alternatives.” In addition, they contend that the Corps erred in viewing the alternatives with the applicants’ objectives in mind instead of with an eye towards environmental maintenance. Both arguments must be rejected.
The first contention is simply not borne out by the record. There is nothing in the Corps’ reports to show that profit-maximization was a consideration, let alone the primary factor in the alternatives analysis.11 The Corps did view the economic feasibility of alternatives, a permissible criterion under both the Environmental Protection Agency’s Guidelines and the stated objectives of the permit applicants. However, in granting several of the applications, the alternative selected by the Corps did not allow the applicant to clear the entire tract (the profit-maximizing position) as it had originally requested. Instead, the Corps carefully limited the clearing allowed under the permits so as to forbid land [1048]*1048clearance below certain elevations, require maintenance of uncleared buffer zones on each side of streams traversing the tracts, require turnrows to be seeded and maintained in suitable grass, and mandate the application of the Best Management Practices required by the Louisiana Department of Natural Resources.12 The corps thus chose alternatives that reduced both the applicants’ profit and the economic efficiency of their proposed operations in order to preserve other environmental values.
The environmental protection organizations’ second contention, that the alternatives may not be viewed with the applicant’s objectives in mind, is not substantiated by either case law or the applicable regulations. As the district court recognized, the Preamble to the Guidelines states, "... [w]e consider implicit that, to be practicable, an alternative must be capable of achieving the best purpose of the proposed activity.”13 In turn, the text of the Guidelines provides that an alternative is practicable if it is available and capable of being done after taking into account costs, existing technology and logistics in light of the overall project purposes.14 .Under these Guidelines, therefore, not only is it permissible for the Corps to consider the applicant’s objective; the Corps has a duty to take into account the objectives of the applicant’s project.15 Indeed, it would be bizarre if the Corps were to ignore the purpose for which the applicant seeks a permit and to substitute a purpose it deems more suitable.
The case law, although sparse, is in accord with our conclusion. In Hough v. Marsh, supra, residents of Edgartown, Massachusetts challenged a Corps permit authorizing the filling of a coastal tract to construct two private homes and a tennis court. The District Engineer had found that the project was not “water dependent,” and undertook the requisite examination to discover the existence of “practicable alternatives.” The Engineer defined the basic purpose of the project as “providing two homes and a tennis court.” 16
Free access — add to your briefcase to read the full text and ask questions with AI
PER CURIAM:
Six environmental organizations object to the issuance by the U.S. Army Corps of Engineers of six individual permits allowing private landowners to clear and convert to agriculture approximately 5200 acres of bottomland hardwood wetlands. They also oppose the construction of the Sicily Island Area Levee Project (the Project), a federal flood control project to abate backwater flooding in a 75,000 acre area of Catahoula Parish, Louisiana, without an additional Environmental Impact Statement (EIS) to supplement the Corps’ 1981 EIS. As to the six individual permits, we agree with the district court that the Corps properly followed both the National Environmental Policy Act (NEPA), and the Environmental Protection Agency’s regulatory guidelines in making its determination. As to the construction of the Project, however, we hold that the Corps failed to give adequate consideration to the question of whether the 1981 EIS must be revised in light of our decision in Avoyelles III.1 Consequently, we vacate that part of the district court’s opinion which dealt with this issue and remand to the district court for the purposes of requiring the Corps to perform an adequate analysis of whether a supplemental EIS is required.
The district court opinion efficiently distilled a voluminous record and described in detail both the nature of the Sicily Island Project and the physical characteristics of the six tracts affected by the permit applications.2 We, therefore, do not attempt to repeat the factual background of this case.
I.
