CLF v. Fed'l Highway, NHDOT
This text of 2007 DNH 106 (CLF v. Fed'l Highway, NHDOT) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
CLF v. Fed'1 Highway, NHDOT CV—06—45—PB 08/30/07 P
UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE
Conservation Law Foundation
v. Case No. 06-cv-45-PB Opinion No. 2007 DNH 106 Federal Highway Administration and New Hampshire Department of Transportation
MEMORANDUM AND ORDER
Nearly twenty years ago, the New Hampshire Department of
Transportation ("NHDOT") began to evaluate proposals to address
traffic congestion and safety concerns associated with the 19.8-
mile section of Interstate 93 ("1-93") between Salem and
Manchester, New Hampshire. The project stalled for several years
while NHDOT refined its traffic projection methodology but
recommenced in 1999. In April 2004, the Federal Highway
Administration ("FHWA") and NHDOT issued a Final Environmental
Impact Statement proposing, among other things, to add four
lanes--two in each direction--to 1-93 between Salem and
Manchester. On June 28, 2005, FHWA issued a Record of Decision
approving the proposed alternative. The Conservation Law Foundation ("CLF") challenges the
Record of Decision, contending that NHDOT and FHWA violated the
National Environmental Policy Act, 42 U.S.C. § 4321 et seq. and
the Federal-Aid Highway Act, 23 U.S.C. § 101 et seq. The parties
agree that the case can be resolved on their cross-motions for
summary judgment.
I. LEGAL OVERVIEW
A. National Environmental Policy Act
The National Environmental Policy Act ("NEPA") is implicated
when an agency proposes "a major Federal action[] significantly
affecting the quality of the human environment."1 42 U.S.C. §
4332(2)(C). NEPA requires an agency contemplating a major
federal action to take a "hard look" at alternatives and
environmental consequences before undertaking the action.2
1 Regulations promulgated by the Council on Environmental Quality ("CEQ") provide guidance for the implementation of NEPA. See 40 C.F.R. §§ 1500-1518. In addition, FHWA has promulgated its own NEPA regulations. See 23 C.F.R. Part 771. Both sets of regulations are entitled to substantial deference. Andrus v. Sierra Club. 442 U.S. 347, 358 (1979); Conservation Law Found, v. Fed. Highway Admin.. 24 F.3d 1465, 1480 (1st Cir. 1994).
2 The federal agency must also cooperate with state and local agencies to reduce duplication between NEPA and state and local requirements. 40 C.F.R. § 1506.2(b)-(c ). Such cooperation may include: joint planning processes, joint environmental
-2- Baltimore Gas & Elec. Co. v. Natural Resources Defense Council,
Inc., 462 U.S. 87, 97 (1983). To this end, the agency ordinarily
must prepare an Environmental Impact Statement ("EIS") that
includes, among other things, a rigorous, objective evaluation of
all reasonable alternatives to the proposed action--including the
alternative of no action--and, for alternatives which were
eliminated from detailed study, a brief discussion of why they
were eliminated. 40 C.F.R. § 1502.14. The EIS must also include
a discussion of the direct and indirect environmental effects of
the proposed action and its alternatives. 40 C.F.R. § 1502.16.
Direct effects are effects caused by the action that occur at the
same time and place. 40 C.F.R. § 1508.8. Indirect effects are
effects "which were caused by the action and are later in time or
farther removed in distance, but are still reasonably
foreseeable." 40 C.F.R. § 1508.8.
research and studies, joint public hearings, joint environmental assessments, and joint environmental impact statements. 40 C.F.R. § 1506.2(b)-(c ). It appears from the Administrative Record that FHWA and NHDOT cooperated with respect to all of these processes. Thus, for purposes of simplicity, in the sections below dealing with such cooperative actions, I use the collective term "Defendants" when referring to FHWA and NHDOT even though FHWA alone is ultimately responsible for the issuance of the Record of Decision.
-3- Indirect effects "include growth-inducing effects and other
effects related to induced changes in the pattern of land use,
population density or growth rate, and related effects on air and
water and other natural systems, including ecosystems." 40
C.F.R. § 1508.8. Agencies must address a proposed action's
indirect effects in an EIS if they are reasonably foreseeable,3
sufficiently definite,4 and significant.5 Dubois. 102 F.3d at
3 "Reasonable foreseeability means that 'the impact is sufficiently likely to occur that a person of ordinary prudence would take it into account in reaching a decision.'" Dubois v. U.S. Dep't of Aqric., 102 F.3d 1273, 1286 (1st Cir. 1996) (quoting Sierra Club v. Marsh. 976 F.2d 763, 767 (1st Cir. 1992) ) .
4 Whether an indirect effect is too speculative to require analysis depends on several factors:
With what confidence can one say that the impacts are likely to occur? Can one describe them "now" with sufficient specificity to make their consideration useful? If the decisionmaker does not take into account "now," will the decisionmaker be able to take account of them before the agency is so firmly committed to the project that further environmental knowledge as a practical matter will prove irrelevant to the government's decision?
Sierra Club. 769 F.2d at 877-78.
5 An indirect effect's significance depends on both its "context" and "intensity." 40 C.F.R. § 1508.27. Among the factors that may be relevant to a significance determination are: (1) "[t]he degree to which the proposed action affects public health or safety;" (2) "[t]he degree to which the possible effects on the human environment are likely to be highly
-4- 1286; Sierra Club, 769 F.2d at 878 (citation omitted).
Before work on an EIS begins, the federal agency proposing
the project must engage in a "scoping" process. 40 C.F.R. §
1501.7. To initiate the process, the agency invites the
participation of other federal, state, or local agencies, and
other interested parties, including those who might object to the
Free access — add to your briefcase to read the full text and ask questions with AI
CLF v. Fed'1 Highway, NHDOT CV—06—45—PB 08/30/07 P
UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE
Conservation Law Foundation
v. Case No. 06-cv-45-PB Opinion No. 2007 DNH 106 Federal Highway Administration and New Hampshire Department of Transportation
MEMORANDUM AND ORDER
Nearly twenty years ago, the New Hampshire Department of
Transportation ("NHDOT") began to evaluate proposals to address
traffic congestion and safety concerns associated with the 19.8-
mile section of Interstate 93 ("1-93") between Salem and
Manchester, New Hampshire. The project stalled for several years
while NHDOT refined its traffic projection methodology but
recommenced in 1999. In April 2004, the Federal Highway
Administration ("FHWA") and NHDOT issued a Final Environmental
Impact Statement proposing, among other things, to add four
lanes--two in each direction--to 1-93 between Salem and
Manchester. On June 28, 2005, FHWA issued a Record of Decision
approving the proposed alternative. The Conservation Law Foundation ("CLF") challenges the
Record of Decision, contending that NHDOT and FHWA violated the
National Environmental Policy Act, 42 U.S.C. § 4321 et seq. and
the Federal-Aid Highway Act, 23 U.S.C. § 101 et seq. The parties
agree that the case can be resolved on their cross-motions for
summary judgment.
I. LEGAL OVERVIEW
A. National Environmental Policy Act
The National Environmental Policy Act ("NEPA") is implicated
when an agency proposes "a major Federal action[] significantly
affecting the quality of the human environment."1 42 U.S.C. §
4332(2)(C). NEPA requires an agency contemplating a major
federal action to take a "hard look" at alternatives and
environmental consequences before undertaking the action.2
1 Regulations promulgated by the Council on Environmental Quality ("CEQ") provide guidance for the implementation of NEPA. See 40 C.F.R. §§ 1500-1518. In addition, FHWA has promulgated its own NEPA regulations. See 23 C.F.R. Part 771. Both sets of regulations are entitled to substantial deference. Andrus v. Sierra Club. 442 U.S. 347, 358 (1979); Conservation Law Found, v. Fed. Highway Admin.. 24 F.3d 1465, 1480 (1st Cir. 1994).
2 The federal agency must also cooperate with state and local agencies to reduce duplication between NEPA and state and local requirements. 40 C.F.R. § 1506.2(b)-(c ). Such cooperation may include: joint planning processes, joint environmental
-2- Baltimore Gas & Elec. Co. v. Natural Resources Defense Council,
Inc., 462 U.S. 87, 97 (1983). To this end, the agency ordinarily
must prepare an Environmental Impact Statement ("EIS") that
includes, among other things, a rigorous, objective evaluation of
all reasonable alternatives to the proposed action--including the
alternative of no action--and, for alternatives which were
eliminated from detailed study, a brief discussion of why they
were eliminated. 40 C.F.R. § 1502.14. The EIS must also include
a discussion of the direct and indirect environmental effects of
the proposed action and its alternatives. 40 C.F.R. § 1502.16.
Direct effects are effects caused by the action that occur at the
same time and place. 40 C.F.R. § 1508.8. Indirect effects are
effects "which were caused by the action and are later in time or
farther removed in distance, but are still reasonably
foreseeable." 40 C.F.R. § 1508.8.
research and studies, joint public hearings, joint environmental assessments, and joint environmental impact statements. 40 C.F.R. § 1506.2(b)-(c ). It appears from the Administrative Record that FHWA and NHDOT cooperated with respect to all of these processes. Thus, for purposes of simplicity, in the sections below dealing with such cooperative actions, I use the collective term "Defendants" when referring to FHWA and NHDOT even though FHWA alone is ultimately responsible for the issuance of the Record of Decision.
-3- Indirect effects "include growth-inducing effects and other
effects related to induced changes in the pattern of land use,
population density or growth rate, and related effects on air and
water and other natural systems, including ecosystems." 40
C.F.R. § 1508.8. Agencies must address a proposed action's
indirect effects in an EIS if they are reasonably foreseeable,3
sufficiently definite,4 and significant.5 Dubois. 102 F.3d at
3 "Reasonable foreseeability means that 'the impact is sufficiently likely to occur that a person of ordinary prudence would take it into account in reaching a decision.'" Dubois v. U.S. Dep't of Aqric., 102 F.3d 1273, 1286 (1st Cir. 1996) (quoting Sierra Club v. Marsh. 976 F.2d 763, 767 (1st Cir. 1992) ) .
4 Whether an indirect effect is too speculative to require analysis depends on several factors:
With what confidence can one say that the impacts are likely to occur? Can one describe them "now" with sufficient specificity to make their consideration useful? If the decisionmaker does not take into account "now," will the decisionmaker be able to take account of them before the agency is so firmly committed to the project that further environmental knowledge as a practical matter will prove irrelevant to the government's decision?
Sierra Club. 769 F.2d at 877-78.
5 An indirect effect's significance depends on both its "context" and "intensity." 40 C.F.R. § 1508.27. Among the factors that may be relevant to a significance determination are: (1) "[t]he degree to which the proposed action affects public health or safety;" (2) "[t]he degree to which the possible effects on the human environment are likely to be highly
-4- 1286; Sierra Club, 769 F.2d at 878 (citation omitted).
Before work on an EIS begins, the federal agency proposing
the project must engage in a "scoping" process. 40 C.F.R. §
1501.7. To initiate the process, the agency invites the
participation of other federal, state, or local agencies, and
other interested parties, including those who might object to the
action on environmental grounds. 40 C.F.R. § 1501.7(a)(1).
During the scoping process, the agencies and outside parties work
cooperatively to identify the significant issues to be analyzed
in depth in the EIS and to eliminate insignificant issues from
further study. 40 C.F.R. § 1501.7(a ) (2)-(3) .
At the close of the scoping process, the agency begins to
prepare the EIS. Environmental impact statements are generally
prepared in two stages. 40 C.F.R. § 1502.9. First, the agency
works with cooperating agencies to prepare a Draft Environmental
Impact Statement ("DEIS"). 40 C.F.R. § 1502.9(a). After
preparing the DEIS, the agency must obtain comments from "any
Federal agency which has jurisdiction by law or special expertise
with respect to any environmental impact involved or which is
controversial;" and (3) "[t]he degree to which the possible effects on the human environment are highly uncertain or involve unique or unknown risks." Id.
-5- authorized to develop and enforce environmental standards." 40
C.F.R. § 1503.1(a)(1). Additionally, the agency must request
comments from the public and affirmatively solicit comments from
interested persons. 40 C.F.R. § 15 03.1(a)(4).
After the DEIS is released, the agency must prepare a Final
Environmental Impact Statement ("FEIS"). 40 C.F.R. § 1502.9(b).
In preparing the FEIS, the agency must accept and consider public
comments on the DEIS--both individually and collectively--and
include responses to those comments in the FEIS.6 40 C.F.R. §§
1503.4(a)- (b). The agency must supplement either the DEIS or
FEIS--via a Supplemental Environmental Impact Statement ("SEIS")
--in the event of "significant new circumstances or information
relevant to environmental concerns and bearing on the proposed
action or its impacts." 40 C.F.R. § 1502.9(c )(1)(11).
