Harriet F. Laflamme v. Federal Energy Regulatory Commission, Joseph Keating , Respondent-Intervenor

852 F.2d 389
Court of Appeals for the Ninth Circuit·Decided July 5, 1988·No. 85-7571·Published·Cited by 82 cases

Opinion

ORDER

In LaFlamme v. FERC, 842 F.2d 1063 (9th Cir.1988) we vacated FERC’s order *391 issuing a license to Joseph M. Keating for Sayles Flat Project No. 3195 for the construction, operation and maintenance of a diversion dam, reservoir intake, 4,000 foot steel pen stock, power house and generating units, transformer transmission line and appurtenant facilities. We vacated the license because of the Federal Energy Regulatory Commission’s (FERC) failure to comply with the requirements of the Federal Power Act (FPA), the National Environmental Policy Act (NEPA), and all applicable regulations regarding the Sayles Flat Project’s recreational use and visual quality, cumulative impact and need for a comprehensive plan.

Intervenor has now filed a petition for rehearing requesting that we modify our opinion and not vacate the license pending completion of the required analysis by FERC on remand, thereby allowing operation of the Sayles Flat Hydroelectric Plant during the remand. Intervenor states that the Sayles Flat Project is substantially complete and that prohibition on operation will cause irreparable harm to intervenor and, finally, that the operation will not interfere with FERC’s decision making or result in harm to the environment.

FERC responded to the petition for rehearing stating that under certain conditions it had no objection to allowing, the intervenor to operate the Project while FERC is conducting proceedings on remand pursuant to our opinion. However, FERC noted that the court must somehow alter its opinion so that the license remains intact on remand, if not, the Project operators would be in violation of § 23b of the Federal Power Act, 16 U.S.C. § 817 (1982). FERC also asserts that if the court simply preserves the original license, the Commission could arguably find itself bound by the terms and conditions presently in the license and, therefore, without sufficient authority to fulfill our mandate by protecting the environment with appropriate interim measures.

We also note that after the matter was submitted FERC, on October 20, 1987, issued an order approving a pre-project recreation use and visual quality study, and in that order has apparently increased and possibly doubled proposed minimum water flows to be released during the operation of the Project. FERC has amended the Sayles Flat Project license to establish those increaséd flow releases; to require the filing with FERC of a plan and schedule determining a ramping rate (the maximum rate of change in river flow due to project operation); and to establish a maximum pool elevation. We also note that on July 23, 1986, FERC prepared a cumulative impact study entitled “Environmental Assessment of Potential Cumulative Impacts Associated with Hydropower Development in the South Fork of the American (SO-FAR) Basin, California” (EA), with regard to five other hydroelectric projects in the same basin where the Sayles Flat Project is located. While the July 23,1986 EA specifically discussed the proposed hydropower projects for Pyramid Creek, Foot Trail, Upper Rock Creek, Frye Creek and Twenty-Nine Mile Creek, it also made limited reference to the Sayles Flat Project but did not make the required analysis with regard to Sayles Flat as required by our opinion.

In its order of August 23, 1985, denying LaFlamme a rehearing, FERC amended the Sayles Flat license adding Article 44 requiring a “recreation use-visual quality study”. We make no findings as to whether FERC’s order approving the Pre-Project Recreational Use and Visual Quality Study or the July 23, 1986, EA satisfy the requirements of our remand. Neither documents were considered on August 23, 1985, when FERC entered an order rejecting all of LaFlamme’s arguments and denied her petition for rehearing, nor were they in existence when the license was issued to Keating. In accordance with the reasoning in our opinion this subsequent documentation may be considered by FERC on remand with regard to the requirements of NEPA and FPA.

Intervenor states that because the Federal Power Act, 16 U.S.C. § 806, requires the licensee to commence construction within two years of the date of the issuance of the license, he was faced with the necessity of going forward with the construction of the *392 Project to meet the deadlines of the Federal Power Act. Relying on Forelaws on Board v. Johnson, 743 F.2d 677 (9th Cir.1984), intervenor asserts that the power project is completed and we should not vacate the license. In Forelaws the Bonneville Power Administration (BPA) argued that it did not prepare an Environmental Impact Statement (EIS) prior to offering long term contracts for power delivery pursuant to the Pacific Northwest Electric Power Planning & Conservation Act (Regional Act), 16 U.S.C. § 839-39h (1982), because Congress had mandated that within 21 months of the Act’s effective date, a new system of contracts allocating BPA’s supply of hydropower was to be in place. BPA argued that the statutory deadlines for contract offer and acceptance made it impossible to prepare an EIS. We found, in fact, that the statute did not mandate the schedule which BPA followed and we refused to enjoin the contracts pending the completion of the EIS. Forelaws is clearly distinguishable because of “clear tension between NEPA’s charge to the agency to evaluate the effects of action upon the environment and the command of the Regional Act that the contracts be in place within 21 months of its passage.” Forelaws, 743 F.2d at 686. Such statutory conflict does not exist between NEPA and the Federal Power Act under which the Sayles Flat Project was issued a license.

Free access — add to your briefcase to read the full text and ask questions with AI

Harriet F. Laflamme v. Federal Energy Regulatory Commission, Joseph Keating , Respondent-Intervenor, 852 F.2d 389 (9th Cir. 1988).

852 F.2d 389 (Harriet F. Laflamme v. Federal Energy Regulatory Commission, Joseph Keating , Respondent-Intervenor) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Earth Island Institute v. Usfs
87 F.4th 1054 (Ninth Circuit, 2023)
Aqualliance v. U.S. Bureau of Reclamation
287 F. Supp. 3d 969 (E.D. California, 2018)
In Defense of Animals v. United States Department of the Interior
909 F. Supp. 2d 1178 (E.D. California, 2012)
Ocean Mammal Institute v. Gates
546 F. Supp. 2d 960 (D. Hawaii, 2008)
Citizens for Better v. US Dept. of Agriculture
497 F. Supp. 2d 1062 (N.D. California, 2007)
Born Free USA v. Norton
278 F. Supp. 2d 5 (District of Columbia, 2003)
Georgia River Network v. U.S. Army Corps of Engineers
334 F. Supp. 2d 1329 (N.D. Georgia, 2003)
Border Power Plant Working Group v. Department of Energy
260 F. Supp. 2d 997 (S.D. California, 2003)