Swinomish Tribal Community v. Federal Energy Regulatory Commission

66 A.L.R. Fed. 356, 627 F.2d 499, 10 Envtl. L. Rep. (Envtl. Law Inst.) 20628, 201 U.S. App. D.C. 40, 14 ERC (BNA) 1705, 1980 U.S. App. LEXIS 16447, 1980 WL 579572
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 20, 1980
DocketNos. 78-1659, 78-1949, 78-1957 and 78-1958
StatusPublished
Cited by2 cases

This text of 66 A.L.R. Fed. 356 (Swinomish Tribal Community v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Swinomish Tribal Community v. Federal Energy Regulatory Commission, 66 A.L.R. Fed. 356, 627 F.2d 499, 10 Envtl. L. Rep. (Envtl. Law Inst.) 20628, 201 U.S. App. D.C. 40, 14 ERC (BNA) 1705, 1980 U.S. App. LEXIS 16447, 1980 WL 579572 (D.C. Cir. 1980).

Opinions

Opinion for the Court filed by District Judge JOHN H. PRATT.

JOHN H. PRATT, District Judge:

This petition challenges the validity of orders1 by the Federal Energy Regulatory Commission (hereinafter “Commission”) approving an amendment to the license of the Department of Lighting of the City of Seattle (hereinafter “City”) for the Skagit River Project No. 553 in Washington State. Application for the amendment was made to the Federal Power Commission2 on December 17, 1970, more than 9 years ago. The orders under review raised the height of the present Ross Dam by 121 feet, thereby increasing the peaking capacity and energy output of the Ross Power Plant. The petitioners, all intervenors before the Commission, consist of three separate groups: the Swinomish Tribal CommunLy, Upper Skagit Tribe and Sauk-Suiattle Tribe, et al. (hereinafter “Tribes”), the North Cascades Conservation Council, et al. (hereinafter (“American Intervenors”) and the Run Out Skagit Spoilers Committee (R.O.S.S. Committee), et al. (hereinafter “Canadian Intervenors”). The principal intervenor3 on the side of the respondent Commission is City, a large municipally owned electric utility serving a total population of approximately 750,000 persons. The issues have been fully briefed and argued and for the reasons set forth hereafter, we affirm the orders of the Commission and dismiss the petition.

HISTORICAL BACKGROUND

The Skagit River rises in British Columbia, flows south across the international boundary and then west to its outlet in Puget Sound. Prior to 1920, when the Federal Water Power Act4 was passed, which required federal licensing of all hydro-electric projects on navigable waters of the United States, City had constructed the Gorge development on the Upper Skagit, consisting of a concrete arch dam with a capacity of 175 MW (megawatts). In 1927, City in Project No. 553 was licensed by the Commission to construct a second development at Diablo, upstream from Gorge, and consisting of a concrete arch dam with a capacity of 159 MW. This license for Project No. 553 was for a 50 year period and covered three Skagit River dams and power plants, known in order proceeding upstream as Gorge, Diablo and Ross. Ross, the largest, was proposed for construction in four stages as power needs required. It contemplated an ultimate reservoir elevation of 1725 feet above mean sea level. Stages 1 and 2 were authorized in 1937 and 1942. Stage 3, by virtue of several Commission orders, the latest being 1967, raised the water surface of the Ross reservoir to 1602.5 feet, the present level.

The fourth and final stage for increasing the height of the Ross Dam for which application to the Commission was made in 1970, would raise the water surface in the reservoir (hereinafter sometimes Ross Lake) to 1725 feet. The orders now under review concern the Commission’s approval of such construction (hereinafter High Ross).