The agency must wait at least thirty days after notice of
6 Possible responses are to: (1) modify alternatives including the proposed action; (2) develop and evaluate alternatives not previously given serious consideration by the agency; (3) supplement, improve, or modify its analyses; (4) make factual corrections; (5) explain why the comments do not warrant further agency response, citing the sources, authorities, or reasons which support the agency's position and, if appropriate, indicate those circumstances which would trigger agency reappraisal or further response. 40 C.F.R. § 1503.4(a).
-6- the FEIS is published in the Federal Register7 before it may make
or publish a decision. 40 C.F.R. §§ 1606.10(a)- (b). Before it
makes its decision, the agency may solicit public comments on the
FEIS. 40 C.F.R. § 1503.1(b). Additionally, other agencies or
persons may comment on the FEIS before the agency makes its
decision. 40 C.F.R. § 1503.1(b).
The agency must publish a Record of Decision ("ROD") when it
makes its decision. 40 C.F.R. § 1505.2. In addition to
announcing the decision, the ROD must, among other things,
identify all alternatives considered and specify which
alternative or alternatives were considered environmentally
preferable. 40 C.F.R. §§ 1505.2(a)- (b). The agency may also
discuss preferences among alternatives based on relevant factors
such as economic and technical considerations as well as agency
statutory missions. 40 C.F.R. §§ 1505.2(b). The ROD must also
state whether all practicable means to avoid or minimize
environmental harm from the alternative selected have been
adopted, and if not, why they were not. 40 C.F.R. § 1505.2(c).
7 Each week, the Environmental Protection Agency must publish a notice in the Federal Register of the environmental impact statements filed during the preceding week. 40 C.F.R. § 1506.10(a) .
-7- The agency must adopt and summarize a monitoring and enforcement
program where applicable for any such mitigation. Id.
B. The Federal-Aid Highway Act
The Federal-Aid Highway Act ("FAHA") requires, among other
things, that the Secretary of Transportation adopt design
standards for the interstate highway system which, "as applied to
each actual construction project, shall be adequate to enable
such project to accommodate the types and volumes of traffic
anticipated for such project for the twenty-year period
commencing on the date of approval ... of the plans,
specifications, and estimates for actual construction of such
project." 23 U.S.C.A. § 109(b).
FAHA also requires that "possible adverse economic, social,
and environmental effects relating to any proposed project on any
Federal-aid system [be] fully considered in developing such
project," and that "the final decisions on the project [be] made
in the best overall public interest, taking into consideration
the need for fast, safe and efficient transportation, public
services, and the costs of eliminating or minimizing such adverse
effects." 23 U.S.C. § 109(h). II. FACTUAL OVERVIEW8
Interstate 93 is a north-south principal arterial Interstate
Highway, portions of which run through the state of New
Hampshire. Administrative Record ("AR") 21402. Interstate 93
was built in the 1960s and early 1970s, and the 19.8-mile section
from Salem to Manchester (the "Project Area"), which currently
consists of two lanes in each direction, has not been
substantially widened since it was built. AR 21404.
In 1988, in order to address perceived problems associated
with traffic congestion, NHDOT began to evaluate conceptual
widening alternatives for the southerly section of the 1-93
corridor. AR 21405. In 1991, Defendants initiated preliminary
designs and environmental analyses of alternatives and impacts.
Id. The process was later delayed for several years, however,
while NHDOT refined its traffic projection methodology. Id.
A. The Statewide Model
In 1999, with the development of the traffic model nearing
completion, NHDOT restarted the environmental review process by
8 The Administrative Record exceeds 28,000 pages and spans nearly 20 years. I describe here only those portions of the record that pertain to CDF's legal arguments.
-9- initiating preliminary engineering and environmental studies.
Id. To assist in analyzing regional transportation needs.
Defendants employed the traffic projection model developed by
NHDOT during the Project's hiatus (the "Statewide Model"). AR
21779. The Statewide Model estimates future travel demand based
on data collected on highway, rail, and bus systems; land use;
and socio-economic characteristics. AR 21779, 26442, 26810. It
then predicts travel behavior and travel demand based on these
inputs and additional information developed by the New Hampshire
Office of Energy and Planning ("OEP") regarding population and
employment data extrapolated from the 1990 Census and local
master plans. AR 26442-43, 26810. The Statewide Model also uses
data such as the number of households in each traffic analysis
zone, broken down by vehicle availability, income level, and
number of workers. AR 26773. The Statewide Model is a "trip
based" model that consists of many "sub-models." AR 21779,
26443. The 1-93 sub-area is one such sub-model. Id. Details of
the sub-models were developed in consultation with the
appropriate regional planning commissions, local officials, and
others. Id.
-10- Defendants used the Statewide Model to forecast traffic on
1-93 for the year 2020 ("the Design Year").9 AR 21780, 26443.
Defendants' 2020 traffic projections for the 1-93 sub-area were
checked against the traffic projections provided by both the
Southern New Hampshire Planning Commission's travel demand model
and the Nashua Regional Planning Commission's model, and the
correlations were found to be acceptable. AR 21780, 26443. FHWA
also engaged an in-house expert in transportation planning from
FH W A 's Eastern Resource Center in Baltimore, Maryland to
independently evaluate the Statewide Model and provide further
validation for the data outputs. AR 10442-43. The expert
concluded that the traffic volume output appeared valid and that
the Statewide Model displayed a "sophisticated level of
development." Id.
B. Scoping Phase
The 1-93 transportation improvement project proceeded in two
phases: (1) the scoping phase, in which Defendants worked
cooperatively with other federal and state agencies to determine
9 A design year is a future year--typically ten to twenty years from the start of construction--used to estimate the probable traffic volume for which a highway is designed. 23 C.F.R. § 772 .5(a) .
-11- a reasonable range of alternatives to consider in detail during
the second phase; and (2) the EIS phase, in which Defendants
considered the alternatives identified during the scoping phase,
selected a preferred alternative, solicited comments from
agencies and the public, and in which FHWA ultimately issued a
ROD.
On May 31, 2000, Defendants published a "Scoping Report" for
the 1-93 project. AR 4846-5082. According to the report, the
project's purpose was to "improve transportation efficiency, and
reduce safety problems associated with [the] approximately 18-
mile segment of 1-93 between Salem and Manchester." AR 4861.
In detailing the congestion and safety problems on 1-93 in
the Project Area, the report noted that 1-93 had been expected to
carry 20,000 vehicles per day over the course of its twenty-year
design life when it was constructed. AR 4857. By 1997, however,
traffic volumes in excess of 100,000 vehicles per day had been
recorded between Exit 1 and the Massachusetts state line, with
segments north of Exit 1 carrying between 60,000 and 80,000
vehicles per day. Id. By 2000, when the report was prepared,
motorists were experiencing traffic congestion and substantial
delays during weekday peak traffic hours. AR 4862.
-12- The report also indicated that traffic operations were
expected to deteriorate further under future conditions as
traffic volumes increased. Id. Traffic forecasts for the year
2020 predicted average daily traffic ranging from approximately
73.000 vehicles per day between Exits 3 and 4 to as high as
137.000 vehicles per day between Exit 1 and the Massachusetts
state line. Id. This level of traffic, the report stated, will
result in much greater congestion along 1-93, at its
interchanges, and along nearby local roads. Id. The additional
delays experienced by motorists, according to the report, are
expected to expand to more hours of the day and to a greater
number of days during the year. Id. The report also predicted
that the delays will increase the frequency of accidents, which
already numbered 1,227 during a five-year study period from
January 1995 to December 1999 .10 AR 4863.
Defendants indicated that they would consider options such
as widening the highway to either three or four lanes each way,
reactivating rail service, and implementing other transportation
10 This figure was later updated in the FEIS, which indicated that a total of 2,427 accidents occurred between the Massachusetts state line and 1-293 during the eight-year period from January 1995 through December 2002. AR 21554-55.
-13- strategies such as improving bus transit service. AR 4861.
Defendants also noted that bus or rail service alone would likely
not be adequate to address the transportation needs and safety
deficiencies within the corridor. Id.
In July 2000, a "Board of Directors" comprised of officials
from numerous federal and state agencies was formed as part of an
environmental streamlining process ("Streamlining Process") for
the 1-93 project. The purpose of the Streamlining Process, which
was conducted pursuant to Section 1309 of the Transportation
Equity Act for the 21st Century ("TEA-21"), Pub. L. 105-178, 112
Stat. 107 (1998), was to coordinate environmental review
processes between various agencies and to expedite federal
highway and transit projects through coordination of
environmental reviews, analyses, opinions, and obtaining
necessary permits, licenses, or approvals. AR 7602, 7607. In
addition to FHWA and NHDOT, agencies such as the United States
Environmental Protection Agency ("EPA"), the Army Corps of
Engineers, the New Hampshire Department of Environmental Services
("NHDES"), and the New Hampshire Department of Fish and Game ("NH
Fish & Game") worked cooperatively to streamline the
environmental review and permitting process.
-14- On November 13, 2000, Defendants published a "Rail
Alternatives Evaluation Report" ("RAER") discussing operations,
costs, and 2020 ridership projections for passenger rail service
in the Project Area. AR 6777-7098. The purpose of the RAER was
to explore the possibility of providing commuter rail service to
Boston, Massachusetts in order to relieve congestion on 1-93. AR
6794-96. The RAER examined four rail alternatives along three
basic alignments: (1) commuter rail service along the New
Hampshire Main Line (the "West Rail Corridor" from Manchester to
Lowell, Massachusetts via Bedford, Merrimack, and Nashua); (2)
commuter rail service along the Manchester and Lawrence Branch
(the "East Rail Corridor" from Manchester to Lawrence,
Massachusetts) with two optional alignments near the Manchester
Airport; (3) two light rail services along the 1-93 highway
right-of-way beginning near either Exit 5 or the Manchester
Airport, and continuing along 1-93 south of Exit 1 and connecting
either to Lawrence, Massachusetts (the "1-93 Basic Rail
Corridor") or to the Anderson Transportation Center in Woburn,
Massachusetts (the "1-93 Enhanced Rail Corridor"). AR 6777-7098.
The RAER examined two key components: operational
requirements and infrastructure needs. AR 6796. The operational
-15- component focused on the identification and development of rail
transit operating assumptions and a preliminary operating plan
for each rail alternative. Id. The infrastructure component
evaluated existing conditions along the rail corridors, including
data relative to general corridor characteristics, track
structure, undergrade bridge structures, grade crossings, and
signal and communications systems. AR 6796-98. This process
also included an operating plan that described each corridor and
its connection to the existing passenger rail system, station
locations, and service possibilities. AR 6798.
On January 22, 2001, Defendants published a "Rationale
Report," identifying transportation alternatives to be carried
forward into the EIS. AR 8242-8437. The Rationale Report
presented an evaluation of each alternative considered as well as
the rationale for eliminating specific alternatives from further
consideration pursuant to NEPA's "reasonable range of
alternatives" selection requirement. AR 8251. Defendants
concluded--on the basis of the data from the RAER and the
Statewide Model--that rail would not be considered in further
detail during the EIS alternatives analysis because it would not
divert enough traffic from 1-93 to eliminate the need to widen
-16- the highway. AR 8342.
In reaching this conclusion. Defendants reasoned that
although rail--and other options such as high occupancy vehicle
lanes--would help shorten periods of congestion on 1-93, serious
congestion problems would nonetheless remain. Id. For instance.
Defendants' projections for the segment of 1-93 between Exit 1
and the Massachusetts state line in the year 2020 revealed that
even the rail transit combination with the largest projected
ridership--!.e ., Enhanced Rail with two general purpose lanes and
an already existing bus service--would generate only 3,365 daily
southbound trips. AR 8322, 8325. According to the report, this
new ridership would only divert 2,263 vehicles from 1-93, leaving
a daily southbound vehicle volume of 67,550 on the segment
between Exit 1 and the Massachusetts state line. AR 8325.
Projections for the same segment during the most congested three
hours of the day (the "Peak Period") were similar. AR 8326. The
transit combination most effective in decreasing Peak Period
vehicle volume diverted only 1,856 vehicles, leaving a Peak
Period vehicle volume of 21,716. Id.
