Pacific Gas & Electric Co. v. United States

73 Fed. Cl. 333, 64 ERC (BNA) 1395, 2006 U.S. Claims LEXIS 302
United States Court of Federal Claims·Decided October 13, 2006·No. Nos. 04-74C, 04-75C·Published·Cited by 37 cases

Opinion

OPINION1

HEWITT, Judge.

This case is before the court following a trial on a claim by plaintiff, Pacific Gas & Electric Co. (PG & E or plaintiff), for partial breach of contract against the federal government (government or United States or defendant). Plaintiff’s action is one of many similar actions against the government that are either pending before this court or that have already been tried in this court involving contracts for the disposal of spent nuclear fuel (SNF) and/or high-level radioactive waste (HLW) between nuclear electric utilities (utilities) and the government. In a previous opinion in this case, the court granted defendant’s motion for summary judgment with respect to counts II and III of plaintiffs complaint, which sought restitution from defendant arising from the Department of Energy (DOE)’s alleged breach of contract and damages from defendant arising from DOE’s alleged taking of plaintiffs property without just compensation. Pac. Gas & Elec. Co. v. United States (PG & E II), 70 Fed.Cl. 766, 767, 782 (2006).

In count I of plaintiff’s complaint—the count addressed in this Opinion—plaintiff seeks damages from defendant arising from an alleged partial breach by DOE of its contractual obligations under the Nuclear Waste Policy Act. Complaint (Compl.) ¶¶ 1, 25.2 Specifically, plaintiff seeks a total of $92.1 million in damages incurred through December 31, 20043 as a result of defen[338]*338dant’s partial breach of a contract executed between the parties in 1983 for the acceptance, transportation and disposal by DOE of SNF and/or HLW generated at two power plants owned and operated by PG & E — the Humboldt Bay Power Plant Unit 3 (Humboldt Bay) and the Diablo Canyon Power Plant (Diablo Canyon). See Pacific Gas & Electric’s Post-Trial Brief (PL’s Br.) at 2-3.

The terms of the parties’ contract are substantially the same as the terms of a standard contract executed by DOE individually with all utilities in 1983. Compare PX 54 (parties’ contract) with 10 C.F.R. 961.11 (2006) (standard contract). Each of these individual contracts obligates DOE to accept SNF and/or HLW4 beginning no later than January 31, 1998 and ending when all such substances have been disposed of, under a schedule to be established that would specify the place in an acceptance queue for each individual utility’s SNF and/or HLW. See generally 10 C.F.R. 961.11, Art. II. DOE did not accept utilities’ SNF and/or HLW beginning on January 31, 1998, nor has it begun to do so with respect to any utility, including PG & E, as of the date of this Opinion. See Trial Transcript (Tr.) at 992:18-21 (Womack). The utilities have sued the government for damages for partial breach of contract, including continued storage and related costs incurred as a direct result of the government’s failure to begin acceptance of SNF and/or HLW by January 31,1998. See Compl. ¶ 1.

In Maine Yankee Atomic Power Co. v. United States, the United States Court of Appeals for the Federal Circuit held that DOE had breached the standard contract by not beginning to accept, transport, and dispose of SNF and/or HLW by the deadline of January 31, 1998. 225 F.3d 1336, 1343 (Fed.Cir.2000). In Indiana Michigan Power Co. v. United States (Indiana Michigan III), the Federal Circuit held that a claim against the government for its breach was a claim for partial breach of contract. 422 F.3d 1369, 1376-77 (Fed.Cir.2005). Defendant does not appear to dispute that it has partially breached the standard contract by not beginning to accept SNF and/or HLW by January 31, 1998. See generally Defendant’s Memorandum of Contentions of Fact and Law (Def.’s Memo.) passim; Defendant’s Posh-Trial Brief (Def.’s Br.) passim. Accordingly, as an initial matter, the court finds that defendant has partially breached the parties’ contract in

[339]*339this case. See Maine Yankee, 225 F.3d at 1343; accord Sacramento Mun. Util. Dist. v. United States (SMUD I), 63 Fed.Cl. 495, 502-503 (Fed.Cl.2005); Tenn. Valley Auth. v. United States (TVA I), 60 Fed.Cl. 665, 679 (Fed.Cl.2004). It is the impact that DOE’s breach had on PG & E on which this Opinion focuses.