The six permits granted by the Corps authorize the agricultural conversion of 5200 acres of wetlands. For environmental protection purposes, such wetlands are denominated “special aquatic sites.”3 Both the Environmental Protection Agency’s Guidelines and the Corps of Engineers’ regulations treat all special aquatic sites as worthy of extra protection, and state as “[t]he guiding principle ... that degradation or destruction of special sites may [1047]*1047represent an irreversible loss of valuable aquatic resources.”4
Such heightened solicitude for wetlands is manifest in the regulations stating the considerations that must be taken into account when evaluating a proposed alteration to wetlands acreage. When a discharge of dredged or fill material is proposed, the Corps’ Guidelines prohibit issuance of a permit if there is a “practicable alternative that would have less adverse impact on the aquatic ecosystem____”5 A “practicable alternative,” in turn, is defined as one that is, “available and capable of being done after taking into consideration cost, existing technology, and logistics in light of overall project purposes.”6 With respect to wetlands, however, the Guidelines specify:
[wjhere the activity associated with a discharge which is proposed for a special aquatic site ... does not require access or proximity to or siting within the special aquatic site in question to fulfill the basic purpose (i.e. is not ‘water dependent’), practicable alternatives that do not involve special aquatic sites are presumed to be available, unless clearly demonstrated otherwise.7
“Thus, the guidelines couple a general presumption against all discharges into aquatic ecosystems with a specific presumption that practicable alternatives to the fill of wetlands exist.” 8
In each of the six permit-application proceedings, the Corps characterized the applicant’s basic purpose for the project as being, “to increase soybean production or to increase net return on assets owned by the company.”9 It is undisputed that soybean production is a non-water dependent activity. As shown above, this fact “necessitate[s] a more persuasive showing than otherwise concerning the lack of alternatives.” 10
The environmental protection organizations argue on appeal that the applicants failed to make the required showing, and that the Corps erroneously granted them permits by interpreting “practicable alternatives” to mean “profit-maximizing alternatives.” In addition, they contend that the Corps erred in viewing the alternatives with the applicants’ objectives in mind instead of with an eye towards environmental maintenance. Both arguments must be rejected.
The first contention is simply not borne out by the record. There is nothing in the Corps’ reports to show that profit-maximization was a consideration, let alone the primary factor in the alternatives analysis.11 The Corps did view the economic feasibility of alternatives, a permissible criterion under both the Environmental Protection Agency’s Guidelines and the stated objectives of the permit applicants. However, in granting several of the applications, the alternative selected by the Corps did not allow the applicant to clear the entire tract (the profit-maximizing position) as it had originally requested. Instead, the Corps carefully limited the clearing allowed under the permits so as to forbid land [1048]*1048clearance below certain elevations, require maintenance of uncleared buffer zones on each side of streams traversing the tracts, require turnrows to be seeded and maintained in suitable grass, and mandate the application of the Best Management Practices required by the Louisiana Department of Natural Resources.12 The corps thus chose alternatives that reduced both the applicants’ profit and the economic efficiency of their proposed operations in order to preserve other environmental values.
The environmental protection organizations’ second contention, that the alternatives may not be viewed with the applicant’s objectives in mind, is not substantiated by either case law or the applicable regulations. As the district court recognized, the Preamble to the Guidelines states, "... [w]e consider implicit that, to be practicable, an alternative must be capable of achieving the best purpose of the proposed activity.”13 In turn, the text of the Guidelines provides that an alternative is practicable if it is available and capable of being done after taking into account costs, existing technology and logistics in light of the overall project purposes.14 .Under these Guidelines, therefore, not only is it permissible for the Corps to consider the applicant’s objective; the Corps has a duty to take into account the objectives of the applicant’s project.15 Indeed, it would be bizarre if the Corps were to ignore the purpose for which the applicant seeks a permit and to substitute a purpose it deems more suitable.
The case law, although sparse, is in accord with our conclusion. In Hough v. Marsh, supra, residents of Edgartown, Massachusetts challenged a Corps permit authorizing the filling of a coastal tract to construct two private homes and a tennis court. The District Engineer had found that the project was not “water dependent,” and undertook the requisite examination to discover the existence of “practicable alternatives.” The Engineer defined the basic purpose of the project as “providing two homes and a tennis court.” 16 Although the district court remanded for the landowners to demonstrate more clearly that no practicable alternatives to the proposed fill existed, the court did not question the Engineer’s formulation of the project’s objective, and did not suggest that the alternatives were not considered from the proper perspective.17
The district court’s findings that the Corps properly analyzed all six permit applications and correctly decided to grant permission to clear the tracts for agricultural use is amply supported by the record. Nothing in it convinces us that the Corps’ actions were arbitrary, capricious, or otherwise not in accordance with law, the sole standards by which we review such actions.18
II.