The Rationale Report also concluded that the addition of
rail to any of the alternatives studied in the report would not
-17- improve the Level of Service ("LOS") at any segment of 1-93 in
the Project Area during the hour of the year that is customarily
used when developing highway designs (the "Design Hour").11 AR
8336. While even the most effective rail option would leave all
segments of 1-93 at LOS F during the Design Hour without the
11 LOS is a qualitative measure describing operational conditions within a traffic stream. AR 5035. LOS is determined by considering such factors as speed and travel time, density or freedom to maneuver, traffic interruptions, comfort and convenience, and safety. AR 5035. LOS ranges from A to F, with A representing the best operating conditions, C representing stable flow conditions, E indicating that the roadway is operating at capacity, and F indicating failing conditions. AR 21552-21553. State highway design standards specify that freeways such as 1-93 should be designed to produce LOS D or better during the Design Hour. AR 21777. The general unit of measure used to quantify roadway usage is average daily traffic ("ADT"), which is defined as the total traffic volume during a given timeperiod divided by the number of days in that period. AR 21550. A more specific unit of measure is known as average annual daily traffic volume ("AADT"). AR 21550. AADT is determined by dividing the total yearly volume by the number of days in the year. I d . AADT can also be estimated in terms of hourly traffic volume, which is the primary datum used in evaluating and designing roadways. I d . For instance, peak hour volume is a measurement that represents traffic volume at the most congested hour of the year ("the Peak Hour"). However, designs based on peak hour traffic would be inefficient given the size of the road that would be required. Similarly, merely using the AADT condition of a roadway would result in an inadequate design because the roadway's capacity would be exceeded much of the time. Accordingly, industry practice dictates that the Design Hour should be the hour of the year with the thirtieth highest hourly traffic volume. AR 21550- 51.
-18- addition of new lanes, the Rationale Report concluded that the
widening of 1-93 to four lanes each way would result in 2020
Design Hour operating conditions of LOS E between Exit 1 and the
Massachusetts state line, LOS D between Exits 1 and 3, and LOS C
north of Exit 3. AR 8336.
C. EIS Phase
1. Delphi Study
After identifying the alternatives that would be considered
in detail. Defendants began to draft a DEIS for the 1-93 project.
During this time, in 2001, NHDOT commissioned a study ("the
Delphi Study") to better understand the indirect growth-inducing
effects of widening 1-93 in the Project Area. For the Delphi
Study,12 NHDOT convened a panel ("the Delphi Panel") of sixteen
people comprised of local planning board members, real estate
brokers, regional planners and experts from academia, business,
and non-governmental organizations. AR 11871.
12 A Delphi Study uses a highly structured method for collecting and refining group opinions. The Delphi method was developed in the 1950s by the RAND Corporation to obtain group opinions regarding the state of Soviet nuclear capabilities. Bogdan Dziurzynski, FDA Regulatory Review and Appeal Process: A Delphi Inquiry. 51 Food & Drug L.J., 143, 146 (1996).
-19- The panel assessed the 1-93 project's impacts on a town-by-
town basis for twenty-nine Northern Massachusetts and Southern
New Hampshire communities in and around the Project Area,
estimating future population and employment growth for the year
2020 both with, and without, a four lane expansion of 1-93. AR
21963-65. The Delphi Study was conducted in two phases. The
first phase assessed the likely growth within the New Hampshire
communities in and around the Project Area that would result if
1-93 were not widened, and the second phase forecast the
additional population growth that was likely to occur if the road
were widened by four lanes. AR 21964. In each phase, the panel
evaluated potential land use changes by allocating population and
employment growth among the twenty-nine communities over the
course of several rounds of questionnaires or surveys. Id. A
moderator tallied and summarized the results of each round and
returned the results to the panel members for an opportunity to
revise their initial analyses based on a review of their fellow
panelists' work. AR 21963, 21965. Each phase was complete when
the responses to repeated rounds of questioning did not markedly
change. AR 21963. At the end of each phase, the panelists'
allocations were summarized using a "blended" average to
-20- represent the collective work of the panel. AR 21965.
The Delphi Panel was presented with briefing materials that
included a recent OEP population growth forecast for 2020. AR
9731-32. The OEP forecast presented to the Delphi Panel
predicted that 465,652 people will be living in the New Hampshire
communities in the Project Area in 2020. AR 9732. After
considering the OEP forecast, the Delphi Panel ultimately adopted
a somewhat higher baseline population forecast ("baseline
population growth forecast") of 474,375. AR 11760, 26445.
The Delphi Panel also produced a forecast for the additional
population growth that the panel predicted would occur if 1-93
were widened ("induced population growth forecast"). Focusing on
the New Hampshire communities in the Project Area, the panel's
forecast predicted that the population in the area would grow by
35,317 additional people, or approximately seven percent, if the
road were widened to four lanes each way. AR 11760, 26445. The
Delphi Panel forecast a total induced population increase of
40,629 when the six northern Massachusetts communities adjacent
to the Study Area were included. Id.
2. DEIS and FEIS
Defendants published the DEIS on September 13, 2002. AR
-21- 13829. They later refined their analysis of relevant issues,
responded to comments on the DEIS, and issued the FEIS on April
28, 2004. AR 21381. In the FEIS, Defendants set forth their
selected alternative: widening 1-93 to four lanes in each
direction for the entire length of the Salem-Manchester corridor
(the "Four Lane Alternative"). AR 21403-04. In selecting the
Four Lane Alternative, Defendants relied on the Statewide Model's
2020 traffic projections. 21779-80. The FEIS concluded that if
the highway were not widened (the "No Action Alternative"), all
segments of the 1-93 study corridor would either operate at
capacity or in failing conditions--LOS E or F--during the Design
Hour in 2020. AR 21781. Additionally, the Statewide Model
projected that the congestion would worsen during peak hours, and
that there would be more peak hours of congestion. Id. In
contrast, projections for the Four Lane Alternative suggested
that 1-93 would operate at LOS E south of Exit 1, LOS D between
Exits 1 and 2, and LOS C or better north of Exit 2. AR 21783.
Defendants also concluded that the Four Lane Alternative would
reduce traffic on secondary roads by causing trip diversions from
those roads onto 1-93. AR 21783.
-22- The FEIS also assessed the direct effects of the Four Lane
Alternative on air quality, water quality, and wildlife. With
respect to air quality, the FEIS discussed both regional and
local effects. It explained that Defendants had based their
assessment of the project's regional air quality effects on an
analysis that had been conducted pursuant to the Clean Air Act's
Transportation Conformity Rule.13 AR 21573. In accordance with
13 The Transportation Conformity Rule is codified at 40 C.F.R. §§ 51.390 and 93. It is intended to "ensure[] that transportation plans, programs and projects do not produce new air quality violations, worsen existing violations, or delay the timely attachment of national ambient air quality standards (NAAQs)." 62 Fed. Reg. 43780 (August 15, 1997). As a general rule, transit projects that receive funding under FAHA or that require FHWA approval are subject to the conformity process. 40 C.F.R. 93.102. The Rule covers specific transportation-related pollutants for which NAAQs exist such as ozone, carbon monoxide, and nitrogen dioxide. Susan Shaheen, Randall Guensler & Francisca Mar, Concurrent Air Quality Analysis Under the National Environmental Policy Act and Transportation/Air Quality Conformity, Transportation Quarterly. Fall 1995, at 56. Transportation planning agencies must employ travel demand and vehicle emission rate models to ensure that transportation plans and regionally significant projects contained in plans such as the 1-93 project will not exceed emissions budgets established in the state's air quality management plan. I d . at 56. If a project is subject to a conformity determination, the proposing agency must demonstrate that the project will not cause or contribute to any new violations of air quality standards, exacerbate existing violations, or interfere with the timely attainment or required interim emissions reductions necessary for attainment. See generally Conservation Law Found.. 24 F.3d at 1477 (describing conformity requirements); Shaheen, Guensler &
-23- the rule, the Four Lane Alternative was included in the state's
Transportation Improvement Plan, which was reviewed by EPA and
approved by the United States Department of Transportation
pursuant to the conformity process. AR 21573. As a result, the
FEIS concluded that "a regional analysis outside of that
completed for the conformity determination is not necessary."
Id.
With respect to the local analysis. Defendants calculated
maximum carbon monoxide concentrations at receptor locations for
each intersection using then-current (1997) traffic conditions,
as well as estimated conditions for the project's expected year
of completion (2010) and the design year (2020) both with and
without the proposed widening. AR 21793-97. The local analysis
predicted that carbon monoxide concentrations for both the Four
Lane and No Action Alternatives would be below NAAQs for carbon
monoxide. AR 21801. Defendants did not take traffic generated
by the Delphi Panel's population growth forecasts into account
when they made their air quality predictions. AR 21793-21800.
Mar at 6 0.
-24- The FEIS analyzed the project's effects on water quality by
assessing impacts to surface water, AR 21802-38, aquatic life, AR
21838-48, groundwater, AR 21849-66, and flood plains, AR 21866-
99. Notably, Defendants studied the potential effects of
additional sodium and chloride that could be released into area
waters due to the increased level of deicing required to maintain
additional highway lanes. AR 21810. To document existing
chloride concentrations, the analysis consisted of extensive
sampling of fourteen streams during the 2002-2003 winter season.
AR 21811. The data indicated that under the current conditions,
chloride concentrations during the winter months may occasionally
exceed acceptable levels in several streams. AR 21593. However,
in general, the data revealed that few streams appeared to
consistently have much higher chloride concentrations downstream
from 1-93 relative to upstream concentrations. AR 21592. Thus,
Defendants reasoned that, with the exception of Dinsmore Brook,14
14 Dinsmore Brook has two branches, with the main branch originating about one mile northeast of Exit 3 and flowing through the Exit 3 Interchange area into Cobbetts Pond. AR 21586. The other smaller branch originates just north of Exit 3 within the median of 1-93. The entire watershed area of Dinsmore Brook is estimated to be about 200 acres in size and includes about one mile of the 1-93 Roadway. AR 21586.
-25- these elevated concentrations appeared to be influenced more by
upstream sources as opposed to 1-93. AR 21593. These upstream
sources included salts used in water softening treatment systems,
road salt used and stored in open piles on commercial parking
lots, and road salt applied to municipal roadways. Id.
The FEIS also described an analysis that NHDOT conducted to
estimate the future potential concentrations of chloride and
sodium in streams attributable to 1-93, both under the No Action
Alternative and the Four Lane Alternative. AR 21811. The
analysis indicated that under the Four Lane Alternative, future
chloride concentrations could exceed acceptable levels in four
streams: a tributary to Harris Brook, the south and north
tributaries to Canobie Lake, and Dinsmore Brook .15 AR 21830.
Defendants noted that Policy Brook currently has elevated
chloride levels and a predicted future concentration that
15 The tributary to Harris Brook is a small tributary with a watershed of about 330 acres that runs along the west side of 1-93 for about 3,500 feet before emptying into Harris Brook, which is located south of the Massachusetts state line. AR 21583-84. The south tributary to Canobie Lake is a small stream that originates just west of 1-93 with a 165-acre watershed that includes about 2,000 feet of the existing 1-93 roadway. AR 21585. The north tributary to Canobie Lake is similar in size to the south tributary, with a 160-acre watershed that covers 2,500 feet of the existing 1-93 roadway. AR 21586.
-26- approaches the maximum acceptable level.16 AR 21830.
The FEIS noted that the 1-93 project will include extensive
mitigation measures, including as many as fifty different
extended detention basins and twenty-four grass swales to address
water quality issues. AR 21831. In addition to the basins and
swales, the FEIS described NHDOT's plans to institute enhanced
maintenance measures and use technology to give maintenance
staff real-time pavement temperature and moisture data in order
to prevent unnecessary salt application, and to use salt brine--a
mixture of water and salt--which contains twenty to twenty-five
percent of the salt typically applied to a highway at the
beginning of a storm, yet more efficiently prevents the build up
of ice and snow on asphalt. AR 21833-34. The FEIS also
described NHDOT's decision to participate in a Total Maximum
Daily Load ("TMDL") study to evaluate and manage the various
sources of chloride pollution in the affected watersheds.17 AR
16 Policy Brook flows parallel to the east side of 1-93 within 500 feet of the northbound lane for about one mile before it empties into the Spicket River just north of the Massachusetts state line and encompasses a drainage area of about 3,500 acres. AR 21584.
17 "A TMDL is a specification of the maximum amount of a particular pollutant that can pass through a waterbody each day
-27- 21836. Finally, the FEIS noted that NHDOT will be required to
obtain a Section 401 water quality certification18 from the state
and a Section 404 wetlands permit19 from the United States Army
Corps of Engineers in order to construct the 1-93 project. AR
without water quality standards being violated." Sierra Club. Inc. v. Leavitt. 488 F.3d 904, 908 (11th Cir. 2007) (citations and internal quotation marks omitted). "States must establish a TMDL for every pollutant that prevents or is expected to prevent a waterbody from attaining applicable water quality standards." I d . (citing 40 C.F.R. § 130.7(c )(1)(ii )). "Once a TMDL is established, the state (as well as the federal government) strives to decrease the amount of the pollutant to which that TMDL applies so that the TMDL is not exceeded." Id.
