Port of Seattle v. Pollution Control Hearings Board

90 P.3d 659, 151 Wash. 2d 568
CourtWashington Supreme Court
DecidedMay 14, 2004
DocketNo. 73419-4
StatusPublished
Cited by216 cases

This text of 90 P.3d 659 (Port of Seattle v. Pollution Control Hearings Board) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Port of Seattle v. Pollution Control Hearings Board, 90 P.3d 659, 151 Wash. 2d 568 (Wash. 2004).

Opinion

Bridge, J.

Construction of the third runway at the Seattle-Tacoma International Airport (SeaTac) will require placing fill into area wetlands. Before the Army Corps of Engineers may issue a permit to fill wetlands, the project proponent must obtain certification from the State, pursuant to § 401 of the Clean Water Act (33 U.S.C. § 1341), stating that there is reasonable assurance that the project will not violate applicable state water quality standards. On September 21, 2001, the Washington State Department of Ecology issued a § 401 water quality certification to the Port of Seattle (Port) for the third runway project. The Airport Communities Coalition (ACC) appealed the certification to the Pollution Control Hearings Board (PCHB). After a lengthy hearing, the PCHB affirmed the certification but added 16 new conditions it deemed necessary for reasonable assurance that state water quality standards would be met. All parties appealed and this court accepted direct review of the PCHB decision. We conclude that there is reasonable assurance that the third runway project will not violate state water quality standards. We uphold some of the PCHB’s additional conditions but reverse others.

I

Facts and Procedural History

In 1996, after years of study and debate, the Puget Sound Regional Council determined that a third runway was [580]*580needed at SeaTac. In response, the Port developed a master plan update for SeaTac, which includes a new 8,500-foot parallel runway to be constructed in the Miller Creek, Walker Creek, and Des Moines Creek watersheds. All three creeks are classified as class AA waters, affording them the highest protection available in the state. The third runway project will fill all or portions of 50 wetlands within those watersheds. The PCHB found:

The site of the proposed Third Runway is currently a wooded canyon encompassing Miller Creek, the bottom of which lies approximately 150 feet below the level of the Airport’s existing runways. To provide the site for the Third Runway, the Port proposes to fill the canyon with over twenty (20) million cubic yards of fill.

Airport Cmtys. Coalition v. Dep’t of Ecology, PCHB No. 01-160, at 12, 2002 WL 1875289, at *6, Findings of Fact, Conclusions of Law, and Order at 12 (Aug. 12, 2002) (PCHB Dec.). On October 25, 2000, the Port submitted a joint aquatic resource permit application (JARPA) to the Army Corps of Engineers and to the Washington State Department of Ecology (Ecology), pursuant to § 404 of the Clean Water Act (33 U.S.C. § 1344). The Port’s JARPA also constituted an application to Ecology for certification that the Port’s plan complies with applicable water quality laws, as required by § 401 of the Clean Water Act (33 U.S.C. § 1341).1

The Port submitted to Ecology numerous reports and studies on the impact of the third runway on various aspects of water quality. Ecology conducted a series of public hearings and proceeded with an in depth review of the Port’s plan. Ecology issued a § 401 certification on August 10, 2001, and ACC and the Port appealed that certification to the PCHB. After negotiations between the Port and Ecology, Ecology rescinded its August certification and issued a new § 401 certification on September 21, 2001. Ecology issued the new § 401 certification as an order under chapter 90.48 RCW, thereby ensuring that its conditions [581]*581would be enforceable, independent of the federal § 404 permit. The ACC again appealed the § 401 certification to the PCHB.

In December 2001, the PCHB granted ACC’s motion to stay the effectiveness of the certification and Citizens Against SeaTac Expansion (CASE) successfully intervened. The PCHB held a 10-day hearing in March 2002. The PCHB admitted written direct testimony, portions of deposition testimony, and numerous exhibits. After an in depth review of the nearly 58,000-page record, the PCHB issued a 139-page decision on August 12, 2002, including findings of fact and conclusions of law. The PCHB affirmed Ecology’s § 401 certification but added 16 new conditions which the PCHB deemed necessary for reasonable assurance.2 Sev[582]*582eral conditions are not challenged here and therefore stand.3

The Port filed a petition for judicial review of the PCHB decision in King County while ACC and CASE and Ecology filed separate petitions for judicial review in Thurston County. All of the cases were transferred to King County and consolidated.

[583]*583The Port immediately filed a motion for direct review at Division One of the Court of Appeals, and the Court of Appeals certified all motions for discretionary review to this court. All parties urged this court to review the PCHB decision directly. This court accepted certification and granted discretionary review on March 6, 2003.

In the meantime, on December 13, 2002, the Army Corps of Engineers issued a federal Clean Water Act § 404 permit to the Port, incorporating Ecology’s certification and 7 of the PCHB’s 16 conditions. Airport Cmtys. Coalition v. Graves, 280 F. Supp. 2d 1207, 1211, 1214 (W.D. Wash. 2003).4 The ACC sought review of the Army Corps’ certification in federal court, arguing that the Corps acted arbitrarily and capriciously when it failed to incorporate all of the PCHB’s conditions. On August 18, 2003, Judge Rothstein of the United States District Court granted summary judgment in the Corps’ favor. Judge Rothstein concluded that it was within the Corps’ discretion to accept or reject the PCHB’s conditions because those conditions arose outside of the one-year time frame for state certification imposed by § 401 of the Clean Water Act. Judge Rothstein further noted that the Corps district engineer, in his discretion, may modify the § 404 permit to incorporate additional conditions upon conclusion of this court’s review. The federal court may then again review the engineer’s decision. Moreover, the Graves court noted that the state of Washington can take measures to ensure its continued involvement, including issuing the § 401 certification, “in the form of an independently enforceable order such that at the end of the judicial review process, there are independent state requirements above and beyond the federal requirements.” Id. at 1217.

In sum, the federal court did not require that the Army Corps adopt any PCHB conditions affirmed by this court. However, the § 401 certification was issued as an [584]*584independently enforceable state order under chapter 90.48 RCW, and the PCHB decision merely added conditions to that order. Thus, all unchallenged PCHB conditions and those affirmed by this court must be incorporated into the § 401 certification by Ecology and are independently enforceable under state law.

II

Issues and Summary of Conclusions

A. Deference and Scope of Review

1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seattle Historic Waterfront Ass'n v. Amli Residential
Court of Appeals of Washington, 2024
Aldoren Kauzlarich, V. State Dept. Of Ecology
Court of Appeals of Washington, 2024
Annette Holding, LLC v. Northwest Clean Air Agency
Court of Appeals of Washington, 2020
First Student, Inc. v. Dep't of Revenue
Washington Supreme Court, 2019
Crown Resources, Corp. v. Dep't of Ecology
Court of Appeals of Washington, 2019
Arley Jimenez, V State Department Of Health
Court of Appeals of Washington, 2019
Ibaq Mohamed v. Dshs
Court of Appeals of Washington, 2019
First Student, Inc., V State Of Wa Dept Of Revenue
423 P.3d 921 (Court of Appeals of Washington, 2018)
Deoide Lea Cunningham v. State Of Wa., Dshs
Court of Appeals of Washington, 2017
Quinault Indian Nation v. Imperium Terminal Services, LLC
387 P.3d 670 (Washington Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
90 P.3d 659, 151 Wash. 2d 568, Counsel Stack Legal Research, https://law.counselstack.com/opinion/port-of-seattle-v-pollution-control-hearings-board-wash-2004.