Rivers v. Commission

201 F.3d 1186
CourtCourt of Appeals for the Ninth Circuit
DecidedJanuary 14, 2000
DocketNos. 98-70079, 98-70084
StatusPublished
Cited by19 cases

This text of 201 F.3d 1186 (Rivers v. Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rivers v. Commission, 201 F.3d 1186 (9th Cir. 2000).

Opinion

ORDER

The Opinion filed August 11, 1999, slip op. 8973, and appearing at 187 F.3d 1007 (9th Cir.1999), is amended as follows:

At slip op. 8991, in the first sentence of the first full paragraph; 187 F.3d at 1016, in the first sentence of the first full paragraph, change “The petitioners contend” to “Petitioners contend that FERC ignores continuing impacts and the environmental impacts caused by ongoing operation. In effect, the petitioners contend”.

With this amendment, the panel has voted unanimously to deny the petitions for rehearing of respondent Federal Energy Regulatory Commission, petitioners American Rivers et al., respondent-intervenor Eugene Water and Electric Board, and the federal intervenors. Judges McKeown and Wardlaw have voted to reject the suggestions for rehearing en banc of respondent Federal Energy Regulatory Commission, petitioners American Rivers et al., and respondent-intervenor Eugene Water and Electric Board, and Judge Leavy has so recommended.

The full court has been advised of the suggestions for rehearing en banc and no active judge has requested a vote on whether to rehear the matter en banc. Fed. R.App. P. 35.

The petitions for rehearing are DENIED and the suggestions for rehearing en banc are REJECTED.

OPINION

WARDLAW, Circuit Judge:

At stake in these consolidated petitions is the continued operation of two hydro[1190]*1190electric power facilities located in Lane County, Oregon along a twenty-five mile stretch of the McKenzie River. The petitioners,1 a coalition of conservation/environmental organizations and the Oregon Department of Fish and Wildlife, challenge the decision of the Federal Energy Regulatory Commission (“FERC” or the “Commission”) to reissue a hydropower license to the incumbent licensee, the Eugene Water and Electric Board (“EWEB”).2 Specifically, the petitioners contend that the Commission granted the disputed license (i) without conducting the requisite environmental analysis under relevant provisions of the Federal Power Act (“FPA”), 16 U.S.C. § 791a et seq., and the National Environmental Policy Act (“NEPA”), 42 U.S.C. § 4321 et seq., and (ii) in violation of sections 10(j) and 18 of the FPA. For the reasons set forth below, we grant in part and deny in part the petitions for review.

I

The license under review authorizes the continued operation of the 14.5-megawatt Leaburg Hydroelectric Project and the 8-megawatt Walterville Hydroelectric Project for a duration of 40 years. See Eugene Water & Elec. Bd., 78 Fed. Energy Reg. Comm’n Rep. (CCH) ¶ 62,207, at 64,-693 (Mar. 24, 1997) (“Order Issuing New License ”).3 The Leaburg and Walterville faculties have operated since 1930 and 1911, respectively. The Commission’s predecessor, the Federal Power Commission, granted original FPA hydropower licenses to the WaltervUle development in 1967 and the Leaburg development in 1968. See In re City of Eugene, 37 F.P.C. 979 (May 23, 1967); In re City of Eugene, 39 F.P.C. 904 (June 3, 1968). Both licenses expired by their terms on December 31, 1993. After the licenses expired, EWEB managed both developments under separate annual licenses by operation of FPA section 15(a).4

The Leaburg development, the project’s upstream facility, consists of a dam, canal, powerhouse facilities, a tailrace, and a power substation. The dam creates a fifty-seven acre backwater called Leaburg Lake which extends approximately 1.5 miles upstream. On each side of the dam are fish ladders, only one of which is operational. On the upstream side of the dam, intake gates divert water through a downstream migrant fish screen into the five-müe Leaburg power canal. The diverted water passes through the power plant for-ebay into the two-turbine Leaburg powerhouse. The water returns to the McKenzie River through a 1,100-foot taürace. [1191]*1191The bypassed reach of the McKenzie between the entrance to the Leaburg canal and the point where the diverted water rejoins the river is 5.8 miles long.

Six miles downstream, headworks divert water from the McKenzie into the un-screened, four-mile Walterville power canal. The Walterville canal feeds into a single-turbine powerhouse from which water returns to the McKenzie through a two-mile tailrace. The Walterville canal bypasses a 7.3 mile stretch of the McKenzie.

The Director issued the disputed license on March 24, 1997, pursuant to the FPA.5 Section 4(e) of the FPA empowers the Commission to issue licenses for hydroelectric projects on waterways that are subject to congressional regulation under the Commerce Clause. See 16 U.S.C. § 797(e) (1994). Section 10(a) of the FPA authorizes the Commission to issue such licenses subject to conditions that the Commission finds best suited for power development and other public uses of the nation’s waters. See 16 U.S.C. § 803(a) (1994). In the mid-1980’s, Congress amended these provisions to realize an increased sensitivity to environmental concerns, directing the Commission to devote greater consideration to a project s overall effect on fish and wildlife. See Electric Consumers Protection Act of 1986 (“ECPA”), Pub.L. No. 99-495, 100 Stat. 1243 (1986) (codified principally at 16 U.S.C. §§ 797(e), 803(a)(1), 803(j)).6 The new license reflects many of these concerns and would require EWEB to construct several new facilities and provide other measures for the benefit and protection of the fish populations that pass through and reside in the project area. See Order Issuing New License, 78 Fed. Energy Reg. Comm’n Rep. (CCH) at 64,-706-719.7 From a power standpoint, the new license authorizes EWEB to increase the project’s generation capacity from 22.5 megawatts to 23.2 megawatts. See id. at 64,708. Under the terms of the license, EWEB would achieve this increased generation capacity by raising the water level at Leaburg Lake by 18 inches, constructing fixed sill dams or other diversion structures at the head of the Walterville power canal, replacing the turbine runners at both powerhouses, and excavating the Walterville tailrace. See id. at 64,701-703. The license also would increase the minimum flows8 in the bypassed reaches below the diversions of both developments to [1192]*11921,000 cubic feet per second. See id. at 64,703.

During the relicensing deliberations, the Director considered the final environmental impact statement prepared by the Commission’s environmental staff.9 The Commission’s staff issued the final environmental impact statement on January 8, 1997, after soliciting and receiving comments on a draft.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fall River Rural v. Ferc
Ninth Circuit, 2008
Powers v. Wells Fargo Bank NA
439 F.3d 1043 (Ninth Circuit, 2006)
Bpa v. Ferc
Ninth Circuit, 2005
Armstrong v. Davis
275 F.3d 849 (Ninth Circuit, 2002)
In Re: Gary Lazar
237 F.3d 967 (Ninth Circuit, 2001)
Consrvtn Law Fdn v. FERC
D.C. Circuit, 2000
Watkins v. California Dept. of Corrections
100 F. Supp. 2d 1227 (C.D. California, 2000)
United States v. Ernesto Ibarra-Galindo
206 F.3d 1337 (Ninth Circuit, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
201 F.3d 1186, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rivers-v-commission-ca9-2000.