18 Section 401 of the Clean Water Act states in pertinent part: "Any applicant for a Federal license or permit to conduct any activity including, but not limited to, the construction or operation of facilities, which may result in any discharge into the navigable waters, shall provide the licensing or permitting agency a certification from the State in which the discharge originates or will originate . . . that any such discharge will comply with the applicable provisions of sections 1311, 1312, 1313, 1316, and 1317 of this title. . . . No license or permit shall be granted until the certification required by this section has been obtained or has been waived. . . . No license or permit shall be granted if certification has been denied by the State . . . ." 33 U.S.C. § 1341.
19 Regulations promulgated under Section 404 of the Clean Water Act provide that "No discharge of dredged or fill material shall be permitted if it . . . [clauses or contributes, after consideration of disposal site dilution and dispersion, to violations of any applicable State water quality standard . . . ." 40 C.F.R. § 230.10.
-28- 21412 .
With respect to effects on wildlife. Defendants investigated
the entire Project Area for the purpose of documenting wildlife
corridors and wildlife habitats of concern as well as locating
threatened or endangered plant and animal species. AR 21643. As
a result of the investigation. Defendants compiled a
comprehensive list of wildlife species observed, listing both
where they were observed and the way they were observed--!.e .,
auditory or visual observation. Id.
Defendants also conducted a survey during the winter and
spring of 2003 to examine the distribution and abundance of New
England cottontails--a species that the United States Fish and
Wildlife Service is considering listing as threatened or
endangered--and their habitat within the 1-93 study corridor. AR
21652. The study included an intensive search for all suitable
habitats along the Project Area that involved track inventories,
livetraps, and DNA analysis of fecal pellets. Id. Defendants
found that the area immediately adjacent to 1-93 contains few
sites that are suitable habitat for New England cottontails. Id.
Additionally, Defendants found no New England cottontails on any
of the sites along the project corridor or mitigation sites. Id.
-29- The study only identified New England cottontails on one site,
which is located north of the Project Area. Id.
The FEIS also considered the indirect effects of the induced
population growth forecast by the Delphi Panel on land use, AR
21960-87, surface water, AR 21831, groundwater, AR 21863-64,
flood plains, AR 21871, wetlands, AR 21891, and wildlife, AR
21918. As discussed above, the panel projected population and
employment growth for each city and town in the Project Area. AR
21966. Defendants then used this data to identify the extent of
residential and commercial development that could be expected in
the affected communities as a result of anticipated population
growth. AR 21969-87. Defendants further explained that, for the
most part, they could offer only a qualitative assessment of the
environmental effects of induced growth because such
environmental effects would depend to a great extent on local
land use regulations and decisionmaking. AR 21831, 21863, 21880,
21918 .
3. Traffic Sensitivity Analysis
Following publication of the FEIS, Defendants continued to
receive comments from members of the public and other federal and
state resource agencies. Some of the commenters expressed
-30- concern as to whether the Delphi Panel's population and
employment forecasts had been properly accounted for in
Defendants' traffic projections. AR 23608-09. In response, FHWA
undertook a Traffic Sensitivity Analysis ("TSA"), which attempted
to make alternative traffic projections using the Delphi Panel's
population growth forecasts. AR 26442-26450. The TSA was not
released for public comment. However, it was later referenced by
Defendants in their responses to public comments on the FEIS. AR
26951.
The TSA described the population growth forecast that
Defendants had used in developing the traffic projections
disclosed in the FEIS and compared that forecast with the Delphi
Panel's population growth forecasts. AR 26445. The comparison
established that the Delphi Panel's baseline forecast for the
twenty-nine New Hampshire communities exceeded the forecast
Defendants had used in preparing the FEIS by 51,457 people, or
approximately twelve percent. Id. It also noted that the Delphi
Panel's combined forecasts of baseline population growth and
induced population growth for the twenty-nine New Hampshire
communities exceeded Defendants' original population growth
forecast by 86,774 people, or approximately twenty percent. Id.
-31- When the Delphi Panel's population forecast was incorporated into
the Statewide Model, the TSA demonstrated that the panel's
population forecast produced increases in AADT and Design Hour
traffic volumes of nearly thirty percent at all segments of 1-93
south of Exit 4. AR 26448. This analysis revealed that the
changes in traffic would alter the predicted Level of Service
during the Design Hour in 2020 from LOS E to LOS F south of Exit
1, from LOS D to LOS E between Exit 2 and Exit 1, from LOS C to
LOS E between Exit 3 and Exit 2, and from LOS B to LOS C between
Exit 3 and Exit 4. Id.
The TSA also examined the effect of the Delphi Panel's
higher population growth forecast on Defendants' decision to
exclude Rail from the Alternatives analysis. This examination
revealed that the use of the Delphi Panel's population forecast
produced only modest changes in Peak Period vehicle reductions on
1-93 with none of the reductions occurring within the Peak
Hour.20 AR 26449.
20 The TSA states that no vehicle reductions would occur during the Design Hour but the parties agree that this statement actually refers to the Peak Hour.
-32- D. Record of Decision
On June 28, 2005 FHWA issued a ROD approving the Four Lane
Alternative. AR 26912-58. In the ROD, FHWA described the Four
Lane Alternative as the "Environmentally Preferred Alternative"
because it "best balances the need to provide safe and efficient
transportation with social, economic, and natural environment
concerns." AR 26913.
The Four Lane Alternative consists of four lanes in each
direction--northbound and southbound--beginning at the
Massachusetts state line and extending 19.8 miles north through
Salem, Windham, Derry, and Londonderry into Manchester, ending
just north of the I-93/I-293 interchange. AR 26914. In addition
to the construction of additional lanes, the Four Lane
Alternative consists of improvements to the five existing
interchanges along the corridor. Id. To minimize environmental
harm, the ROD incorporated certain "commitments" made in the
FEIS. These commitments include, among other things, the
construction of new park-and-ride facilities to enhance ride-
sharing opportunities and the implementation of the detention
basins and grass swales discussed above to treat water runoff
from the highway. AR 26920, 26922.
-33- Additionally, to further address the chloride pollution
issue and comply with water quality standards, the ROD included a
commitment to employ an "adaptive management approach" that
enables the 1-93 project to address current transportation and
safety needs without causing or contributing to water quality
violations. AR 26914. The core component of this approach,
according to the ROD, is to maintain salt usage at existing
levels. Id. As the selected alternative entails maintenance of
additional lanes on 1-93 during the winter season, FHWA noted
that a reduction in salt usage would be necessary. Id. To this
end. Defendants developed a multi-faceted strategy to reduce salt
usage that includes the technological solutions discussed above
and, if necessary, implementing the proposed project
incrementally by building the full footprint for the Four Lane
Alternative, but paving and operating the highway only as a three
lane facility until chloride pollution issues are addressed to
the satisfaction of NHDES. AR 26914-15.
Ill. STANDARD OF REVIEW
A. Administrative Procedure Act
Neither NEPA nor FAHA provide their own standards of review.
-34- Instead, the appropriate scope of review for claims under both
statutes is the standard set forth in the Administrative
Procedure Act ("APA"). See Dubois, 102 F.3d at 1284. Pursuant
to the APA, "[t]he reviewing court shall . . . hold unlawful and
set aside agency action, findings, and conclusions found to be
arbitrary, capricious, an abuse of discretion, or otherwise not
in accordance with law." 5 U.S.C. § 706(2)(A).
A court reviewing agency action under the APA's "arbitrary
and capricious" standard must "determine whether the agency has
considered the relevant factors and articulated a rational
connection between the facts found and the choice made." Dubois.
102 F.3d at 1284 (emphasis, citations, and internal quotation
marks omitted). "If the agency decision was based on a
consideration of the relevant factors and there has not been a
clear error of judgment, then the agency decision was not
arbitrary or capricious." I d . (citations and internal quotation
marks omitted). Although the APA standard of review is narrow
and highly deferential, "it is not a rubber stamp." I d . at 1285.
Rather, "the [reviewing] court must undertake a thorough,
probing, in-depth review and a searching and careful inquiry into
the record." I d . (citation and internal quotation marks
-35- omitted). The "reviewing court . . . may not supply a reasoned
basis for [an] agency's action that the agency itself has not
given." I d . (citations and internal quotation marks omitted).
B. Summary Judgment
"[The] rubric [of summary judgment review] has a special
twist in the administrative law context." Associated Fisheries
of Me.. Inc. v. Dalev. 127 F.3d 104, 109 (1st Cir. 1997). As
discussed above, "where the APA standard obtains, a court may set
aside an administrative action only if that action is arbitrary,
capricious, or otherwise contrary to law." Id. Thus, a
reviewing court's role in a case governed by the APA is "not to
resolve contested fact questions which may exist in the
underlying administrative record," but rather to "determine the
legal question of whether the agency's action was arbitrary and
capricious." See Gilbert Equip. Co.. Inc. v. Higgins. 709 F.
Supp. 1071, 1077 (S.D. Ala. 1989), aff'd 894 F.2d 412 (11th Cir.
1990). In short, a reviewing court "must look to see if the
agency decision, in the context of the record, is too
unreasonable (given its statutory and factual context) for the
law to permit it to stand." Sierra Club. 976 F.2d at 769. It is
with this framework in mind that I conduct my analysis.
-36- IV. ANALYSIS
CLF has launched a multifaceted attack on Defendants'
decision to proceed with the Four Lane Alternative. Its
principal arguments fall into three broad categories. First, it
argues that Defendants violated NEPA by excluding rail as a
possible alternative during the scoping process. Next, it
contends that Defendants failed to properly assess the direct
effects of the 1-93 project on air quality, water quality, and
wildlife. CLF then argues that Defendants based the FEIS on
inaccurate traffic projections that failed to account for
additional traffic projected by their experts and the resulting
indirect environmental effects that the additional traffic will
produce.
CLF also presents several less well-developed arguments that
are difficult to categorize. Among these are its claim that the
Four Lane Alternative violates FAHA because it will not produce a
large enough reduction in traffic congestion to satisfy NHDOT's
highway design standards. I address each category of arguments
in turn.
-37- A. Rail As An Alternative To Highway Expansion
CLF makes several distinct arguments in support of its
assertion that Defendants improperly excluded rail as an
alternative during the scoping process. First, CLF argues that
the Defendants' decision to exclude rail was tainted by improper
bias. Second, CLF contends that Defendants relied on flawed
assumptions and uncoordinated, piecemeal planning to eliminate
rail from consideration. Third, according to CLF, Defendants
avoided their duty to assess rail through an agreement with the
EPA that they subsequently breached. Finally, CLF argues that
Defendants improperly treated rail as a "stand-alone
alternative."
1. Prejudgment
CLF first argues that Defendants' decision to exclude rail
as an alternative during the scoping process was fatally flawed
because NHDOT began the process with an improper bias against
rail service as an alternative to highway expansion. In support
of this position, CLF points to statements made by NHDOT
officials before rail ridership numbers were projected and before
the publication of the RAER, which essentially indicated that
-38- widening 1-93 was their preferred alternative.21 CLF argues that
NHDOT's prejudgment was so pervasive that its subsequent
evaluation of rail was "mere window dressing" rather than the
objective, rigorous analysis required by NEPA. I am unpersuaded
by this argument.
While I can envision circumstances in which prejudgment
could taint the NEPA review process, the record in this case
reveals, at most, that NHDOT began the process with the view that
highway expansion was the best way to address traffic congestion
and safety issues on 1-93. Courts that have addressed this issue
have recognized that evidence that an agency preferred a
particular alternative from the outset of the NEPA process does
not, by itself, violate NEPA. Envtl. Def. Fund. Inc. v. U.S.
Army Corps of Enq'rs, 492 F.2d 1123, 1129 (5th Cir 1974); Envtl.
Def. Fund. Inc. v. U.S. Army Corps of Enq'rs, 470 F.2d 289, 296
21 According to CLF, the "most compelling evidence of NHDOT's prejudgment against rail" is a statement made by NHDOT official Jeff Brillhart during an exchange with an EPA official: "[I]f induced travel means that our [2020 traffic projections] are low, I suppose the inference is we need to do more in terms of widening the highway." AR 6486. CLF points to additional, similar statements as evidence of NHDOT's prejudgment of rail in its memorandum of law in support of its motion for summary judgment. See Doc. No. 57 at 13, n.5.
-39- (8th Cir. 1972); Seattle Audubon Soc'v v. Lyons. 871 F. Supp.
1291, 1318 (W.D. Wash. 1994). This is particularly true in cases
such as the present one, in which a state agency that is seeking
approval for a major federal action is actively involved in the
preparation of the EIS. As one commentator has explained in
discussing this issue:
Bad faith is not proven by showing that an agency was committed to a project before it initiated its environmental study, promoted the project by speeches or letters while environmental studies were underway, used data provided by an interested party, refused to change its position after preparing an impact statement, or decorated the EIS with "rhapsodic prose." Bad faith usually is reserved in the decisions to describe conduct that would amount to a flagrant violation of NEPA's procedural provisions that would be readily reviewable in court--fraud in the preparation of a statement, outright refusal to comply, or a contemptuous effort evincing a "callous disregard" of environmental consequences.
