National Wildlife Federation v. Federal Energy Regulatory Commission, the City of Fort Smith, Arkansas, Intervenor

912 F.2d 1471, 286 U.S. App. D.C. 117, 115 P.U.R.4th 278, 20 Envtl. L. Rep. (Envtl. Law Inst.) 21098, 1990 U.S. App. LEXIS 12595
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 31, 1990
Docket88-1697
StatusPublished
Cited by36 cases

This text of 912 F.2d 1471 (National Wildlife Federation v. Federal Energy Regulatory Commission, the City of Fort Smith, Arkansas, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Wildlife Federation v. Federal Energy Regulatory Commission, the City of Fort Smith, Arkansas, Intervenor, 912 F.2d 1471, 286 U.S. App. D.C. 117, 115 P.U.R.4th 278, 20 Envtl. L. Rep. (Envtl. Law Inst.) 21098, 1990 U.S. App. LEXIS 12595 (D.C. Cir. 1990).

Opinion

Opinion for the Court filed PER CURIAM.

PER CURIAM:

The National Wildlife Federation, et al. (“NWF”) petitions for review of orders of the Federal Energy Regulatory Commission (“FERC” or “the Commission") granting to the City of Fort Smith, Arkansas, (“Fort Smith”) a license for the construction and operation of a dam on Lee Creek, near the Arkansas-Oklahoma border. Because a small hydroelectric powerhouse was to be built along the dam, FERC jurisdiction attached to the project which was undertaken primarily to satisfy the water-supply needs of Fort Smith. The questions presented for review are whether FERC, in granting the license, failed to comply with certain requirements, involving the consideration of the projected environmental impact of the proposed dam, of the Federal Power Act (“FPA”), 16 U.S.C. §§ 797(e), 803(a), and 803(j), the Clean Water Act (“CWA”), 33 U.S.C. § 1341, and the National Environmental Policy Act (“NEPA”), 42 U.S.C. § 4332(2)(C). We find no reason to disturb FERC’s actions and accordingly deny the petition for review.

I. BACKGROUND

In the late 1970s, Fort Smith, aware that its municipal water supply would not be able to meet the demands of its growing populace, decided to create a reservoir by building a dam on Lee Creek. Lee Creek flows south from Oklahoma into Arkansas, and the proposed dam was to be built in Crawford County, Arkansas, just south of the Oklahoma-Arkansas border. The proposed dam was to enable Fort Smith to construct a reservoir in Arkansas, but it was also going to flood parts of Oklahoma. In November 1983, Fort Smith sought from FERC a license to construct, operate and maintain a small hydroelectric generator at the proposed Lee Creek site.

As envisioned by Fort Smith, the proposed project was to be implemented in two phases. The initial phase (“Phase I”) was to allow for an approximately 10 million-gallon-per-day water supply. “Phase II,” the eventual extension of Phase I envisioned by Fort Smith, was further to increase substantially Fort Smith’s water supply. Phase II was to entail environmental costs over and above those of Phase I because the rise in the height of the dam would increase the total area of lands flooded, and would eliminate part of Lee Creek in Oklahoma, including several miles of an Oklahoma state-designated scenic river.

Because approval of the proposed project would constitute a major federal action “significantly affecting the quality of the human environment” within the meaning of NEPA, 42 U.S.C. § 4332(2)(C), FERC directed its staff to prepare an environmental impact statement (“EIS”) relating to the proposed dam. After a public hearing and a meeting with interested parties concerning the projected environmental impact of the proposed dam, FERC issued a draft EIS and solicited comments from interested parties and the public. In February 1987, FERC issued a final EIS in which it addressed many of the comments received in response to its draft EIS.

In March of 1988, although numerous objections to the proposed dam project remained, FERC granted Fort Smith’s license application with a few conditions and modifications. Order Issuing License (Minor), 42 FERC ¶ 61,361 (1988). FERC subsequently denied various requests for rehearing and upheld its grant to Fort Smith of a license to undertake the Lee Creek dam project. Order on Rehearing, 44 FERC ¶ 61,160 (1988). The State of Oklahoma and the Oklahoma Water Resources Board (collectively “Oklahoma”) petitioned this Court for review of FERC’s grant of the license, arguing that FERC had failed to comply with certain FPA and CWA requirements involving consideration of the environmental impact of the dam. NWF also petitioned this Court, raising most of Oklahoma’s FPA and CWA contentions, as well as other challenges based on the FPA and NEPA.

