Sierra Club v. John O. Marsh, Jr., Etc.

907 F.2d 210, 106 A.L.R. Fed. 487, 20 Envtl. L. Rep. (Envtl. Law Inst.) 21343, 31 ERC (BNA) 2128, 1990 U.S. App. LEXIS 10518, 1990 WL 85697
CourtCourt of Appeals for the First Circuit
DecidedJune 26, 1990
Docket90-1005
StatusPublished
Cited by55 cases

This text of 907 F.2d 210 (Sierra Club v. John O. Marsh, Jr., Etc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sierra Club v. John O. Marsh, Jr., Etc., 907 F.2d 210, 106 A.L.R. Fed. 487, 20 Envtl. L. Rep. (Envtl. Law Inst.) 21343, 31 ERC (BNA) 2128, 1990 U.S. App. LEXIS 10518, 1990 WL 85697 (1st Cir. 1990).

Opinion

SELYA, Circuit Judge.

This appeal marks the latest chapter in the encyclopedic saga chronicling the Sierra Club’s challenge to Maine’s development efforts on Sears Island, a 940-acre uninhabited land mass in upper Penobscot Bay. We find that the order appealed from — an order altering the conditions upon which a preliminary injunction was predicated but not affecting the operation of the injunction itself — does not fall within the purview *211 of 28 U.S.C. § 1292(a)(1) and is not otherwise immediately appealable. Hence, we leave the chapter largely unread and all but the introductory pages uncut.

I. BACKGROUND

To make a tedious tale tolerably terse, we eschew a lengthy historical narrative describing the trials and tribulations attendant to progress on the Sears Island project, secure in the certain knowledge that sources abound from which interested readers can quench their thirst for further detail. See, e.g., Sierra Club v. Marsh, 769 F.2d 868 (1st Cir.1985) (Sierra I); Sierra Club v. Secretary of Transportation, 779 F.2d 776 (1st Cir.1985) (Sierra II); Sierra Club v. Secretary of the Army, 820 F.2d 513 (1st Cir.1987) (Sierra III); Sierra Club v. Marsh, 701 F.Supp. 886 (D.Me.1988) (Sierra IV-A); Sierra Club v. Marsh, 872 F.2d 497 (1st Cir.1989) (Sierra IV-B); Sierra Club v. Marsh, 714 F.Supp. 539 (D.Me.1989) (Sierra IV-C); Sierra Club v. Marsh, No. 88-0116, slip op. (D.Me. Nov. 1, 1989) (unpublished) (Sierra IV-D). It is crucial for our purposes, nonetheless, to instill an understanding of the etiology of the order to which error is assigned.

Plaintiff-appellant Sierra Club (Club), a nonprofit interest group concerned with environmental preservation, has fought the planned transformation of Sears Island tooth and nail. Initially, this court concluded that because the project would require the developer, the state of Maine, to dredge the channel, clear the island and build a causeway connecting the island to the mainland, the National Environmental Policy Act, 42 U.S.C. §§ 4321-4347 (1982 & West Supp.1990) (NEPA), required the Federal Highway Administration (FHwA), a provider of project funding, to prepare an environmental impact statement (EIS). Sierra I, 769 F.2d at 882; see also Sierra II, 779 F.2d at 783-84 (requiring that appropriate causeway permits be procured). All work was halted. Eventually, FHwA and the Maine Department of Transportation (MDOT) adopted a final EIS and obtained all of the necessary permits from the United States Coast Guard and the Army Corps of Engineers (Corps). MDOT then proceeded to clear the site and started to build the causeway and cargo pier.

Plaintiff renewed its objections to continued development, this time asserting that the EIS neither adequately evaluated the environmental effects inherent in choosing the Sears Island site nor adequately explored other alternatives. Plaintiff also contended that a supplemental EIS (SEIS) was mandatory and should have been prepared. On these bases, the Club once again asked the district court to enjoin the work pendente lite.