William H. Rodgers, Environmental Law. 867-68 (2nd Ed. 1994).
CLF has failed to show improper prejudgment by NHDOT. To
the contrary, the Administrative Record demonstrates that
Defendants undertook a rigorous, objective analysis of rail,
including three separate studies concerning rail and other mode
options, before eliminating rail from further detailed
consideration: (1) the Scoping Report, which examined the
-40- condition of existing railroad facilities, the existing railroad
rights of way, and identified potential constraints to providing
passenger rail service, AR 3926-4025; (2) the RAER, which
evaluated three separate passenger rail corridors in southern New
Hampshire by summarizing the infrastructure each would require
and providing ridership and revenue projections, AR 6777-7098;
and (3) the Rationale Report, which considered possible
alternatives at a conceptual level. AR 8242-8437. CLF has
pointed to no evidence of bad faith in the conduct of these
studies or in Defendants' subsequent analysis of the results.
Thus, CLF's prejudgment argument fails.
2. Flawed Assumptions and Uncoordinated Planning
CLF next argues that Defendants' decision to eliminate rail
service from further consideration was based on flawed
assumptions and uncoordinated planning. With respect to its
flawed assumptions argument, CLF contends that the rail ridership
projections in the RAER--which provided the basis for Defendants'
decision in the Rationale Report--were inaccurately low because
they relied on two flawed assumptions: (1) a $0.20 per mile cost
of driving, and (2) a $5.00 average daily parking cost in
downtown Boston. AR 7022. I am unpersuaded by CLF's arguments.
-41- Although these assumptions might seem arbitrarily low at
first blush. Defendants explained in the FEIS why they relied on
the assumptions. AR 22679-81 (responding to CLF's DEIS comments
regarding the two assumptions).22 With respect to automobile
operating costs. Defendants based the cost-per-mile figure on the
marginal cost of operating a vehicle for commuting rather than
the total cost of vehicle ownership and maintenance. AR 22680.
This figure was appropriate. Defendants explained, because they
did not reasonably expect rail service to substantially reduce
the number of required vehicles per household because most
residents will need to use vehicles to get to rail park-and-ride
facilities as well as for other trips such as shopping,
recreation, or transporting children to school or daycare. Id.
Regarding parking costs. Defendants explained that the $5.00 per
day parking cost assumption represents the average cost to all
commuters driving to Boston on a regular basis. AR 22679. These
commuters include those whose parking is partially or totally
paid for by employers, those who park in less expensive lots in
22 Defendants' consulting firm also explained the basis of the parking cost assumption in a September 14, 2000 memorandum to NHDOT. AR 5 957.
-42- South Boston, those who receive lower rates by paying for parking
on a monthly basis, and those who carpool and share the costs of
parking. Id. Consequently, Defendants explained, the average
cost paid by all commuters is considerably less than the daily
rates posted at Boston garage facilities. Id.
Moreover, Defendants conducted an additional sensitivity
test as part of the FEIS which tripled the daily parking cost
assumption to $15. AR 26825. The results of the test
demonstrated that even under the rail alternative which yielded
the highest ridership, $15 daily parking costs would only divert
approximately 360 additional vehicles from 1-93, and that this
diversion would generally take place in the off-peak hours rather
than the Design Hour. Id. Defendants reasonably concluded that
this diversion was insufficient to obviate the need to widen I-
93. Id.
Because Defendants articulated a rational explanation for
the vehicle operation and parking cost assumptions in the
Administrative Record, I decline to conclude that Defendants'
determination to exclude rail from further consideration was
arbitrary and capricious due to their reliance on these
assumptions.
-43- CLF also argues that Defendants' rail ridership projections
were flawed because they were the result of segmented, piecemeal
planning--!.e . a lack of coordination with Massachusetts.
Specifically, CLF attacks Defendants' reliance on a "transit
impedance" assumption that rail service would terminate in
Lawrence, Massachusetts, requiring passengers traveling to Boston
to change trains. AR 7022. If Defendants had coordinated with
Massachusetts in developing the RAER, CLF argues, they could have
learned of additional rail options in Massachusetts that could
eliminate the need for passengers to change trains in Lawrence.
I reject this argument.
As the First Circuit has explained, "alternatives cannot be
studied Ad infinitum . . . ." See Seacoast Anti-Pollution League
v. Nuclear Regulatory Comm'n. 598 F.2d 1221, 1232-33 (1st Cir.
1979). Here, the Administrative Record shows that Defendants
conducted a thorough analysis of four rail options on three
different lines, including a newly constructed line that would
run in the median of 1-93. CLF has not persuaded me that this
analysis was deficient. To be sure, extensive coordination with
Massachusetts during Defendants' evaluation of rail alternatives
phase could have yielded other viable rail options, but in light
-44- of the fact that Defendants studied a fair number of rail
alternatives, I decline to hold that the absence of such
coordination runs afoul of NEPA's requirements.23
3. Breach of EPA Agreement
CLF argues that Defendants improperly avoided their duty to
assess rail as part of the EIS alternatives analysis by entering
into an agreement with the EPA and later breaching that
agreement. The agreement CLF refers to is described in an EPA
"sign-off" letter executed on September 21, 2001 during the
23 CLF also argues that Defendants' assessment of rail alternatives was flawed because it failed to consider potential benefits of rail such as reducing pollution, reducing vehicle- miles-of-travel, providing transportation choice, and supporting more compact, less sprawling development patterns. CLF contends that Defendants' decision to focus only on the extent to which rail service could eliminate the need to widen 1-93 rather than on these potential benefits is further evidence of their prejudgment of the project and their failure to perform a rigorous alternatives analysis. This argument is unpersuasive. The project's purpose was to improve transportation efficiency and safety on 1-93. While rail has many beneficial environmental effects when compared to automobile use, these benefits did not obligate Defendants to include rail as an alternative in the FEIS if they reasonably concluded, as they did in this case, that rail would not produce enough improvement in traffic congestion to eliminate the need to widen 1-93. Ass'ns Working for Avora's Rural Env't v. Colo. Dep't of Transp., 153 F.3d 1122, 1130 (10th Cir. 1998)("it is clear that an agency need not independently evaluate alternatives it determines in good faith to be ineffective as a means to achieving the desired ends").
-45- Environmental Streamlining Process. AR 10829-31. In the letter,
the EPA agreed not to recommend that the rail alternative be
studied in detail during the EIS process. Id. The EPA was
clear, though, that this agreement was contingent upon NHDOT
committing to conduct--and to eventually implement the results
of--a bi-state transit study with Massachusetts that would
analyze future rail alternatives in the 1-93 corridor. Id.
CLF misapprehends the effect of this "sign-off" letter.
Although the EPA participated in the Streamlining Process,
Defendants, not the EPA, "bore the ultimate statutory
responsibility for actually preparing the environmental impact
statement." Citizens Against Burlington. Inc. v. Busev. 938 F.2d
190, 201 (D.C. Cir. 1991) (citation omitted). Accordingly,
Defendants do not "have to follow the EPA's comments slavishly --
[Defendants] just [have] to take them seriously." Id. Thus, the
EPA had no power to "relieve" the Defendants of their statutory
duty to assess alternatives. See i d . A lead agency cannot
"contract away" its NEPA duties during an environmental
streamlining process. See i d . The issue here is simply whether
Defendants fulfilled their duties under NEPA--i.e., whether
Defendants took the EPA's pre- and post-EIS comments seriously
-46- and responded to them reasonably. See i d .
A review of the Administrative Record yields no indication
that Defendants did not take the EPA's suggestions seriously.
The Record shows--as CLF points out--that Defendants responded to
the SPA's pre-EIS concerns about future rail alternatives by
committing to undertake a bi-state transit study with
Massachusetts. This study is currently underway. AR 25951-53.
While the study may not have commenced by the original date
contemplated in the FEIS, and the EPA expressed concerns about
this delay in its comments to both the DEIS and the FEIS, I
decline to conclude that delay in beginning the study proves that
Defendants did not take the EPA's comments seriously or that they
otherwise violated NEPA.
4. Treating Rail as a "Stand-alone" Alternative
CLF next argues that Defendants improperly treated rail as a
"stand-alone" alternative rather than as an alternative that
could be adopted in combination with widening the highway. I
disagree.
Defendants considered a wide range of alternatives
including: (1) no action; (2) implementation of Transportation
-47- System Management24 actions such as modifying entrance and exit
ramps, installing signals at entrance ramps, permitting shoulder
lane use, and a number of technological solutions known as
Intelligent Transportation Systems ("ITS");25 (3) numerous
combinations of highway widening including widening individual
24 Transportation Systems Management ("TSM") refers to short range, moderate cost measures aimed at reducing congestion and enhancing safety on an existing transportation system or roadway network. AR 21430. TSM includes such measures as adding traffic signals, modifying traffic signal timing, adding or extending turn lanes, improving acceleration and deceleration lanes, restriping of existing pavement markings, and the incorporation of turn restrictions. Id.
25 ITS are applications of information processing, communications, control, and electronics to improve the efficiency and/or safety of a transportation system such as a highway. AR 21439. Several ITS initiatives are currently underway in New Hampshire. I d . These include a system of electronic toll collection and a cooperative program being undertaken by New Hampshire, Maine, and Vermont to develop a regional traveler and tourism information system comprising databases containing construction, incident, accident, delay, tourism event information, weather conditions, and a system providing for public access to these information databases on the Internet. AR 21439-40. Additional ITS technology contemplated by Defendants includes information collection tools such as additional traffic flow counters, road-weather information systems, real-time vehicle location systems to track bus or maintenance vehicle progress, video cameras, and cellular phone reports from consumer volunteers, as well as information dissemination tools such as changeable message signs, highway advisory radio, Internet, cable TV, and telephone information systems. AR 21443.
-48- segments or groups of segments to three or four lanes; (4)
implementation of transportation demand management strategies
such as employer-sponsored or subsidized transportation programs
and congestion pricing--!.e . construction of toll facilities; (5)
providing alternative modes of transportation such as passenger
rail service on three potential rail corridors, bus service,
park-and-ride facilities, high occupancy vehicle lanes; and (6)
numerous combinations of the first five alternatives. AR 21428-
21513. With respect to combinations of alternatives. Defendants
considered various combinations of different numbers of general
purpose lanes with HOV lanes, bus service, and rail service. AR
21512. The record in this case demonstrates that CLF is simply
wrong in contending that Defendants improperly treated rail as a
stand-alone alternative.
B. Direct Environmental Effects of Highway Expansion
CLF next argues that Defendants violated NEPA by failing to
adequately assess the effects of the 1-93 project and its
alternatives in three areas: air quality, water quality, and
wildlife. Under NEPA, Defendants were required to "consider
every significant aspect of the environmental impact" of the 1-93
project. See V t . Yankee Nuclear Power Corp. v. Natural Res. Def.
-49- Council, 435 U.S. 519, 553 (1978). In this section, I consider
whether Defendants have fulfilled this duty.
1. Air Quality
a. Failure to Assess Impacts of Mobile Source Air Toxics
CLF argues that Defendants violated NEPA by failing to
assess the public health and environmental effects of certain
pollutants known as mobile-source air toxics ("MSATs") .26
The Administrative Record reveals that Defendants based
their analysis of air quality in the FEIS on the EPA's then-
current regulatory vehicle emissions model, which did not have
the capability to predict select MSAT emissions. AR 26943. The
record also shows that the EPA did not announce the availability
of a model that could predict these MSAT emissions--M0BILE6.2--
until May 2004, after the FEIS had been published. Id.
Nevertheless, despite the belated availability of MOBILES.2, and
in response to comments on the DEIS and FEIS regarding MSATs,
FHWA used the new model to conduct an MSATs analysis before it
26 MSATs are emitted by motor vehicles. They include the pollutants acetaldehyde, acrolein, benzene, 1,3-butadiene, diesel particulate matter, and formaldehyde, commonly referred to as "priority MSATs". AR 26943.
-50- issued the ROD. AR 26679. The analysis compared the 1-93
project with a similar hypothetical highway improvement project.
Id. Using this approach, together with data on the 1-93 project,
FHWA estimated that MSATs produced on the section of 1-93 in the
Project Area will be reduced by approximately eighty percent by
2020, regardless of whether 1-93 is widened or left unchanged.27
AR 26680-81. FHWA concluded that anticipated reductions in MSAT
emissions would be comparable under either alternative because
any increases in MSAT emissions produced by the additional
vehicles that will travel along the newly widened highway under
the Four Lane Alternative would be offset by the reductions in
emissions resulting from anticipated improvements in the flow of
traffic. Id.
