Sierra Club v. John O. Marsh, Jr.

872 F.2d 497, 19 Envtl. L. Rep. (Envtl. Law Inst.) 20931, 29 ERC (BNA) 1472, 1989 U.S. App. LEXIS 4292, 1989 WL 28638
CourtCourt of Appeals for the First Circuit
DecidedMarch 31, 1989
Docket88-2049
StatusPublished
Cited by130 cases

This text of 872 F.2d 497 (Sierra Club v. John O. Marsh, Jr.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sierra Club v. John O. Marsh, Jr., 872 F.2d 497, 19 Envtl. L. Rep. (Envtl. Law Inst.) 20931, 29 ERC (BNA) 1472, 1989 U.S. App. LEXIS 4292, 1989 WL 28638 (1st Cir. 1989).

Opinion

BREYER, Circuit Judge.

In Commonwealth of Massachusetts v. Watt, 716 F.2d 946 (1st Cir.1983), we said that the National Environmental Policy Act (“NEPA”), 42 U.S.C. § 4321 et seq. (1982 & Supp. IV 1986), seeks to create a particular bureaucratic decisionmaking process, a process whereby administrators make important decisions with an informed awareness of how the decision might significantly affect the environment. We wrote that, if any such decision is made without the information that NEPA seeks to put before the decisionmaker, the harm that NEPA seeks to prevent occurs. Watt, 716 F.2d at 952. And we held that courts are to take account of that kind of harm when they consider whether to enjoin governmental actions that plaintiffs claim violate NEPA. Id. at 952-53. We now consider whether the Supreme Court, in Amoco Production Co. v. Village of Gambell, 480 U.S. 531, 107 S.Ct. 1396, 94 L.Ed.2d 542 (1987), over *498 ruled this holding. We conclude that the Court did not overrule or significantly modify Watt, and we therefore remand this case to the district court, which ruled to the contrary.

I. Background

This case involves the State of Maine’s efforts to build a new six-berth marine dry cargo terminal at Searsport, one of the busiest ports in Maine. The Maine Department of Transportation (“MDOT”) wants to build the terminal on Sears Island, a 940-acre, uninhabited, undeveloped piece of land directly opposite Mack Point, the site of a present two-berth terminal. (See Appendix A for a map.)

In a previous case, we noted that the Sears Island project would not only require Maine to dredge the channel, clear the island and build a causeway connecting the island to the mainland (for a highway and a railroad spur), but it would also lead to considerable secondary development on the island; hence NEPA required the Federal Highway Administration (“FHWA”), which would fund much of the project, to prepare an Environmental Impact Statement (“EIS”). Sierra Club v. Marsh, 769 F.2d 868 (1st Cir.1985) (Sierra Club I). See also Sierra Club v. Secretary of Transportation, 779 F.2d 776 (1st Cir.1985) (Sierra Club II) (holding that the physical mainland link was a “causeway,” not a “bridge,” and therefore that it required appropriate “causeway” permits).

Subsequently, MDOT secured financial backing from the Federal Highway Administration and MDOT and FHWA together hired a consultant, prepared a Draft EIS, obtained public comments from both the public and governmental agencies, adopted a Final EIS, and decided to proceed with the Sears Island project. They then obtained the necessary permits from the U.S. Coast Guard and the U.S. Army Corps of Engineers, both of which adopted the findings of the Final EIS.

After MDOT and the FHWA received permits allowing them to proceed with the Sears Island project, the Sierra Club returned to federal court and began the present action. The Sierra Club, objecting to the Sears Island development (the option that the Draft EIS and the Final EIS favored), says that the Final EIS did not adequately evaluate the environmental effects of choosing the Sears Island site, nor did it adequately explore other alternatives (such as expanding the Mack Point terminal, or no new development at all) less harmful to the environment. Three federal “resource” agencies, the U.S. Environmental Protection Agency (“EPA”) (which hired its own consultant to review this matter), the U.S. Fish and Wildlife Service (“FWS”), and the National Marine Fisheries Service (“NMFS”), agree with the Sierra Club’s overall assessment.