The impact of DOE’s breach is dependent upon the resolution of the issue most sharply-disputed by the parties, about which the court heard the most testimony at trial, and of paramount importance to the resolution of this case: namely, the scope of DOE’s performance obligation under the standard contract generally, and the parties’ contract specifically, within the unique regulatory environment in which such contracts were negotiated, executed and implemented. Central to this disputed issue is the rate at which DOE would have accepted utilities’ SNF and/or HLW had DOE begun to perform on January 31, 1998. In brief, the higher DOE’s acceptance rate, the earlier in time plaintiff’s SNF and/or HLW would have been accepted by DOE under the schedule containing the acceptance queue, and the earlier DOE would have completed performance of the parties’ contract had it performed beginning on January 31, 1998. The higher DOE’s acceptance rate, the greater the amount of continued storage and related costs that would be the direct result of DOE’s failure to begin performance of the standard contract by January 31, 1998, and therefore, the greater the award of damages to plaintiff.

Plaintiff’s main theory of the case is that DOE’s acceptance rate was left as an open term in the parties’ contract, see Pl.’s Br. at 7, and that the court should therefore supply such a term based on the intent of the parties, see PG & E’s Reply to the Government’s Post-Trial Brief (Pl.’s Reply) at 2. Defendant’s main theory of the case is that, after negotiation on the issue and, by choice, the parties’ contract does not contain a specific acceptance rate obligation and that, as was envisioned by the express terms of the parties’ contract, DOE’s acceptance rate eventually was “sufficiently definitized ... to create an enforceable schedule against which damages can be measured.” Def.’s Memo, at 2. Plaintiffs theory posits a high acceptance rate; DOE’s a low one.

The court conducted nine days of trial and heard the testimony of seventeen witnesses5 [341]*341in June of 2006. In addition to the trial record, the court has considered extensive post-trial briefing and certain deposition designations filed by the parties. The court addresses first the scope of DOE’s performance obligation to accept PG & E’s spent fuel under the parties’ contract. Principally, this issue focuses on DOE’s acceptance rate.6 Resolution of the scope of DOE’s performance obligation to accept PG & E’s spent fuel under the parties’ contract will facilitate the court’s remaining analysis, which will focus on whether the costs claimed as damages by PG & E were incurred as a direct and reasonably foreseeable result of defendant’s partial breach of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Pacific Gas & Electric Co. v. United States, 73 Fed. Cl. 333, 64 ERC (BNA) 1395, 2006 U.S. Claims LEXIS 302 (uscfc 2006).

73 Fed. Cl. 333 (Pacific Gas & Electric Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Energy Northwest v. United States
115 Fed. Cl. 69 (Federal Claims, 2014)
Power Authority v. United States
99 Fed. Cl. 661 (Federal Claims, 2011)
Entergy Nuclear Fitzpatrick, LLC v. United States
101 Fed. Cl. 305 (Federal Claims, 2011)
Pyramid Real Estate Services, LLC v. United States
95 Fed. Cl. 613 (Federal Claims, 2010)
Kansas Gas & Electric Co. v. United States
95 Fed. Cl. 257 (Federal Claims, 2010)
Yankee Atomic Power Co. v. United States
94 Fed. Cl. 678 (Federal Claims, 2010)
Southern California Edison Co. v. United States
93 Fed. Cl. 337 (Federal Claims, 2010)
Pacific Gas & Electric Co. v. United States
92 Fed. Cl. 175 (Federal Claims, 2010)
Dairyland Power Cooperative v. United States
90 Fed. Cl. 615 (Federal Claims, 2009)
Dominion Resources, Inc. v. United States
84 Fed. Cl. 259 (Federal Claims, 2008)
Pacific Gas & Electric Co. v. United States
536 F.3d 1282 (Federal Circuit, 2008)
Sacramento Municipal Utility District v. United States
293 F. App'x 766 (Federal Circuit, 2008)
Yankee Atomic Electric Co. v. United States
536 F.3d 1268 (Federal Circuit, 2008)
Carolina Power & Light Co. v. United States
82 Fed. Cl. 23 (Federal Claims, 2008)
Schortmann v. United States
82 Fed. Cl. 1 (Federal Claims, 2008)