[44]*44STATEMENT OF FACTS

The purpose of the High Ross amendment is to meet the growing energy needs of the Seattle area, served by City, its electric utility, and to provide sources of power important to the Pacific Northwest Power Pool. City’s present resources are insufficient to serve both peak and base energy demands and this shortage has had to be made up by purchases from the Bonneville Power Administration (BPA). City and other preference customers have already received notice from BPA that by 1983 BPA will not be able to meet the demands caused by preference customer growth. It does not appear to be seriously contested that City is confronted with prospects of an acute energy shortage and must act to increase its existing supplies.5

The present development at the Ross Dam consists of a dam with a current height elevation of 1615 feet above sea level and a powerhouse with four generating units with a capacity of 252 MW. The present height of Ross Lake, the reservoir, is 1602.5 feet and the Lake presently covers a surface area of 11,700 acres.

The proposed High Ross amendment, by adding 122V2 feet to the existing structure, would increase the present generating capacity of the Ross development from 252 MW to 525 MW, an increase of 273 MW. This enlargement of capacity will result from the increase in the hydraulic or pressure head available to rotate the hydro-electric turbines which will result from the greater storage capacity of Ross Lake. Raising the present Ross Dam to permit a reservoir elevation of 1725 feet, which is 122V2 feet above the present elevation of 1602.5 feet, will make available an additional 292,000 kilowatts of peaking capacity and 30,000 kilowatts of firm energy. At the same time, Ross Lake will inundate an additional 8320 acres, 4720 in Canada and 3600 in the United States.

Because the reservoir at the maximum elevation of 1602.5 presently extends into Canada about one mile covering 480 acres and because the proposed construction of High Ross will further increase the surface area of the reservoir, Canadian interests have been implicated since Project No. 553 was originally authorized in 1927.

The Canadian-American Waters Treaty of 1909, 36 Stat. 2448, established an International Joint Commission (hereinafter IJC) over waters flowing across the international boundary. Article IV of the Treaty prohibits construction of dams on one side of the boundary which would raise the natural water level on the other, unless approved by the IJC. City received IJC approval for High Ross in 1942, conditioned on City’s execution of a compensation agreement with the Province of British Columbia regarding the flooding of provincial lands. Work commenced on the initial stages of the Ross Dam and in 1947 the passage by the Province of the Skagit Valley Lands Act, authorized City to flood lands in the Province, subject to payment to be agreed upon. This resulted in a series of annual agreements, which covered inundation caused by the Ross reservoir to elevation 1602.5, the operating level of the third stage. In 1967, the Province and City executed a 99 year rental agreement to cover all lands in Canada flooded as the result of raising the surface of the Ross reservoir to elevation 1725. IJC approved this agreement, noting that the condition of its 1942 approval of High Ross had been met. Since 1967, City has been making annual rental payments of $34,566 as well as paying annual property taxes levied by the Province. The 1967 agreement permits the Province, at its option, to take such payments in electrical energy, which option has thus far not been exercised. To sum up, the present reservoir at elevation 1602.5 has a maximum surface of 11,700 acres, 480 acres of which are in Canada. High Ross with an elevation of 1725 will flood an additional 8320 acres, 4720 of which are in Canada. The present reservoir extends one mile into [45]*45Canada; the enlarged reservoir will extend seven miles into Canada.

To complete this factual recitation, it is appropriate to single out the specific Acts of Congress passed by the same Congress on October 2, 1968 and having a direct bearing on the present proposal. (1) Section 5(a)(24) of the Wild and Scenic Rivers Act (hereinafter WSRA), 16 U.S.C. § 1276(a)(24) designated portions of the Skagit River approximately 11 miles below City’s Gorge development for potential addition to the Wild and Scenic Rivers System established by the Act.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
66 A.L.R. Fed. 356, 627 F.2d 499, 10 Envtl. L. Rep. (Envtl. Law Inst.) 20628, 201 U.S. App. D.C. 40, 14 ERC (BNA) 1705, 1980 U.S. App. LEXIS 16447, 1980 WL 579572, Counsel Stack Legal Research, https://law.counselstack.com/opinion/swinomish-tribal-community-v-federal-energy-regulatory-commission-cadc-1980.