The Sicily Island Levee Project is a federally funded agricultural flood control and drainage plan designed to reduce the frequency and duration of backwater flooding throughout the 75,000 acre project area by the use of backwater levees and other drainage works.
[1049]*1049The Corps’ final EIS on the Project was submitted in 1981. The environmental protection organizations argue that the Environmental Protection Agency failed to perform a mandatory duty imposed by the Clean Air Act19 to review and comment on this final EIS. The district court did not address this claim in its opinion, but it was asserted in the plaintiffs’ amended complaint, and is properly before us.20
The EPA did comment on a 1978 draft EIS, the final form of which was released in 1979. The environmental protection organizations do not challenge the sufficiency of this EIS, nor do they contend that the Environmental Protection Agency’s comments were inadequate or did not fulfill their statutory purpose. Instead, they assert that the Agency should have reviewed and commented on the 1981 revised EIS, which included data concerning the establishment of the Tensas National Wildlife Refuge. The 1981 EIS specifically adopted the prior EIS statement of the environmental impact of the levee project.21 The issue narrows, therefore, to whether the EPA was required to review the 1981 EIS after it had already commented on the 1978 EIS.
The ■ answer must be no. There is no indication that the Environmental Protection Agency found the 1978 draft EIS to be “unsatisfactory from the standpoint of public health or welfare or environmental quality.”22 If it had, it would have published this determination and referred the matter to the Council on Environmental Quality.23 There is an indication that the Agency thought the draft was “inadequate,” but such a finding is obviously not the same as “unsatisfactory,” and did not require any further EPA action. The EPA had fully reviewed the environmental impact of the levee project in 1978, and the Agency’s silence on the statement’s subsequent incorporation into a revised document concerning the same project should be construed as showing the Agency’s continued approval.24
III.
Finally, the environmental protection organizations contend that the Corps erred in not submitting a supplemental EIS on the Project. To understand this objection to the Project, we must briefly describe the preparatory work performed by the Corps on the final EIS, as well as the Avoyelles litigation25 which concerned acreage similar to that affected by the Project.
The Corps’ final EIS on the Project noted that, of the 75,000 acres involved, 21,100 acres are bottomland hardwood forests, and of these, 1,357 acres are classified as wetlands. The Corps surveyed the property owners of the 21,100 acres, and discovered that 82%, or 17,300 acres, would be cleared even if the Project were not under[1050]*1050taken.26 On the basis of this survey, the Corps concluded that no adverse impact on the functional ecological values of the 17,-300 acres could be attributed to the Project because conversion of this property to agriculture was not in any way dependent on the Project.
The Avoyelles litigation concerned the Lake Long Tract which contained approximately 20,000 acres in Avoyelles Parish, Louisiana. The owners had decided that the land could be put to agricultural use, and had begun a large-scale program of deforestation. This program was halted, however, first by order of the Corps pending a wetlands determination, and then by a citizens’ suit seeking declaratory and in-junctive relief against the owners’ land-clearing activities.
After a bifurcated trial, the district court held that over ninety percent of the Lake Long Tract was wetlands,27 and that a permit from the Corps was required for the landclearing activities on that acreage.28 On appeal, the Fifth Circuit agreed that a private landowner’s clearing of wetlands for agricultural use is subject to the permit requirements of the Corps of Engineers under Section 404 of the Clean Water Act.29 The district court’s wetlands determination was set aside, however, and the Environmental Protection Agency’s determination was reinstated.30
The environmental protection organizations argue in this case that the 1981 final EIS is insufficient because it did not disclose or assess the environmental impacts associated with the loss of the acreage that the Corps assumed would be cleared if the Project were not undertaken. They contend, correctly, that the effect of Avoyelles III is to subject this acreage to the requirements of the Corps’ permit application process. The Corps’ initial assumption that 82% of the forested acres would be cleared regardless of the project, therefore, is no longer tenable, as the Corps is now able to “control” how much land can be cleared. They urge us to find that the district court erred in holding that the Corps was not required to supplement its 1981 final EIS in the light of the decision in Avoyelles III.
A.
