City of Oconto Falls v. Federal Energy Regulatory Commission

204 F.3d 1154, 340 U.S. App. D.C. 266, 2000 U.S. App. LEXIS 3482
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 7, 2000
Docket98-1594, 99-1065
StatusPublished
Cited by12 cases

This text of 204 F.3d 1154 (City of Oconto Falls v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Oconto Falls v. Federal Energy Regulatory Commission, 204 F.3d 1154, 340 U.S. App. D.C. 266, 2000 U.S. App. LEXIS 3482 (D.C. Cir. 2000).

Opinion

Opinion for the court filed by Circuit Judge KAREN LeCRAFT HENDERSON.

KAREN LeCRAFT HENDERSON, Circuit Judge:

On November 13, 1997 the Federal Energy Regulatory Commission (Commission, FERC) issued a license order awarding the Oconto Falls (Wisconsin) hydroelectric project to N.E.W. Hydro (NEW). See 81 FERC ¶ 61,238 (1997). Both the City of Oconto Falls (City) and the Wisconsin Department of Natural Resources (WDNR) challenge the Commission’s action. WDNR argues that the Commission breached its statutory obligation under section 10(j) of the Federal Power Act (FPA), 16 U.S.C. § 803(j), to give “due weight” to WDNR’s recommendations to protect fish. The City argues that the Commission improperly determined that: (1) the City’s license application was “essentially equal” to NEW’s application under section 15(a)(2) of the FPA, 16 U.S.C. § 808(a)(2); (2) the Commission’s “first to file” tie-breaker procedure applied; and (3) NEW’s application need not be dismissed for anticompetitive activity with Wisconsin Electric Power Company, allegedly resulting from the Commission’s licensure of NEW. In turn, the Commission challenges the court’s jurisdiction over WDNR’s petition for review because WDNR identified only the rehearing order, 85 FERC 1161,222 (1998), not the license order in its petition. For the reasons set forth infra, we conclude that we have jurisdiction to review WDNR’s petition and, based on our review, the Commission satisfied its duty under section 10(j) of the FPA to give WDNR’s recommendations “due weight.” We further conclude that the Commission’s factual determination that both NEW’s and the City’s applications were “essentially equal” is supported by substantial evidence, that the “first to file” tiebreaker procedure did not unfairly prejudice the City and that the Commission correctly declined to dismiss NEW’s application. Accordingly, we deny both WDNR’s and the City’s petitions for review.

I.

In 1977 the Federal Power Commission issued Wisconsin Electric Power Company (WEPCO) a license to operate a hydroelectric project (Oconto Falls Project) located on the Oconto River near Oconto Falls, Wisconsin, to expire Decern- *1158 ber 31, 1993. In 1988 WEPCO filed a notice of intent to refile an application for relicensure but it failed to file its application before the December 31, 1991 deadline. Instead, WEPCO initiated discussions to sell the Oconto Falls Project to NEW. The sale was not completed by the December 31, 1991 deadline, however, and because no other party filed a notice of intent to file an application, the Oconto Falls Project became orphaned. 1 In February 1992 the Commission issued a public notice pursuant to Part I of the FPA, 16 U.S.C. §§ 791a-823a, to solicit license applications. At that time NEW informed the Commission of its intent to file an application. In May 1992 the City informed the Commission of its intent to file a competing application. In addition the City petitioned FERC for an order declaring that any license application for the Oconto Falls Project was subject to a municipal preference pursuant to section 7(a) of the FPA, 16 U.S.C. § 800(a). 2 The Commission ruled instead that section 15 of the FPA, 16 U.S.C. § 808, governs an orphan proceeding and therefore declared the municipal preference inapplicable. 3 This court subsequently affirmed the Commission’s decision. See Oconto Falls v. FERC, 41 F.3d 671, 674-75 (D.C.Cir.1994).

In the meantime WEPCO accepted NEW’s offer to acquire the Oconto Falls Project conditioned on NEW’s licensure by the Commission. See License Order, 81 FERC at 61,982. On August 21, 1992 NEW requested the Commission to waive the “first stage” pre-filing consultation requirement to provide “the relevant Federal, State and interstate resource agencies” detailed studies, data and documentation on the Oconto Falls Project, see 18 C.F.R. § 16.8(a)(1), (b), inasmuch as WEPCO had already completed the consultation requirement and had transferred all of the relevant materials to NEW. On September 1, 1992 the Commission Director granted NEW’s request. In November 1992 the City requested a copy of WEP-CO’s Initial Consultation Package (ICP), which contained not only WEPCO’s detailed studies and data but also the resource agencies’ comments detailing the studies and methodologies they recommended WEPCO to use. NEW planned to use WEPCO’s ICP to prepare its license application but WEPCO refused to make it available. The City subsequently petitioned the Commission for a copy of WEP-CO’s ICP to obtain the data it needed to prepare its application. In August 1993 NEW filed an application for a license with the Commission. Two months later the Commission ordered WEPCO to make its ICP publicly available and it did so in November 1993. Finally, in August 1994 the City filed a competing application for licensure with the Commission. Several months later, while the applications were pending, the City filed a complaint with FERC alleging anticompetitive activity by NEW and WEPCO, asking the Commission both to order them to cease the activity and to dismiss NEW’s application.

Pursuant to section 10(j) of the FPA, the Commission must include as license conditions any recommendations from “State fish and wildlife agencies” unless the Commission determines that the recommended conditions are “inconsistent with the pur *1159 poses and requirements” of the FPA or other laws. 16 U.S.C. § 80S(j)(l), (2). During the licensing process, WDNR recommended that the Oconto Falls Project licensee be required to reduce fish entrainment, i.e., their passage into and through the turbines of the hydroelectric project. On November 13, 1997 the Commission issued an order granting NEW the Oconto Falls Project license. See 81 FERC ¶ 61,-238 (1997) (License Order). The Commission concluded that both NEW’s and the City’s license applications were essentially equal, that the “first to file” tie-breaker procedure was appropriate under the circumstances and that NEW and WEPCO had not engaged in anticompetitive activity. After finding no evidence that entrainment significantly adversely affected the fish populations, the Commission also declined to impose WDNR’s proposed conditions to reduce fish entrainment. On November 13, 1998 the Commission denied both WDNR’s and the City’s petitions for rehearing. See 85 FERC ¶ 61,222 (1998) (Rehearing Order). The City then petitioned for review of the Commission’s License Order and Rehearing Order while WDNR petitioned the Seventh Circuit for review of the Commission’s Rehearing Order.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
204 F.3d 1154, 340 U.S. App. D.C. 266, 2000 U.S. App. LEXIS 3482, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-oconto-falls-v-federal-energy-regulatory-commission-cadc-2000.