CLF faults FH W A 's MSAT analysis both because FHWA did not
perform the analysis until after the FEIS was released and
because FHWA allegedly did not base its analysis on "project
specific" data. Neither argument has merit. The timing of the
analysis cannot be seriously questioned because MOBILE6.2 did not
27 The projected reductions in MSAT emissions are expected to result from new nationwide mobile-source control programs such as reformulated gasoline and low emission vehicle standards. AR 26680-81.
-51- become available for use until after the FEIS was released.28 AR
26943. Second, while FHWA used a hypothetical highway
improvement project similar to 1-93 in their analysis, they also
clearly considered project specific data for the 1-93 project
when estimating MSAT emissions under the No Action and Four Lane
Alternatives. Supplemental Record ("SR") 53, AR 26377. In any
event, FHWA did not even adopt interim guidance requiring the use
of project specific data in the analysis of MSAT emissions until
after the ROD was issued. SR 678.
b. Other Air Quality Effects
CLF also takes Defendants to task for failing to separately
assess the impact of the Four Lane Alternative on air quality in
Massachusetts as a part of its analysis of the project's regional
air quality effects. The short answer to CLF's argument--which
is warranted because CLF has presented this argument in only a
skeletal form--is that the FEIS documents the fact that
Defendants carefully considered the regional air quality effects
of the Four Lane Alternative in the manner required by the Clean
28 I do not consider whether the MSAT analysis qualifies as significant new information that should have been disclosed in an SEIS because CLF does not claim that an SEIS was required for this purpose.
-52- Air Act's Conformity Rule. It was not arbitrary and capricious
for the Defendants to assess regional air quality impacts under
the rule without also separately analyzing air quality impacts in
Massachusetts. See Shaheen, Guensler & Mar at 63 (explaining
that "conformity analysis should more than satisfy NEPA air
quality requirements").
2. Water quality
CLF next agues that Defendants failed to properly address
the effects of the 1-93 project on water quality. CLF first
claims that Defendants used the wrong water quality standard for
chloride pollution in the FEIS and the ROD because both documents
incorrectly assume that Defendants may proceed with the Four Lane
Alternative without violating the Clean Water Act as long as the
proposed lane widening does not result in additional chloride
loading into impaired waterbodies. Next, it claims that the ROD
is invalid because it breaches Defendants' alleged commitments to
participate in a regional TMDL study and to operate 1-93 as a
three lane facility until chloride pollution issues are properly
addressed.
a. Clean Water Act Standards
CLF argues that § 401 and § 404 of the Clean Water Act each
-53- require Defendants to refrain from expanding 1-93 unless they can
demonstrate that total chloride discharges from the expanded I-
93--including both the existing four lanes and the four proposed
additional lanes--will be reduced to the point that all affected
waterbodies will meet state and federal water quality standards
for chloride.
CLF cites no statutory, regulatory, or judicial authority
for its novel interpretation of the Clean Water Act, and its
theory is especially problematic in this case because the
Administrative Record establishes that most of the existing
chloride pollution in the region is caused by sources that are
unrelated to 1-93. AR 21593. I need not evaluate CLF's Clean
Water Act arguments on their merits, however, because I lack
jurisdiction to consider such claims in a NEPA action. NHDOT has
obtained § 401 Water Quality Certification from the state.
Challenges to that certification ordinarily must be brought in
state court. Roosevelt Campobello Int'l Park Comm'n v. U.S.
En v t '1 Pr o t . Agency. 884 F.2d 1041, 1056 (1st Cir. 1982).
Although there are limited circumstances in which a plaintiff
could challenge a state's § 401 certification in federal court,
CLF cannot use its NEPA claim to present such a challenge. See
-54- Dubois, 102 F.3d at 1300-01. NHDOT has also obtained a § 404
permit from the Army Corps of Engineers. CLF remains free to
challenge that permit by bringing a claim under the Clean Water
Act. Because it has not brought such a claim in this case, I
have no jurisdiction to entertain its arguments on this point.
City of Olmstead Falls. Ohio v. Fed. Aviation Admin.. 292 F.3d
261, 273 (D.C. Cir. 2002) .
b. TMDL Study
CLF claims that Defendants agreed in the FEIS that NHDOT
would participate in a regional TMDL study to address the issue
of chloride pollution. CLF also asserts that Defendants agreed
in the ROD that NHDOT would pave and operate 1-93 as a three-lane
facility until the issue of chloride pollution is addressed to
the satisfaction of NHDES. CLF then argues that Defendants have
breached these commitments because NHDOT's § 401 water quality
certificate does not obligate it to fulfill its commitments with
respect to chloride contamination. I find no support in the
record for this argument.
Defendants acknowledged in the FEIS that a TMDL study was
needed to evaluate chloride pollution in regional watersheds. AR
21836. Specifically, Defendants anticipated that NHDES would
-55- develop "a TMDL for chloride sources in the watersheds of any
waterbody that is found to meet the state water quality standards
for chloride." AR 21837. According to the FEIS, "the "TMDL
[would] assess, on a regional basis, the relative contribution
and effect of the various sources, including 1-93, other state
roads, municipal roads, private roads and commercial parking
lots, septic and water softening systems as well as salt storage
practices by local sources on these impaired waterbodies." Id.
The FEIS further states that "NHDOT will participate in this
regional study and work towards implementing, on state highways,
the appropriate and practicable road salt management plans that
may be developed." Id. In their response to comments on the
FEIS, Defendants further stated:
[U]ntil water quality issues associated with additional chloride loadings are addressed regionally, the facility will initially be paved and operated as a six- lane facility (three lanes in each direction). The fourth lane would be completed and opened to traffic when there is agreement between NHDOT and the NHDES that new technology, best management practices, and/or other considerations are sufficient for the project to be completed in compliance with conditions placed on the Section 401 Water Quality Certification.
AR 26707. These commitments are carried forward in the ROD where
-56- Defendants agreed both "to support NHDES in conducting TMDLs, for
waterbodies in the corridor . . and to operate 1-93 as a six-
lane facility until NHDOT reaches an agreement with NHDES that
"new technology, best management practices, and/or other
considerations are sufficient for the project to be completed in
compliance with conditions placed on the Section 401 Water
Quality Certification . . . AR 26915. The only difference
between the FEIS and the ROD with respect to the TMDL study is
that the TMDL study described in the ROD was narrower in scope
than that contemplated in the FEIS. AR 26915. Specifically, the
ROD stated that NHDOT would participate in a "waterbody-
specific"--as opposed to a regional--TMDL study. Id. CLF argues
that this difference "unlawfully undermines the legitimacy of the
NEPA process." I disagree.
As discussed above. Defendants indicated in the FEIS that
NHDES would develop a TMDL study and that NHDOT would participate
in the study. An examination of the Administrative Record
reveals that NHDES decided that a waterbody-specific TMDL study
would be more appropriate given the high estimated cost of a
regional TMDL study. AR 20985. Moreover, the TMDL study
-57- described in the ROD includes the waterbodies most impacted by
the runoff from 1-93 and thus does not materially affect
Defendants' commitment to address the issue of chloride pollution
associated with the project. Id. Thus, I decline to hold that
Defendants' statement in the ROD that NHDOT would participate in
a narrower study was arbitrary and capricious or violated a
commitment in the FEIS.
The § 401 Water Quality Certification issued in this case
also conforms to the commitments that Defendants made in the FEIS
and ROD. In particular, it requires NHDOT to participate in a
TMDL study for surface waters impaired by chloride pollution, and
specifies that those studies "shall be designed to assess and
quantify sources of chloride loads from all sources to watersheds
in the area affected by the activity," it bars highway expansion
from contributing to additional chloride loading, and it requires
NHDOT to operate 1-93 as a six-lane facility until TMDLs and
implementation plans are in place and chloride reductions are
achieved in accordance with the plans. SR 892. Accordingly, the
conditions placed on the § 401 Certification for the project are
consistent with the Defendants' commitments in the FEIS and the
-58- 3. Wildlife
CLF next argues that Defendants failed to adequately assess
impacts on wildlife because NHDOT improperly manipulated the NEPA
process by influencing the formal DEIS comments that NH Fish &
Game made to the DEIS.
In support of this argument, CLF first points to draft
comments on the DEIS that Wildlife Ecologist William Ingham
authored and circulated to the NH Fish & Game staff. AR 24487-
89. Ingham voiced concerns regarding the adequacy of the DEIS's
assessment of wildlife impacts. The comments were not
incorporated into NH Fish & Game's formal comments on the DEIS.
Rather, NH Fish & Game's formal DEIS comments stated, inter alia,
that because the project involves only the widening of an
existing highway, "fragmentation of wildlife habitat is not an
issue." AR 2 2335.
CLF claims that NH Fish & Game's decision not to include the
concerns raised in the Ingham draft was "greatly influenced" by
communications between NHDOT and NH Fish & Game Acting Executive
Director Bill Bartlett regarding Ingham's draft comments. AR
24137 (stating that "NHDOT did provide . . . Bill Bartlett
comments on [the Ingham draft comments]"). According to CLF,
-59- NHDOT's communication with Bartlett constituted improper
manipulation of the NEPA process because it undermined the
legitimacy of an independent agency's comments on the DEIS. The
only authority CLF cites in support of its position is the basic
principle that "where comments from responsible experts or sister
agencies disclose new or conflicting data or opinions that cause
concern that the agency may not have fully evaluated the project
and its alternatives, these comments may not simply be ignored.
There must be good faith, reasoned analysis in response."
Commonwealth of Mass. et a l . v. Andrus et a l ., 594 F.2d 872, 884
(1st Cir. 1979) (citation omitted).
I do not take issue with this fundamental principle.
However, CLF has presented no authority to support its contention
that an agency such as FHWA must not only consider formal
independent agency comments in the FEIS, but must also examine
internal staff-level drafts of those comments. Nor does CLF
point to any authority suggesting that NHDOT acted improperly by
communicating with NH Fish & Game with respect to its DEIS
comments. To the contrary, NEPA encourages cooperation and
consultation with independent agencies throughout the process.
See, e.g.. 40 C.F.R. 1500.5(b); 1501.1(b). To the extent CLF
-60- asserts that these communications were made in bad faith, it has
not identified sufficient evidence to support its assertion.
C. Traffic Projections and the Environmental Effects of Additional Traffic
CLF faults Defendants for relying exclusively on an outdated
OEP population growth forecast in preparing their traffic
projections rather than also considering the traffic-generating
effects of the Delphi Panel's baseline and induced population
growth forecasts. As I will explain, I ultimately conclude that
Defendants erred in failing to account for both forecasts, that
the omitted information was significant, and that Defendants'
errors were not harmless.
1. Baseline Population Growth
The Administrative Record reveals that Defendants based the
traffic projections they disclosed in the FEIS on an OEP
population growth forecast derived from 1990 Census data. AR
26442-43. Inexplicably, although Defendants gave the Delphi
panelists a more recent and substantially higher OEP forecast
well before Defendants issued the DEIS, they made no attempt to
update their own traffic projections in either the DEIS or the
FEIS to account for the revised OEP forecast. Nor did they
-61- incorporate the Delphi Panel's somewhat higher baseline
population growth forecast into their traffic projections even
though it is apparent from the record that the baseline forecast
was based to a significant extent on the revised OEP forecast.
Defendants have failed to explain their decision to rely on
the outdated OEP population growth forecast rather than either
the more recent OEP forecast given to the Delphi Panel or the
Delphi Panel's baseline forecast. The OEP forecast given to the
Delphi Panel is approximately ten percent higher than the
original OEP forecast, and the Delphi Panel's baseline forecast
is twelve percent higher than the original OEP forecast. Thus,
Defendants are in no position to credibly claim that they relied
on the original OEP forecast because the differences between the
forecasts were inconsequential.
Nor can Defendants reasonably claim that they were entitled
to rely on the outdated OEP forecast because the Delphi Panel's
baseline forecast was unreasonably high. Defendants did not make
such a claim at the time and even now they do not contend that
the baseline forecast substantially overstates anticipated
-62- population growth in the region.29 Defendants have consistently
claimed that OEP is the entity in the state with the greatest
expertise in forecasting population growth. Moreover, the Delphi
Panel's baseline forecast was based on a more recent OEP
forecast, and it was the Defendants who commissioned the Delphi
Panel. Having selected their experts. Defendants were not free
to reject without explanation the most recent population
forecasts prepared by the experts in favor of an earlier outdated
forecast.30
29 Such a claim would be difficult to credibly make because, as the TSA acknowledges, the baseline forecast is within one percent of the OEP forecast that was in effect when the TSA was prepared. AR 26444.