No specific statutory requirement ordains the supplementation of an EIS. The Corps’ regulations, however, dictate that “[a] Supplement to the draft or final EIS on file will be prepared whenever significant impacts resulting from changes in the proposed plan or new significant impact information, criteria or circumstances relevant to environmental considerations impact on the recommended plan or proposed action____”31 Similarly, the Council on Environment Quality’s regulations require an agency to supplement an EIS if:
(i) The Agency makes substantial changes in the proposed action that are relevant to environmental concerns; or
(ii) There are significant new circumstances or information relevant to environmental concerns and bearing on the proposed action or its impacts.32
The district court held that, under these regulations, “[t]he decision in Avoyelles was not a ‘significant new circumstance or information’ which required the preparation of an additional EIS” because “[n]o new scientific or technical information was revealed which indicated that the project might have environmental effects which differed from those analyzed in the original EIS.”33 In effect, because the opinion contained no data that is explicitly environ[1051]*1051mental, the district court found that there would be no point in requiring a supplemental EIS that merely would “overlook the same environmental panorama.”34
This is an unduly restrictive interpretation of the Corps’ regulations. As recently explained by the Seventh Circuit in Wisconsin v. Weinberger;35 “The principal factor an agency should consider in exercising its discretion whether to supplement an existing EIS because of new information is the extent to which the new information presents a picture of the likely environmental consequences associated with the proposed action not envisioned by the original EIS.”36 The issue is not whether the new information is directly environmental but whether, whatever its nature, it “raises new concerns of sufficient gravity such that another, formal in-depth look at the environmental consequences of the proposed action is necessary.”37 That is, whether it “provides a seriously different picture of the environmental landscape such that another hard look is necessary.” 38
The focus of the inquiry is not limited solely to the scientific or technical aspects of the new information. Instead, the new information must be evaluated in terms of the likely environmental consequences that follow from the subsequent data. Even if the new information is not technological, therefore, if it “presents a seriously different picture of the environmental impact of the proposed project from what was previously envisioned,”39 it is significant new information and is sufficient to require an agency to supplement an original EIS.40
B.
Because we reject the district court’s conclusion that Avoyelles III was not the kind of new information that could warrant a supplemental EIS, we turn to the question of whether Avoyelles III does in fact warrant a supplemental EIS. We hold that the Corps’ decision not to file a supplemental EIS was unreasonable, since the plaintiffs raised a substantial environmental issue concerning approximately 40% of the forested areas within the project area. Although the Corps need not necessarily prepare a supplemental EIS, it must reconsider its assumption that these acres will be cleared regardless of the Project. If the Corps determines that there is a reasonable possibility that a significant number of these acres will not be cleared except for the Project, and that therefore the Project may have significant additional impacts not considered in the final EIS, then the Corps must prepare a supplemental EIS.
In determining whether a supplemental EIS is required, the legal standard is essentially the same as the standard for determining the need for an original EIS.41 If, as a result of new circumstances, the project may have a “significant” impact upon the environment that was not considered in the original EIS, then a supplemental EIS is required.42 “It is the initial responsibility of the Corps to apply this standard and decide whether or not a supplemental EIS is necessary. If a party affected by that decision challenges it in [1052]*1052court and raises a ‘substantial environmental issue/ the reviewing court should uphold the agency’s decision only if it is reasonable, rather than use the deferential ‘substantial evidence’ standard.”43
Under Marsh, although the Corps has the initial responsibility of deciding whether a supplemental EIS is necessary, a party challenging the Corps’ decision not to file a supplemental EIS has two burdens: First, it must raise a “substantial environmental issue.”44 NEPA does not require that an agency consider the import of any new circumstance, however small. In order to warrant a supplemental EIS, the new circumstance must “present a seriously different picture of the environmental impact of the proposed project from what was previously envisioned.”45 Second, the plaintiff must show that, with respect to this substantial environmental issue, the Corps did not act reasonably. “The standard of judicial review is whether the agency decision not to develop an impact statement is reasonable and made objectively and in good faith on a reviewable environmental record. If the decision is reasonable, ‘the determination must be upheld.’ ”46
In our view, the environmental protection organizations met both of these ■ burdens. First, they raised a substantial environmental issue concerning the effect of the Project on 17,300 acres of bottomland hardwood forests. In its original EIS, the Corps did not consider the environmental impacts of the Project on this area because it assumed that the land would be cleared even if the Project were not undertaken. It reasoned that since the area would be cleared anyway, the Project would not cause any additional adverse impacts.
