Friends of the Ompompanoosuc, State of Vermont v. Federal Energy Regulatory Commission

968 F.2d 1549, 134 P.U.R.4th 574, 1992 U.S. App. LEXIS 15976
CourtCourt of Appeals for the Second Circuit
DecidedJuly 8, 1992
Docket1498, 1681, Dockets 92-4013, 92-4015
StatusPublished
Cited by52 cases

This text of 968 F.2d 1549 (Friends of the Ompompanoosuc, State of Vermont v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Friends of the Ompompanoosuc, State of Vermont v. Federal Energy Regulatory Commission, 968 F.2d 1549, 134 P.U.R.4th 574, 1992 U.S. App. LEXIS 15976 (2d Cir. 1992).

Opinion

ALTIMARI, Circuit Judge:

The Friends of the Ompompanoosuc, an environmental group, and the State of Vermont (collectively “Vermont” or “petitioners”) seek review pursuant to 16 U.S.C. § 825l (1988) of a decision and order of the Federal Energy Regulatory Commission (“FERC” or “Commission”), which denied their request for a hearing to reconsider FERC’s grant of a license for the construction and operation of a hydroelectric power station at Thetford Center Falls on the Ompompanoosuc River in Orange County, Vermont. Petitioners claim that FERC: (1) violated the Federal Power Act, 16 U.S.C. § 792 et seq. (1988) (“FPA”) by failing to consider relevant information in granting the license; (2) made findings unsupported by substantial evidence; (3) violated the National Environmental Policy Act, 42 U.S.C. §§ 4321 et seq. (1988) (“NEPA”) by not preparing an environmental impact statement (“EIS”); and (4) violated various federal regulations by not holding a public hearing, by not disseminating an environmental assessment supplement, and by not considering alternatives to granting the license.

For the reasons set forth below, we affirm.

BACKGROUND

In 1985, Richard Balagur applied for a license to build and operate a hydroelectric power facility (the “Project”) at Thetford Center Falls, also known as Great Falls, on the Ompompanoosuc River near Thetford Center, Vermont. The Project area, a sylvan setting in rural Vermont, includes the Great Falls, the Thetford Center Covered Bridge, and certain structures of historic interest. The Great Falls are Vermont’s only free-flowing falls next to a covered bridge. The site formerly contained a 100 foot Army Corps of Engineers hydropower dam which was breached in the 1920’s and not repaired.

According to the application, the license would allow Balagur to restore the dam by adding two to four feet of new material, so that the height of the dam would be raised to its historic level of 8.5 feet. As a result of this construction, the existing 2.6 acre reservoir at the site would be increased by 0.4 acres. The application also explained that a 400-foot long penstock would connect the dam to a 18-foot by 25-foot pow *1552 erhouse containing a 350 kilowatt generator.

In order to minimize adverse environmental effects and to preserve the historic and aesthetic qualities of the site, Bala-gur’s application proposed a number of “mitigation” measures. Among other things, Balagur proposed that minimum flows be maintained over the falls, construction activities be kept away from the Thetford Center Covered Bridge as well as from historic ruins and archaeologicabsites, that the powerhouse be built behind a screen of trees, that the transmission wires be buried, and that a brick or wood facing be put on the dam and the powerhouse to blend these structures with the surroundings.

After receiving the application, FERC also received comments from local, state, and federal agencies. The Commission also obtained comments on the application from local citizens and citizens groups, including petitioner Friends of the Ompompa-noosuc, and from petitioner State of Vermont. Based on these comments and on other information in the record regarding the project and its environmental impact, FERC issued an environmental assessment (“EA”) in 1987. The EA concluded that the Project would be useful in meeting power needs and that Balagur’s proposed miti-gative measures in Project design and construction would minimize adverse environmental effects, such as decreased scenic attractiveness and reduced recreational opportunities, to acceptable levels. Accordingly, the EA found that the Project “would not constitute a major federal action significantly affecting the quality of the human environment.” As a result of this determination, an environmental impact statement was not necessary for the Project. See 40 C.F.R. § 1508.13 (1991). In addition, a Safety and Design Assessment accompanying the EA found that the Project could be produced safely, in accordance with water resource development plans, and that power could be successfully marketed.

Based on additional comments and information received after release of the EA, including submissions by petitioners, and on further mitigation measures proposed by Balagur, FERC issued an environmental assessment supplement (“EA Supplement”). The EA Supplement addressed petitioners’ concerns that the Project, among other things, was inconsistent with existing state environmental plans, and that the Project would have serious adverse effects on recreation, particularly swimming. The EA Supplement adhered to the EA’s finding that the Project-would not have a significant impact on the quality of the human environment.

As a result of the EA and the EA Supplement, FERC issued an order in May 1989 granting Balagur a license for the Project. In its order, the Commission weighed and rejected claims that the Project would destroy the Great Falls and its environs as a visual, cultural, historical, and recreational resource. FERC also found no conflict between the Project and existing state environmental plans. However, to minimize disruption to the environment, FERC conditioned the license on the implementation of mitigative measures, including setting minimum flow requirements for the falls which would approximate natural flows during the summer and fall, the busiest season for the Falls, and requiring continued public access to the Falls.

After FERC issued the license, Vermont petitioned for rehearing and reconsideration, claiming a variety of procedural and substantive irregularities in licensing the Project. Among other things, Vermont contended that FERC failed to give adequate consideration to state comprehensive environmental programs; that substantial evidence did not support FERC’s findings regarding the effect of reduced flow rates over the Falls; and that FERC improperly failed to perform an environmental impact statement, i.e., that the EA and EA Supplement were defective in finding that the Project would have no significant impact to the human environment.

In a reasoned opinion, FERC rejected these challenges. In so doing, however, FERC further required, as a condition of the license, that Balagur study alternative *1553 sites and prepare a plan for the development of a swimming area to replace the “popular swimming hole” that would be lost. Petitioners remained unmollified, and this appeal followed.

DISCUSSION

I. Consideration of Relevant Factors Under The FPA.

A. Uniqueness, Local Import, and Opposition.

Under the Public Utility Regulatory Policies Act of 1978, 16 U.S.C. § 824a-3 et seq.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maflahi v. United States
S.D. New York, 2024
Town of Southold v. Wheeler
48 F.4th 67 (Second Circuit, 2022)
Twp. of Bordentown v. Fed. Energy Regulatory Comm'n
903 F.3d 234 (Third Circuit, 2018)
Vermonters for a Clean Environment, Inc. v. Madrid
73 F. Supp. 3d 417 (D. Vermont, 2014)
Center for Food Safety v. Salazar
898 F. Supp. 2d 130 (District of Columbia, 2012)
Koffi v. Holder
487 F. App'x 658 (Second Circuit, 2012)
Delaware Audubon Society v. Salazar
829 F. Supp. 2d 273 (D. Delaware, 2011)
233 East 69th Street Owners Corp. v. Lahood
797 F. Supp. 2d 326 (S.D. New York, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
968 F.2d 1549, 134 P.U.R.4th 574, 1992 U.S. App. LEXIS 15976, Counsel Stack Legal Research, https://law.counselstack.com/opinion/friends-of-the-ompompanoosuc-state-of-vermont-v-federal-energy-regulatory-ca2-1992.