In particular, the Sierra Club argued that the Final EIS did not respond adequately to the comments that it, and the resource agencies, had made on the Draft EIS. The Draft, for example, had given several reasons for preferring Sears Island to Mack Point: a six berth terminal means more jobs; there is room at Sears Island for six berths; there is room at Mack Point for only two berths; the cost of acquiring property at Mack Point is greater; the tax revenues would be greater from new development at Sears Island than from modifying Mack Point; and new berths at Mack Point would require more dredging and more tug boats than would Sears Island. The Sierra Club and the resource agencies had commented, in response, that the economy will demand no more than two berths through the year 2010 (so that six berths are not now necessary); the comparative costs and tax advantages favor Sears Island less than the Draft EIS suggested; no extra dredging or tug boats would be needed at Mack Point; and the environmental harms would be greater at Sears Island than they would be at Mack Point and greater than the Draft EIS estimated them to be. The Sierra Club argued in court that the Final EIS did not adequately deal with these and other comments. In particular, it said that the Final EIS exaggerated the economic need for the project (especially in light of an EPA consultant’s report, which criticized the developers’ consultant’s methods and conclusions and *499 which found that only two berths would be necessary for a considerable time); that the Final EIS failed to consider important, less environmentally harmful alternatives (such as a terminal limited to two berths); and that it did not adequately consider secondary development. Furthermore, said the Sierra Club, the Final EIS did not take adequate account of new information discovered after it was published (such as the fact that the Sears Island terminal will require clearing 124 acres of wild land, not 50 acres as the Final EIS had estimated). The Sierra Club also claimed that neither the FHWA nor the Army evaluated the Final EIS properly before reaching their decisions. And the Sierra Club argued several technical failings, such as undisclosed potential conflicts of interest among consultants and improper incorporation of documents by reference.

The Sierra Club asked the district court to enjoin both the federal and state agencies from continuing to build the causeway or otherwise work upon the Sears Island project while the court considered the merits of its various, rather complex objections.

The federal district court denied the Sierra Club’s request for a preliminary injunction. Sierra Club v. Marsh, 701 F.Supp. 886 (D.Me.1988). In doing so, the court referred to this Circuit’s well-known four-part test for the issuance of a preliminary injunction: Will failure to issue the injunction cause the plaintiff “irreparable harm”? Does the “balance of harms” favor the plaintiff or defendant? Can plaintiff show a “likelihood of success” on the merits? Will granting the relief harm the public interest? Planned Parenthood League v. Bellotti,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

US Inventor v. Vidal
Fifth Circuit, 2022
American Tunaboat Association v. Ross
District of Columbia, 2019
Am. Tunaboat Ass'n v. Ross
391 F. Supp. 3d 98 (D.C. Circuit, 2019)
Natural Resources Defense Council, Inc. v. United States
331 F. Supp. 3d 1338 (Court of International Trade, 2018)
Nat'l Parks Conservation Ass'n v. Semonite
282 F. Supp. 3d 284 (D.C. Circuit, 2017)
Sierra Club v. United States Army Corps of Engineers
990 F. Supp. 2d 9 (District of Columbia, 2013)
Grunewald v. Jarvis
930 F. Supp. 2d 73 (District of Columbia, 2013)
Dartmouth-Hitchcock v. NHDHHS
2012 DNH 032 (D. New Hampshire, 2012)
Sierra Club v. United States Army Corps of Engineers
645 F.3d 978 (Eighth Circuit, 2011)
Center for Food Safety v. Vilsack
753 F. Supp. 2d 1051 (N.D. California, 2010)
CITIZENS AGAINST RUINING OUR ENVT. v. Klein
747 F. Supp. 2d 1234 (D. Colorado, 2010)
United States v. Commonwealth of Mass.
724 F. Supp. 2d 170 (D. Massachusetts, 2010)
Food & Water Watch, Inc. v. U.S. Army Corps of Engineers
570 F. Supp. 2d 177 (D. Massachusetts, 2008)
CLF v. Fed'l Highway, NHDOT
2007 DNH 106 (D. New Hampshire, 2007)
Center for Biological Diversity v. Brennan
571 F. Supp. 2d 1105 (N.D. California, 2007)
Sierra Club v. Strock
495 F. Supp. 2d 1188 (S.D. Florida, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
872 F.2d 497, 19 Envtl. L. Rep. (Envtl. Law Inst.) 20931, 29 ERC (BNA) 1472, 1989 U.S. App. LEXIS 4292, 1989 WL 28638, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sierra-club-v-john-o-marsh-jr-ca1-1989.