As a result of Avoyelles III, however, these 17,300 acres of forestland might not be cleared. Under Avoyelles III, the land may be cleared only if the proposed clearances meet the requirements of the Section 404 permit process.47 The Corps has never even claimed to have considered whether, under Avoyelles III, the land qualifies for clearance. Since it has never been determined whether or not the planned clearances do meet the requirements of Section 404, it is an open question whether this land will actually be cleared. If the land is not cleared, then it is also an open question whether or not the Project will have adverse impacts on the area. Thus far, the Corps has avoided taking any look at all at the impacts of the Project on this area, let alone a hard look.
In order to raise a substantial environmental issue, a party need not show that the proposed project will have significant adverse impacts that the Corps has not considered. It must show only that the project may have such impacts. “[I]f the court finds that the project may cause a significant degradation of some human environmental factor ..., the court should require the filing of an impact statement or grant ... such other equitable relief as it deems appropriate.”48
On a previous occasion, we noted that “significant” is “a chameleon-like word that takes its functional meaning from its [1053]*1053context.”49 Here, we have no doubt that the potential effect of the Project on 17,300 acres of forest is “significant.” This area constitutes 82% of the total amount of forest affected by the Project. Although there was evidence in the record that 9,000 of these acres have already been cleared, even if only 8,000 acres of uncleared forest remain, this is still more than twice the number of acres of forest that were the subject of the Corps’ original EIS. Since the Corps believed that the potential impacts of the Project on 3,800 acres of forest were sufficient to warrant an EIS, we assume that the potential impact of the Project on 8,000 additional acres of forest is sufficient to warrant a supplemental EIS.50
Second, we find that the environmental protection organizations not only met their burden of raising a substantial environmental issue; they also demonstrated that the Corps acted unreasonably with respect to that issue. The Corps did not consider the impact of the Project on the 17,300 acres of forest in question because it assumed that this land would be cleared regardless of the Project. It based this assumption on a survey of landowners within the project area which showed that the owners of 17,-300 acres of forested land planned to clear their land even if the Project was not undertaken.
As a result of Avoyelles III, however, this basis has been undermined. Under Avoyelles III, the land in question cannot be cleared simply if the landowners want to. If the proposed clearances do not meet the requirements of Section 404, then the land may not be cleared regardless of what the landowners desire.
Avoyelles III, therefore, is clearly relevant to the accuracy of the Corps’ assumption that the land in question will be cleared regardless of the Project. Despite this, the Corps did not undertake any reevaluation of its assumption. Instead, it merely claimed that Avoyelles III was not the kind of new information that could warrant a supplemental EIS. Given the relevance of Avoyelles III to the question of whether the 17,300 acres will be cleared, the Corps’ failure to consider the effect of that decision was unreasonable.
Finally, we consider what remedy is appropriate in light of the Corps’ unreasonable action. We hold that while the Corps need not necessarily prepare a supplemental EIS, it must at least reconsider its assumption that the 17,300 acres will be cleared regardless of the Project. If the Corps is to adhere to this assumption, it must show that Section 404 permits will be granted to clear most or all of the 17,300 acres. If, on the other hand, the Corps determines that there is a reasonable possibility that a significant amount of land will not receive Section 404 permits, and that the Project may adversely affect this land, then the Corps must prepare a supplemental EIS to consider the effects of the Project on the uncleared land.51 At this stage, we do not order a supplemental EIS because the question of whether the Project might have significant adverse impacts on the 17,300 acres is still an open one.52 Thus far, the Corps has not analyzed this issue in light of Avoyelles III.
[1054]*1054In remanding to the Corps for further consideration, we reaffirm the principle that an EIS is more than a tissue of bare assumptions. If an assumption is to play a critical role in an EIS, it must, at the very least, be well-founded. The Corps cannot avoid the strictures of NEPA by simply assuming away potential problems.
AFFIRMED IN PART AND VACATED IN PART AND REMANDED.