*1474 During the pendency of this litigation, Oklahoma and Arkansas agreed to a settlement which addressed many of Oklahoma’s concerns. Pursuant to Oklahoma’s request, this Court dismissed Oklahoma's petition with prejudice. NWF’s petition remains, however, and that petition raises substantially the same arguments as did Oklahoma’s petition.

First, NWF contends that FERC failed to consider adequately the potential environmental effects of Phase II of the dam project in deciding whether to approve Phase I of that project. FERC’s failure to take into account the environmental impacts of Phase II, according to NWF, violated both the FPA and NEPA. Second, NWF argues that FERC violated several other provisions of the FPA by failing to consider adequately and follow the recommendations of various relevant federal and state agencies and by including the water-supply gains from the dam as a benefit of the dam project to be weighed against the costs. Third, NWF argues that FERC violated section 401(a)(2) of the CWA by granting the Fort Smith license without requiring the city to obtain a water-quality certification from Oklahoma. Finally, NWF argues that FERC’s EIS did not comply with NEPA because the EIS failed to explore reasonable alternatives to the project and because the EIS was based in part on data compiled by a concededly interested party.

II.’ FERC’s Consideration of Phase II

Phase I of Fort Smith’s original dam proposal was designed to satisfy the municipality’s short term anticipated needs of about 10 million gallons per day, which required a reservoir water level of 420 feet above mean sea level. The project was to inundate approximately 3.7 miles of free-flowing stream habitat and approximately 1.5 miles, out of 49 miles, of Lee Creek that was listed in the Nationwide Rivers Inventory.

Fort Smith’s initial proposal also contemplated that average daily water consumption in the population served by Fort Smith would increase during the course of ten to fifteen years, requiring an expansion of the reservoir in Phase II. The Phase II expansion of the dam project, which was expected to yield about 70 million gallons per day of water, was to raise the water level to 462 feet above mean sea level, thereby flooding several more miles of Lee Creek, possibly including some river miles designated for protection by the Oklahoma legislature. The Phase II plans for eventual expansion of the reservoir were included in Fort Smith’s original dam proposal.

In the hearings before FERC many of the intervenors were not as concerned about Phase I as they were about the contemplated expansion of the reservoir built into Phase II of Fort Smith’s plan. In response to various intervenors’ concerns, Fort Smith resubmitted a modified license application which incorporated changes addressing some intervenors’ concerns and which specifically withdrew Fort Smith’s request for approval of its Phase II plans.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Wild Horse Preservation Campaign v. Vilsack
133 F. Supp. 3d 200 (District of Columbia, 2015)
Committee of 100 on the Federal City v. Foxx
87 F. Supp. 3d 191 (District of Columbia, 2015)
Sierra Club v. Federal Highway Administration
715 F. Supp. 2d 721 (S.D. Texas, 2010)
Wilderness Society v. Babbitt
District of Columbia, 2009
Wilderness Society v. Salazar
603 F. Supp. 2d 52 (District of Columbia, 2009)
Brady v. Federal Energy Regulatory Commission
416 F.3d 1 (D.C. Circuit, 2005)
Concerned Citizens Coalition v. Federal Highway Administration
330 F. Supp. 2d 787 (W.D. Louisiana, 2004)
Tomac v. Norton
240 F. Supp. 2d 45 (District of Columbia, 2003)
PIEDMONT ENVIRON. v. US Dept. of Transp.
159 F. Supp. 2d 260 (W.D. Virginia, 2001)
City of Williams v. Dombeck
151 F. Supp. 2d 9 (District of Columbia, 2001)
Consrvtn Law Fdn v. FERC
D.C. Circuit, 2000
Society Hill Towers Owners' Assn. v. Rendell
210 F.3d 168 (Third Circuit, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
912 F.2d 1471, 286 U.S. App. D.C. 117, 115 P.U.R.4th 278, 20 Envtl. L. Rep. (Envtl. Law Inst.) 21098, 1990 U.S. App. LEXIS 12595, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-wildlife-federation-v-federal-energy-regulatory-commission-the-cadc-1990.