30 Defendants have sought to devalue the Delphi Panel's population growth forecasts because the panel expressed its results as blended averages rather than as consensus forecasts. I find this argument puzzling, particularly as it applies to the Panel's baseline population growth forecast. Delphi Panels have been used for many years in a variety of contexts and the National Research Council's Transportation Research Board has endorsed their use in transportation projects. Land Use Impacts of Transportation: A Guidebook. Transportation Research Board, NCHRP Report 423A (1999) at 27-35; see also Desk Reference for Estimating the Indirect Effect of Proposed Transportation Projects. Transportation Research Board, Report 466 (2002) at 72- 73. Moreover, Defendants are the ones who commissioned the Delphi Panel report. If they were concerned that the use of blended averages was somehow unreliable, they could have chosen an alternative methodology. Finally, the close alignment between the panel's baseline forecast and the revised OEP forecast
-63- Finally, it is important to bear in mind that Defendants
were in possession of both the more recent OEP forecast and the
Delphi Panel's baseline forecast well before they issued the
DEIS.31 While NEPA does not require an agency to update its
population forecasts whenever new forecasts become available, it
ordinarily may not rely on outdated forecasts when it sets out to
prepare an EIS even though more recent forecasts from the
agency's own experts are readily available. Defendants' decision
to do so here was error.
2. Induced Population Growth
CLF also argues that Defendants improperly failed to revise
their traffic projections to account for the Delphi Panel's
induced population growth forecast. Defendants respond primarily
reflected in the TSA calls this argument into doubt given Defendants' treatment of OEP forecasts as the gold standard when it comes to population forecasting.
31 Defendants were in possession of revised OEP population projections by June 29, 2001. AR 9731-32. The Administrative Record also demonstrates that the Delphi Panel published its final report containing its baseline population forecast on December 28, 2001 and then revised the report on January 22, 2002. AR 11750, 11760. Therefore, Defendants had both a revised OEP forecast and the Delphi Panel's baseline population forecast well before their September 13, 2002 publication of the DEIS and at least two years before they issued the FEIS on April 28, 2004.
-64- by claiming that the panel's induced growth forecast is too
speculative to be included in traffic projections,
a. Background
The idea that highway improvement can produce additional
traffic, including traffic caused by induced population changes,
is based on the basic economic theory of supply and demand: if
highway improvement significantly reduces the cost of travel by
making it more efficient, and the demand for travel is elastic,
the improvement can be expected to produce more traffic. AR 5857
(a 2000 paper by Roland Nolan and Lewis Lem entitled Induced
Travel: A Review of Recent Literature and the Implications for
Transportation and Environmental Policy) . This phenomenon, which
is often referred to as "induced traffic"32 can include traffic
diverted from other roads and other transportation modes, traffic
that would otherwise not have occurred at all but for the
improvement, and traffic produced by induced population growth.
Nolan & Lem, AR 5861-62.
32 "Induced Traffic" is used in different ways in the professional literature. See generally Peter Hills, What is Induced Traffic, 23 Transp. 5, 5-16 (1996). I use the term to refer to additional traffic on an improved roadway at a given time that would not have been present if the improvement had not occurred.
-65- The Administrative Record demonstrates that Defendants
treated induced traffic from all sources, including induced
population growth, as a real phenomenon that was foreseeable but
difficult to reliably quantify. AR 8417. Defendants assumed
when they developed the Statewide Model that the Four Lane
Alternative would produce induced traffic on 1-93 as a result of
trip diversions and transportation mode shifts. AR 21783.
Accordingly, their traffic projections are approximately seven
percent higher on average for the Four Lane Alternative as
compared to the No Action Alternative. Id. Defendants also used
FH W A 's Spreadsheet Model for Induced Travel Estimation ("SMITE")
to estimate the total combined effect of induced traffic from all
sources. AR 8421. In responding to comments on the DEIS,
Defendants discussed their use of the SMITE spreadsheet and noted
that the increase in vehicle-miles-traveled on 1-93 as a result
of induced traffic varied widely, ranging from seventeen to
forty-one percent."33 AR 22678.
33 CLF presents a conclusory argument that Defendants erred in failing to account for induced traffic caused by sources other than trip diversions, transportation mode shifts, and induced population growth. I reject this argument, because I conclude that Defendants' discussion of the issue in the FEIS and their responses to public comments was adequate under the
-66- Defendants also attempted to quantify the induced population
growth that will result from the adoption of the Four Lane
Alternative. Recognizing that existing quantitative and
qualitative methods for forecasting induced population growth
"all have their shortcomings," Defendants ultimately settled on
the use of a Delphi Panel as the best available method for
forecasting induced population growth. AR 8650. Although
Defendants used the panel's induced growth forecast to evaluate
the indirect effects of induced population growth on land use, AR
21960-21991, water quality, AR 21863-64, 21891-93, and wildlife,
AR 21918, they made a conscious choice not to use the forecast to
evaluate the traffic-generating effects of induced population
growth on 1-93, secondary roads, or air quality issues, AR 8419,
AR 218 0 0.
b. Analysis
Defendants cite several reasons to support their contention
that the Delphi Panel's induced population growth forecast is too
speculative to be used in traffic projections. First, although
circumstances.
-67- Delphi Panels have been used in other transportation projects,
the predictive validity of the Delphi process as a method for
forecasting population growth has yet to be established. Second,
although the idea that traffic improvements can produce
population changes is sound, many different variables must be
considered when quantifying induced population growth, and
interactions among the relevant variables are extremely difficult
to reliably assess. Third, although Delphi Panel forecasts can
inform transportation planning when quantitative methods are
unavailable, the Delphi process is entirely subjective and
therefore a particular panel's forecast is ultimately no better
than the quality of the data provided to the panelists and the
reliability of their individual opinions. Finally, Defendants
have expressed concern that the use of both the panel's induced
growth forecast and its baseline forecast could potentially
overstate the effect of induced population growth in the present
case because the panel's baseline forecast was predicated on a
revised OEP population growth forecast, and OEP presumably was
cognizant of anticipated roadway improvement projects such as the
-68- widening of 1-93 when it prepared its forecast.34
While I agree with Defendants that it is a mistake to assign
talismanic significance to the Delphi Panel's induced population
growth forecast, I cannot accept their more extreme position that
they were free to entirely disregard the forecast when they
prepared their traffic projections. Forecasts are always marked
by a degree of uncertainty, yet NEPA often requires agencies to
forecast uncertain events. See Dubois. 102 F.3d at 1286. An
agency may not treat a foreseeable effect as nonexistent simply
because the magnitude of the effect is difficult to quantify.
In the present case. Defendants used the same outdated OEP
population growth forecast in their traffic projections for both
the No Action Alternative and the Four Lane Alternative even
34 I cannot find support for this last assertion in the Administrative Record. The widening of 1-93 has long been a part of the state's ten-year Transportation Improvement Plan, see, e.g.. N.H. Laws 1995, ch. 240; NH Laws 1998, ch. 306, and it is reasonable to assume that OEP was aware of the 1-93 project when it prepared its population forecasts. Nevertheless, because Defendants used the same population forecasts for both the No Action Alternative and the Four Lane Alternative, and the record does not specifically explain whether and to what extent OEP included an allocation for induced population growth in its forecast, I cannot say whether the OEP forecast understates population growth under the Four Lane Alternative or overstates such growth under the No Action Alternative.
-69- though commentators on the DEIS faulted Defendants for failing to
modify their traffic projections to account for induced
population growth forecast by the Delphi Panel. AR 22558-59.
The traffic-generating effects of population changes were well
understood by the Defendants as such effects can be projected
through the use of the Statewide Model. Accordingly, such
effects are among the least speculative effects of population
growth. Defendants' willingness to consider the effects of
induced population growth in other areas such as land use, water
quality, and wildlife, where the effects of population growth are
less well understood, belies Defendants' contention that the
traffic-generating effects of induced population changes are too
speculative to be considered in this case. Thus, having convened
the Delphi Panel for the purpose of forecasting induced
population growth, and having decided to rely upon the panel's
induced growth forecast for certain purposes. Defendants were not
free, at least without substantial additional explanation, to
treat induced population growth as a non-existent factor in their
traffic projections. Instead, Defendants should have performed
the TSA, disclosed its results in the FEIS, and explained why the
analysis did not affect their decision to proceed with the Four
-70- Lane Alternative. Their failure to do so was error.
3. Significance
Defendants argue that they were under no obligation to
disclose the effects of the Delphi Panel's forecasts on their
traffic projections because the additional traffic that will
result if the forecasts prove to be accurate is not significant.
I disagree.
The TSA demonstrates that the use of the Delphi Panel's
baseline and induced population growth forecasts increases the
projected traffic for the Four Lane Alternative on all segments
of 1-93 south of Exit 4 by approximately thirty percent. AR
26448. This additional traffic changes the LOS projections for
1-93 from LOS E to LOS F south of Exit 1, from LOS D to LOS E
between Exit 1 and Exit 2, from LOS 0 to LOS E between Exit 2 and
Exit 3, and from LOS B to LOS 0 between Exit 3 and Exit 4. AR
26448. Such changes in traffic volumes and Levels of Service can
hardly be considered insubstantial.
Defendants respond by claiming that the additional traffic
congestion that the TSA projects for the Four Lane Alternative is
inconsequential even if it results in substantial increases in
traffic volumes and unacceptable Levels of Service for certain
-71- segments of 1-93. Because any additional projected traffic that
results from the use of the Delphi Panel's baseline forecast will
also be experienced under the No Action Alternative, and any
additional induced traffic that occurs under the Four Lane
Alternative will still leave 1-93 less congested than it would be
under the No Action Alternative, Defendants argue that the TSA
merely underscores the need for the project.35 While this
argument may well justify a decision to proceed with the Four
Lane Alternative even if it is an imperfect solution to the
traffic congestion problem on 1-93, it cannot excuse a decision
to withhold information from the public that leaves it with the
mistaken impression that the selected alternative will be
substantially more effective in achieving one of the project's
35 Defendants also argue that the TSA's traffic projections are insignificant because Defendants acknowledged in the FEIS that they intended to proceed with the Four Lane Alternative even though it failed to produce a large enough improvement in traffic congestion to satisfy state highway design standards. This argument is a non-starter. The TSA establishes that projected traffic under the Delphi Panel's forecasts will be substantially worse than Defendants disclosed in the FEIS. Such information does not become insignificant simply because Defendants disclosed the fact that the Four Lane Alternative is a less-than-perfect solution to the traffic congestion problem on 1-93 even under the substantially lower traffic projections disclosed in the FEIS.
-72- two primary objectives than may actually be the case. Reliable
information produced by the agency's own experts that casts doubt
on the agency's statements concerning a selected alternative's
effectiveness is not insignificant.
The additional traffic projected by the TSA is also
significant because it will produce foreseeable indirect effects
on secondary road traffic and air quality that Defendants failed
to analyze in the FEIS. Defendants did a commendable job in
convening the Delphi Panel and using its induced population
growth forecast to evaluate the indirect effects of induced
population growth on land use, surface water, ground water,
wetlands, and wildlife.36 However, Defendants made a conscious
choice not to consider how, if at all, the traffic-generating
effects of the Delphi Panel's population growth forecasts could
affect either secondary road traffic or air quality. Because
36 CLF claims that Defendants failed to undertake a sufficiently detailed analysis of the indirect effects of induced population growth on these subjects. I am unpersuaded by this argument. Defendants commented extensively on the effects of induced population growth on land use, water quality, and wildlife issues in the FEIS and adequately explained their reasonable conclusion that a more detailed analysis was not possible given their limited ability to predict precisely where population and employment changes will occur and how local land use regulations will affect any resulting development.
-73- Defendants operated under the assumption that the induced
population growth forecast by the Delphi Panel would not produce
any additional traffic, they concluded that traffic congestion on
secondary roads would be reduced under the Four Lane Alternative
as a result of trip diversions onto the newly expanded highway.
AR 21783. CLF's traffic consultant plausibly claims, however,
that the traffic modeling Defendants used in preparing the TSA
establishes that the induced population growth predicted by the
Delphi Panel will produce enough additional traffic on secondary
roads to more than offset any reduced traffic on secondary roads
caused by trip diversions. Doc. No. 73, Attach. 3 (Declaration
of Norman L. Marshall). This foreseeable effect of the Four Lane
Alternative must be assessed by the Defendants in a manner that
allows for public comment.
Defendants also failed to consider in the FEIS how the
additional traffic that results from the use of the Delphi
Panel's population growth forecasts will affect air quality
issues. Because Defendants based their air quality analysis on
traffic counts derived from the use of an outdated OEP population
forecast that did not account for induced population growth, they
did not consider how air quality will be affected by the
-74- additional traffic that will result if the Delphi Panel's
population growth forecasts are correct. Accordingly, they must
revise their analysis to address the foreseeable air quality
effects of the additional baseline and induced population growth
forecast by the Delphi Panel.
