FEDERAL · 16 U.S.C. · Chapter SUBCHAPTER I—REGULATION OF THE DEVELOPMENT OF WATER POWER AND RESOURCES

New licenses and renewals

16 U.S.C. § 808
Title16Conservation
ChapterSUBCHAPTER I—REGULATION OF THE DEVELOPMENT OF WATER POWER AND RESOURCES

This text of 16 U.S.C. § 808 (New licenses and renewals) is published on Counsel Stack Legal Research, covering United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
16 U.S.C. § 808.

Text

(a)Relicensing procedures; terms and conditions; issuance to applicant with proposal best adapted to serve public interest; factors considered
(1)If the United States does not, at the expiration of the existing license, exercise its right to take over, maintain, and operate any project or projects of the licensee, as provided in section 807 of this title, the commission is authorized to issue a new license to the existing licensee upon such terms and conditions as may be authorized or required under the then existing laws and regulations, or to issue a new license under said terms and conditions to a new licensee, which license may cover any project or projects covered by the existing license, and shall be issued on the condition that the new licensee shall, before taking possession of s

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Escondido Mutual Water Co. v. La Jolla Band of Mission Indians
466 U.S. 765 (Supreme Court, 1984)
156 case citations
Alcoa Power Generating Inc. v. Federal Energy Regulatory Commission
643 F.3d 963 (D.C. Circuit, 2011)
31 case citations
Klamath Water Users Ass'n v. Federal Energy Regulatory Commission
534 F.3d 735 (D.C. Circuit, 2008)
24 case citations
Rivers v. Commission
201 F.3d 1186 (Ninth Circuit, 2000)
19 case citations
Marseilles Land & Water Co. v. Federal Energy Regulatory Commission
345 F.3d 916 (D.C. Circuit, 2003)
9 case citations
Escondido Mutual Water Co. v. Federal Energy Regulatory Commission
692 F.2d 1223 (Ninth Circuit, 1982)
8 case citations
Turlock Irrigation District v. FERC
36 F.4th 1179 (D.C. Circuit, 2022)
7 case citations
Nebraska v. Rural Electrification Administration
23 F.3d 1336 (Eighth Circuit, 1994)
3 case citations
Hoopa Valley Tribe v. Federal Energy Regulatory Commission
629 F.3d 209 (D.C. Circuit, 2010)
2 case citations
Swinomish Tribal Community v. Federal Energy Regulatory Commission
627 F.2d 499 (D.C. Circuit, 1980)
2 case citations

Source Credit

History

(June 10, 1920, ch. 285, pt. I, §15, 41 Stat. 1072; renumbered pt. I, Aug. 26, 1935, ch. 687, title II, §212, 49 Stat. 847; Pub. L. 90–451, §3, Aug. 3, 1968, 82 Stat. 617; Pub. L. 99–495, §§4(a), (b)(1), 5, Oct. 16, 1986, 100 Stat. 1245, 1248.)

Editorial Notes

Editorial Notes

Amendments
1986—Subsec. (a). Pub. L. 99–495, §4(a), (b)(1), designated existing provisions as par. (1), substituted "existing" for "original" wherever appearing, and added pars. (2) and (3).
Subsecs. (b) to (f). Pub. L. 99–495, §§4(a), 5, added subsecs. (b) to (e) and redesignated former subsec. (b) as (f).
1968—Pub. L. 90–451 designated existing provisions as subsec. (a) and added subsec. (b).

Statutory Notes and Related Subsidiaries

Effective Date of 1986 Amendment
Amendment by Pub. L. 99–495 effective with respect to each license, permit, or exemption issued under this chapter after Oct. 16, 1986, see section 18 of Pub. L. 99–495, set out as a note under section 797 of this title.