At first, the district court denied the request for further injunctive relief. Sierra IV-A, 701 F.Supp. at 903. On appeal, we ordered reconsideration. Sierra IV-B, 872 F.2d at 504-05. The district court thereafter granted a preliminary injunction, finding that defendants (federal and state agencies and officials) had to comply more fully with three separate NEPA requirements. These related to (1) the need for an adequate evaluation of all reasonably foreseeable secondary impacts of developing a cargo terminal on Sears Island (the secondary impact requirement); (2) the need for an analysis and evaluation of all reasonable alternatives to the planned development (the reasonable alternative requirement); and (3) the need to study and cross-correlate newly emergent information to determine whether an SEIS was exigible (the SEIS requirement). See Sierra IV-C, 714 F.Supp. at 582-87. Noting that the other prerequisites to the issuance of interim injunctive relief were present, id. at 591-93, Judge Cyr enjoined the defendants from pursuing “all further project construction” pending either further order of court or compliance with NEPA, viz., satisfaction of the three enumerated requirements. See id. at 593. An order to this effect was entered on June 1, 1989. We shall from time to time refer to this unexpurgated injunction, and to the later amendment of it, by their respective entry dates. For ease in reference, we have excerpted the operative portions of the two orders and recorded them in an appendix hereto.

*212 Complaining that the district court had misapprehended the administrative record, the defendants moved for reconsideration. They also asked permission to supplement the Record. When the court allowed supplementation, the defendants provided additional record citations and supporting affidavits designed to demonstrate that suitable evaluations of all foreseeable secondary impacts and potential alternatives had taken place. See Sierra IV-D, slip op. at 6. The district court accepted the proffer, reconsidered the matter, reversed its field, and granted summary judgment in defendants’ favor on two of the three NEPA claims (the secondary impact requirement and the reasonable alternative requirement). To implement this decision, the court “amended” the June 1 order, leaving the injunction intact but making clear that it thereafter hung by but a single thread: proof of defendants’ compliance with the SEIS requirement. Phrased another way, as of the date of the reconsidered order (November 1, 1989), the injunction was dependent only on FHwA and the Corps assessing the new information anent Sears-port’s onshore acreage requirements and determining whether the new information was sufficiently significant as to demand preparation of an SEIS (and if it was, proceeding to formulate the SEIS). Id. at 26-27.

The Club seeks to appeal from the November 1 order. 1

II. APPEALABILITY

As a general rule, “it has been a marked characteristic of the federal judicial system not to permit an appeal until a litigation has been concluded in the court of first instance.” Director, O.W.C.P. v. Bath Iron Works Corp., 853 F.2d 11, 13 (1st Cir.1988) (quoting Radio Station WOW, Inc. v. Johnson, 326 U.S. 120, 123, 65 S.Ct. 1475, 1478, 89 L.Ed. 2092 (1945)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Calvary Chapel of Bangor v. Mills
984 F.3d 21 (First Circuit, 2020)
Rosie D. v. Baker
958 F.3d 51 (First Circuit, 2020)
In Re: Deepwater Horizon
Fifth Circuit, 2014
United States v. Philip Morris USA Inc.
686 F.3d 839 (D.C. Circuit, 2012)
Noonan v. Wonderland Greyhound Park Realty LLC
723 F. Supp. 2d 298 (D. Massachusetts, 2010)
Smeal Fire Apparatus Co. v. Kreikemeier
782 N.W.2d 848 (Nebraska Supreme Court, 2010)
Thomas v. Blue Cross and Blue Shield Ass'n
594 F.3d 823 (Eleventh Circuit, 2010)
Corey H. v. Board of Educ. of City of Chicago
534 F.3d 683 (Seventh Circuit, 2008)
United Keetoowah Band of Cherokee v. United States
247 F. App'x 150 (Tenth Circuit, 2007)
Pimentel & Sons Guitar Makers, Inc. v. Pimentel
477 F.3d 1151 (Tenth Circuit, 2007)
Rio Grande Community v. Commonwealth of PR
465 F.3d 33 (First Circuit, 2006)
In re Opinion of Judicial Conference Committee
342 F.3d 106 (U.S. Judicial Conference Committee, 2006)
Mendez v. Radec Corp.
411 F. Supp. 2d 347 (W.D. New York, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
907 F.2d 210, 106 A.L.R. Fed. 487, 20 Envtl. L. Rep. (Envtl. Law Inst.) 21343, 31 ERC (BNA) 2128, 1990 U.S. App. LEXIS 10518, 1990 WL 85697, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sierra-club-v-john-o-marsh-jr-etc-ca1-1990.