For the reasons set forth above, the traffic-generating
effects of the Delphi Panel's population growth forecasts
qualifies as significant information under NEPA and Defendants'
unexcused failure to disclose these effects in the FEIS was
arbitrary and capricious.37
4. Harmless Error
When an Article III court reviews a NEPA challenge under the
APA, the law requires that "due account shall be taken of the
rule of prejudicial error." 5 U.S.C. § 706. The First Circuit
37 CLF argues that the FEIS also fails to account for the significant effect that the Delphi Panel's forecasts have on the viability of rail as an alternative to highway expansion. I am unpersuaded by this argument. The TSA plausibly demonstrates that rail will not produce enough trip diversions from 1-93 to make rail a viable alternative to highway expansion. AR 26449. CLF has not produced sufficient evidence to call this conclusion into serious doubt. Accordingly, the Delphi Panel's population growth forecasts do not have a sufficient impact on Defendants' rail ridership projections to qualify the information as significant for this purpose.
-75- has applied this rule to excuse harmless procedural violations of
NEPA, and other circuit courts have relied on the rule in
rejecting challenges to an FEIS on the ground that it failed to
describe a preferred alternative or its environmental effects
with sufficient specificity. See Save Our Heritage. Inc. v. Fed.
Aviation Admin.. 269 F.3d 49, 61-63 (1st Cir. 2001); see also
Nevada v. Dep't of Energy. 457 F.3d 78, 90-91 (D.C. Cir. 2006);
Laguna Greenbelt, Inc. v. U.S. Dep't of Transp., 42 F.3d 317, 527
(9th Cir. 1994). Accordingly, although Defendants did not
present a harmless error argument, I consider on my own whether
Defendants' failure to account for the traffic-generating effects
of the Delphi Panel's population growth forecasts was harmless.
Defendants cannot rely on the fact that they discussed the
issue in the TSA to excuse their failure to directly address it
in the FEIS because the TSA was not subject to public comment.
See Idaho Sporting Congress. Inc. v. Alexander. 222 F.3d 562, 567
(9th Cir. 2000). CLF and other interested parties did not learn
either that Defendants' failure to account for the Delphi Panel's
population forecasts may have resulted in an understatement of
Defendants' traffic projections by as much as thirty percent, or
that the added traffic would produce a failing Level of Service
-76- south of Exit 1 and unacceptable Levels of Service between Exit 1
and Exit 3, until after Defendants released the TSA pursuant to a
Freedom of Information Act request, after the close of the
comment period on the FEIS. SR 913. Thus, the FEIS did not
disclose sufficient information on this issue to permit
meaningful public comment on either the effectiveness of the Four
Lane Alternative as a traffic congestion control measure or the
indirect effects that highway expansion could have on secondary
road traffic and air quality issues.38
38 CLF has produced an affidavit from its traffic consultant suggesting that further analysis of the ISA's modeling data indicates the traffic-inducing effect of the Delphi Panel's growth forecast is so severe that the section of 1-93 south of Exit 1 will experience failing Level of Service conditions well before 2020, even if the Four Lane Alternative is adopted. SR 915. The consultant also asserts that the Delphi Panel's induced population growth forecast produces enough additional traffic on secondary roads to negate the travel time benefits of expanding 1-93. SR 916-19. Because CLF was unable to engage in this analysis until after it obtained the TSA, its analysis is not in the public record and Defendants have not offered a specific response. I do not know whether these assertions have merit, and ultimately it will be up to Defendants to determine whether they are credible. What is important is that by failing to release the TSA for public inspection until after Defendants had made their decision to proceed with the Four Lane Alternative, the public was not able to provide the input on traffic issues that NEPA requires.
-77- Two purposes underlie NEPA's EIS requirement. First, the
EIS process is intended to ensure that "the agency, in reaching
its decision will have available, and will carefully consider,
detailed information concerning significant environmental impacts
. . . Robertson v. Methrow Valiev Citizen's Council. 49 0 U.S.
332, 349 (1989). Second, "it also guarantees that the relevant
information will be made available to the larger audience that
may also play a role both in the decisionmaking process and the
implementation of that decision." Id. Neither purpose would be
achieved in the present case if Defendants' errors were treated
as harmless. Accordingly, I conclude that Defendants' failure to
take account of the traffic-generating effects of the Delphi
Panel's population growth forecasts was not harmless error.
D. Miscellaneous Arguments
CLF also presents several arguments that cannot be easily
categorized. It argues that Defendants violated FAHA because the
Four Lane Alternative will not satisfy NHDOT's highway design
standards. Additionally, CLF complains that Defendants violated
NEPA by failing to consider the Four Lane Alternative in
conjunction with possible improvements to 1-93 in Massachusetts.
Finally, it faults Defendants for failing to propose effective
-78- mitigation measures. Because these arguments have been less well
developed in the briefs, I address them in a somewhat more
summary fashion.
1. FAHA
Defendants concluded in the FEIS that the segment of 1-93
south of Exit 1 will operate at LOS E during the Design Hour in
2020. AR 21783. They later determined in the TSA that if the
Defendants' traffic projections are modified to include the
results of the Delphi Study, the segment of 1-93 south of Exit 1
will operate at LOS F and the segment between Exits 1 and 3 will
operate at LOS E. AR 26448. Relying on the fact that NHDOT's
highway design standards generally require highways to be
designed to operate at LOS D or better, see AR 21777, CLF
contends that the Four Lane Alternative violates FAHA's
requirement that the Secretary of Transportation adopt
construction standards for the Interstate Highway System that,
"as applied to each actual construction project, shall be
adequate to enable such project to accommodate the types and
volumes of traffic anticipated for such project for the twenty-
year period commencing on the date of approval . . . ." 23
-79- U.S.C. § 109 (b) ,39
CLF has failed to cite any statute, regulation, or case to
support its conclusory assertion that the Four Lane Alternative
violates § 109(b) simply because it does not conform to NHDOT's
design standards. Section 109(b) requires the Secretary of
Transportation to adopt construction standards, but CLF does not
argue either that the Secretary has failed to adopt such
standards or that the Department's existing standards are somehow
inadequate. Nor has CLF presented any developed argument that
FHWA's approval of the Four Lane Alternative violates federal
design standards. These standards, which CLF does not even cite,
do not appear to require improvements to the interstate highway
system to conform to state design standards. See 23 C.F.R. §
625. Accordingly, I agree with Defendants that CLF lacks an
actionable claim under § 109(b).40
39 CLF appears to cite the same data in arguing that the Four Lane Alternative is an "imprudent" alternative that NEPA bars Defendants from selecting. To the extent that CLF makes this argument, it is clearly wrong. NEPA does not impose substantive standards. Robinson. 490 U.S. at 353 (citation omitted); Sierra Club v. Marsh. 872 F.2d 497, 502 (1st Cir. 1989) .
40 For the same reasons, I reject CLF's claim that Defendants violated FAHA by choosing 2020 as the Design Year for
-80- 2. Segmentation
CLF next argues that Defendants' decision to terminate the
Project at the Massachusetts border was the product of
"piecemeal, segmented planning" because the Route 213 interchange
in Massachusetts was a more logical terminus for the Project.
According to CLF, not only did Defendants realize that the state
line was an inferior project terminus, but they selected it in
order to avoid having to produce an SEIS that addressed more
thoroughly the impacts associated with extending the Project to
Route 213. I am unpersuaded by this argument.
"[A]n EIS is of proper geographic scope if the project it
analyzes connects ■'logical termini,' has 'independent utility'
and does not restrict 'consideration of alternatives.'"
Conservation Law Found.. 24 F.3d at 1472 (quoting FHWA
regulations embodying these requirements, 23 C.F.R. §
771.111(f)). Here, CLF appears to argue only that the Four Lane
Alternative does not satisfy the logical terminus requirement.
Thus, I focus my analysis accordingly.
the 1-93 project.
-81- In considering CLF's argument, I keep in mind the following
principle: "[t]hat a terminus is the most logical is not mandated
by the segmentation analysis--that analysis requires only that a
terminus be '■'logical." Vill. of Los Ranchos de Albuquerque v.
Barnhart, 906 F.2d 1477, 1483 (10th Cir. 1990)(emphasis added).
Thus, even if I were persuaded that the Route 213 interchange
were a more logical terminus, CLF cannot prevail unless
Defendants' choice of a different terminus was illogical. See
Here, Defendants offered reasons in the Administrative
Record for their decision which demonstrate that their choice of
terminus was logical. Specifically, Defendants explained in
their response to comments to the FEIS that 1-93 in northern
Massachusetts consists of six lanes near the state line and is
capable of providing eight lane capacity further south because
Massachusetts allows travel on the right shoulders during rush
hour. AR 26749-50. Thus, Defendants explained, additional
highway capacity existed south of the state line, and the Project
Area's four lane capacity creates an "obvious transportation
bottleneck" effect which would be alleviated by widening 1-93
-82- between Salem and Manchester. AR 26775. Additionally, in a June
2002 conference. Defendants reasoned that it was appropriate to
terminate the project at the state line because any work south of
the Massachusetts line would be out of NHDOT's control. AR
13076-77. Thus, Defendants concluded, the state line was a
logical terminus jurisdictionally. AR 13076-77. CLF has not
persuaded me that these reasons are illogical or that Defendants
manufactured them in bad faith simply to avoid having to prepare
an SEIS. Thus, CLF's segmented planning argument fails.41
3. Mitigation
CLF also argues that because Defendants failed to conduct
adequate assessments of the direct effects of the 1-93 project on
41 CLF also argues that in assessing the impacts of the I- 93 project. Defendants failed to adequately assess the cumulative impacts of the project in combination with two other projects: (1) the potential widening of 1-93 in Massachusetts between the state line and Andover, and (2) the possible construction of a new Exit 4A on 1-93 to provide access to Derry and Londonderry. I disagree. Defendants addressed impacts associated with both potential projects in the FEIS. AR 21957-59. While Defendants' cumulative impacts analysis with respect to these projects was fairly superficial, given the speculative nature of the two potential projects--and thus the lack of meaningful data available for analysis--! decline to conclude that Defendants' cumulative impacts analysis with respect to these two projects was deficient under NEPA.
-83- air quality, water quality, and wildlife. Defendants assessment
of measures to mitigate these impacts, and the mitigation
measures to which they committed, were also inadequate. Because
this is the sole basis of CLF's inadequate mitigation argument,
and because I hold that Defendants' assessment of direct
environmental impacts was adequate under NEPA and FAHA, I reject
CLF's argument on this point.
IV. CONCLUSION
Defendants erred when they chose to base the traffic
projections they disclosed in the FEIS on an outdated OEP
population growth forecast rather than their own experts' more
recent forecasts. As a result, they failed to consider in the
FEIS how the substantial additional traffic that results from the
use of the more recent forecasts affects both their assessment of
the Four Lane Alternative as a traffic congestion reduction
measure and the impact that the additional traffic will have on
secondary roads and air quality issues.
CLF argues that Defendants' errors require them to restart
the EIS process, reassess their decision to exclude rail as an
-84- alternative to highway expansion, and reanalyze the direct and
indirect environmental effects of the Four Lane Alternative on
land use, water quality, and wildlife. I disagree. The
Administrative Record demonstrates that Defendants made a careful
study of several rail options and reasonably concluded that rail,
either by itself or in combination with other alternatives, does
not produce enough trip diversions from 1-93 during peak traffic
periods to obviate the need for the Four Lane Alternative. The
TSA persuasively demonstrates that the use of the Delphi Panel's
population forecasts does not alter this conclusion.
The record also establishes that Defendants engaged in a
reasonably thorough analysis of both the direct and indirect
environmental effects of the Four Lane Alternative on land use,
water quality, and wildlife issues. No point would be served by
requiring Defendants to restart the EIS process. Instead, what
is required is an SEIS that specifically considers how the Delphi
Panel's population forecasts affect Defendants' analysis of both
the effectiveness of the Four Lane Alternative as a traffic
congestion reduction measure and the indirect effects of the
additional population predicted by those forecasts on secondary
-85- road traffic and air quality issues.
SO ORDERED.
/s/Paul Barbadoro____________ Paul Barbadoro United States District Judge August 30, 200 7
cc: Thomas Irwin, Esq. Bradford Kuster, Esq. Brian Toth, Esq. Beverly Toth, Esq. Beverly Li, Esq. Gretchen Leah Witt, AUSA Andrew Livernois, Esq. Edith Pacillo, Esq. Mark Hodgdon, Esq.
-86-
Related
Cite This Page — Counsel Stack
2007 DNH 106, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clf-v-fedl-highway-nhdot-nhd-2007.