City of Centralia v. Federal Energy Regulatory Commission

213 F.3d 742, 341 U.S. App. D.C. 385, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20675, 2000 U.S. App. LEXIS 12826, 2000 WL 687704
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 9, 2000
Docket99-1273
StatusPublished
Cited by1 cases

This text of 213 F.3d 742 (City of Centralia v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Centralia v. Federal Energy Regulatory Commission, 213 F.3d 742, 341 U.S. App. D.C. 385, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20675, 2000 U.S. App. LEXIS 12826, 2000 WL 687704 (D.C. Cir. 2000).

Opinion

Opinion for the Court filed by Chief Judge HARRY T. EDWARDS.

HARRY T. EDWARDS, Chief Judge:

The City of Centraba, Washington (“Centraba”) brings this petition for review to challenge an order of the Federal Energy Regulatory Commission (“FERC” or “Commission”) requiring Centraba to conduct a study of thé effects of the Yelm Hydroelectric Project on the anadromous fish in the Nisqually River. Centraba filed an application in 1989 for a bcense to operate the existing Yelm Hydroelectric Project. The National Marine Fisheries Service (“NMFS”) recommended that FERC require Centraba to construct a tailrace barrier to prevent harm to the river’s anadromous fish population. The Acting Director of Hydropower Licensing determined that the cost of constructing a tailrace barrier could not be justified, because the benefits of the barrier had not been demonstrated. He held, however, that a study should be undertaken to determine whether, and to what extent, the Project was harmful to the fish. FERC,-with two Commissioners dissenting, denied Centraba’s petition for rehearing. Centra-ba now petitions for review.

Under sections 4(e) and 10(a) of the Federal Power Act (“FPA” or “Act”), 16 U.S.C. §§ 797(e), 803(a), as amended by the Electric Consumers Protection Act (“ECPA”), Pub.L. No. 99-495, 100 Stat. 1243 (1994), FERC must balance power and non-powér values when deciding whether to issue hydropower licenses. In this case, Centraba contends that the Commission’s order • requiring a study should be vacated, because FERC failed to accurately weigh the high cost of the study against the negligible benefits to be derived from the study. We agree. FERC does not dispute that the study will cost Centraba up to $300,000 to determine whether a tailrace barrier costing $1,000,-000 should be constructed. FERC also concedes that the study could prove inconclusive. In addition, FERC has no meaningful hard evidence to prove that the hydroelectric project is harmful to fish. In contrast, the Nisqually Indian Tribe *744 (“Tribe”), which operates a fishery on the river, has submitted concrete data to show that no real harm to the fish results from the Project. In short, the record in this case does not support either the construction of a tailrace barrier or a study to determine its feasibility. Accordingly, the petition for review is granted.

I. Backgbound

Centraba operates the Yelm Hydroelectric Project along the Nisqually River. In the late 1970s, the Nisqually Indian Tribe, which operates a fishery along the Nisqually River, filed a complaint claiming that the Yelm Project was harming the fishery. Centraba and the Tribe subsequently commenced negotiations in an effort to settle the Tribe’s claims. In 1985, in a separate proceeding, FERC determined that Centraba, which had been operating the Yelm Project since 1930 without a bcense, was required to file for a bcense. Centraba submitted a bcense application in 1989.

The Tribe and Centraba finally reached a settlement in 1991. See Stipulation and Settlement Agreement between the City of Centraba and the Nisqually Indian Tribe, Executed Feb. 28, 1991, reprinted in Joint Appendix (“J.A.”) 88. Centraba agreed to provide the Tribe with money, land, and other concessions in exchange for the Tribe’s support in its bcense appbcation with FERC. Centraba also agreed to achieve a minimum flow in the river.

In the original settlement between Cen-traba and the Tribe, Centraba agreed to construct a tailrace barrier. Not long after the settlement was signed, however, the Tribe submitted a letter to Centraba stating that it did not believe that a tail-race barrier was either necessary or desirable. See Letter from Dorian S. Sanchez, Chairman, Nisqually Indian Tribe to Wil-bam C. Cummings, Director, Centraba City Light (July 25, 1991), reprinted in J.A. 103. The letter noted that, “since minimum flows were established in 1977,” the Tribe had “not documented any delay problems at the powerhouse.” Id. at 2, reprinted in J.A. 104. Moreover, the letter stated that a tabrace barrier would “have an immediate and ongoing negative impact on fisheries habitat.” Id. Finally, the letter acknowledged that, in lieu of constructing a tailrace barrier, Centraba had committed to contribute an amount equal to one-half the cost of a tailrace barrier to support fisheries enhancement projects within the Nisqually River basin. Id. The Tribe viewed these other fisheries enhancements as “much more beneficial” than a tailrace barrier. Id. On this last point, the letter noted that

[t]he Nisqually Tribe’s 1990 settlement agreement with Centraba calls for Cen-traba to construct a tailrace barrier. This portion of the agreement was based on the assumption that a tailrace barrier would be required of Centraba by FERC; it was not based on a lengthy analysis of the need for the barrier and should not be used by FERC or other agencies as a basis for requiring such a barrier. If the tailrace barrier is not imposed by FERC, Centraba and the Nisqually Tribe will meet to modify the settlement agreement to provide additional funding for fisheries enhancement.

Id. at 2-3, reprinted in J.A. 104-05. Subsequently, in a response to FERC’s request for additional information, Centraba maintained that a tailrace barrier would not be in the public interest, both because of its “high cost” and the “absence of any reliable data to support the need for the barrier.” See Centraba’s Response to Enclosure B of FERC Staff Letter Dated April 12,1991, reprinted in J.A. 111.

Meanwhile, as Centraba and the Tribe moved to avoid construction of a tailrace barrier, officials from NMFS pressed a different view. NMFS recommended to FERC that, as a condition of any bcense, Centraba should be required to build a tailrace barrier to protect the fish. See Letter from Dean L. Shumway, Director, Division of Project Review, FERC to Merritt E. Tuttle, Division Chief, NMFS (Mar. 23, 1992), reprinted in J.A. 169 (noting NMFS’ recommendations). On March 16, *745 1992, however, FERC issued an Environmental Assessment for the license and determined that a tailrace barrier was not justified. See Environmental Assessment for Hydropower License, Yelm Project, Mar. 16, 1992, 22-23, reprinted in J.A. 115, 141-42. The Assessment noted that fish could certainly be attracted to “the high velocity of the tailrace discharge flows” which could delay migration or could injure or Mil the fish, and that a tailrace barrier would prevent those“harms. Id: at 22, reprinted in J.A. 141. But, the 'Assessment stated, no “site-specific studies have been completed that quantify the numbers, if any, of salmon delayed in their upstream migration ... or the numbers that are injured or Mlled.” Id. The Assessment also noted the Tribe’s findings that minimum flow had reduced the problem and that large numbers of salmon had successfully migrated past the Project without a tailrace barrier. The Assessment concluded:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Transmission Company v. FERC
988 F.3d 471 (D.C. Circuit, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
213 F.3d 742, 341 U.S. App. D.C. 385, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20675, 2000 U.S. App. LEXIS 12826, 2000 WL 687704, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-centralia-v-federal-energy-regulatory-commission-cadc-2000.