Northwest Requirements Utilities v. Federal Energy Regulatory Commission

798 F.3d 796
CourtCourt of Appeals for the Ninth Circuit
DecidedAugust 10, 2015
DocketNos. 13-70391, 13-70499, 13-70581, 13-72928
StatusPublished
Cited by27 cases

This text of 798 F.3d 796 (Northwest Requirements Utilities v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northwest Requirements Utilities v. Federal Energy Regulatory Commission, 798 F.3d 796 (9th Cir. 2015).

Opinion

OPINION

HURWITZ, Circuit Judge:

These are consolidated petitions for review of orders by the Federal Energy Regulatory Commission (“FERC”) that require the Bonneville Power Administration — a federal agency that both markets electricity and operates a large portion of the transmission grid in the Pacific Northwest — to provide transmission services on terms “not unduly discriminatory or preferential.” Bonneville has complied with the orders, and is not a party to this proceeding. The petitioners, instead, are wholesale electricity customers of Bonneville who challenge the orders on substantive and procedural grounds. We conclude that they lack statutory standing to pursue their claims.

I

A

Bonneville markets electric power generated at federal hydroelectric dams in the Columbia River Basin. Its power customers are primarily public and private utilities that purchase wholesale electricity. See Nw. Envt’l Def. Ctr. v. Bonneville Power Admin., 477 F.3d 668, 672-73 (9th Cir.2007); Ass’n of Pub. Agency Customers, Inc. v. Bonneville Power Admin., 126 F.3d 1158, 1164 (9th Cir.1997). Bonneville also operates 80% of the electricity transmission network in the Pacific Northwest. Thus, Bonneville supplies interconnection and transmission services to public and private power generators, including itself.

Bonneville is self-funded and must recover its costs through rates charged to customers. See 16 U.S.C. §§ 838g, 839e(a)(l); see also id. § 839(4). Its rates are “based upon [its] total system costs.” Id. § 839e(a)(2)(B). Bonneville is also subject to a potentially conflicting mandate to market power “with a view to encouraging the widest possible diversified use of electric power at the lowest possible rates to consumers consistent with sound business principles.” Id. § 838g; see also Ass’n of Pub. Agency Customers, 126 F.3d at 1164.

Bonneville must also comply with various environmental protection requirements. The amount of water that can be stored behind Bonneville’s dams is limited. See, e.g., Bonneville Power Admin., BPA’s Interim Environmental Redispatch and Negative Pricing Policies, Administrator’s Final Record of Decision 11 (May 2011) (“2011 ROD”), http://tinyurl.com/pcgt3pj. But so is the amount of water that can pass over a dam’s spillway. See Nat’l Wildlife Fed’n v. Nat’l Marine Fisheries Serv., 422 F.3d 782, 789 & n. 3 (9th Cir.2005) (per curiam); Nat’l Wildlife Fed’n v. U.S. Army Corps of Eng’rs, 92 F.Supp.2d 1072, 1074-75 (D.Or.2000); 2011 ROD 5-6. Under the Clean Water Act, states have authority to cap the amount of dissolved gas in Columbia River Basin water. See Nat’l Wildlife, 92 F.Supp.2d at 1074-75; [802]*8022011 ROD 5-6. Dissolved gas, which harms fish, increases when water is spilled over a dam; spill must therefore “be carefully managed to. avoid gas supersaturation.” Nail Wildlife, 422 F.3d at 789.

Bonneville is further constrained by the realities of operating hydroelectric dams on an electrical grid. Water that cannot be spilled over Bonneville’s dams must pass through the turbines, generating electricity. This electricity must be consumed to maintain transmission stability. Reliability standards therefore require Bonneville to maintain the balance between supply and demand on its electrical grid. 2011 ROD 7.

B

The demand for electricity is finite. When spill must be limited, Bonneville can dispose of excess electricity by marketing it to other generators at low prices or giving it away, thereby displacing electricity those sources would ordinarily generate. Fossil fuel and nuclear generators gladly accept such inexpensive hydropower because it allows them to save on fuel costs by reducing their more costly output or shutting down entirely. Wind generators, in contrast, do not have fuel costs, and are federally subsidized based on the amount of energy they generate. The availability of free hydropower therefore does not generally cause them to reduce production.

In response to a substantial increase in wind generation on Bonneville’s transmission system and anticipated high water levels in the Columbia River Basin, Bonneville promulgated an Environmental Redispatch Policy (“ER Policy”) in May 2011, to remain in effect until the end of March 2012. Id. at 8, 14-17. The ER Policy allowed Bonneville to curtail the customers’ electricity generation unilaterally through “Dispatch Orders.” Id. at 8, 16-17. Dispatch Orders were to be issued only as a last resort during “overgeneration events” when spill limits were reached, water levels required Bonneville to generate electricity that outpaced demand, and excess hydropower could not be disposed of at low or zero prices or by curtailing non-wind generation. Id. at 14-16.

Under the ER Policy, Bonneville redispatched wind generation for over two hundred hours between May 18 and June 18, 2011, curtailing 5.4% of the wind generation on Bonneville’s transmission system during that period. Bonneville initially estimated that this caused wind generators to lose approximately $50 million in federal credits, although the estimate was later reduced.

C

On June 17, 2012, a group of wind generators filed a FERC complaint against Bonneville, seeking an order that Bonneville “immediately revise its [ER Policy] to comport with the undue discrimination standards of [Federal Power Act] Section 211 A.” Several wholesale energy customers of Bonneville and trade organizations intervened, contending that “[i]f the Commission were to order [Bonneville] to pay the requested compensation to the Complainants, [Bonneville] could pass on those costs to its customers ... in future rate proceedings.” On December 7, 2011, FERC concluded that the ER Policy “results in noncomparable transmission service that unfairly treats non-Federal [i.e., wind] generating resources connected to Bonneville’s transmission system,” and ordered Bonneville,

pursuant to section 211A of the FPA, ... to file ... tariff revisions to address the comparability concerns raised in this proceeding in a manner that provide[s] for transmission service on terms and [803]*803conditions that are comparable to those under which Bonneville provides transmission services to itself and that are not unduly discriminatory or preferential.

FERC emphasized that its order was prospective and that it was “making no determinations as to whether actions taken by Bonneville in the past, whether pursuant to the Environmental Redispatch Policy or otherwise, were prohibited.”

D

In order to comply with the December 2011 FERC order, on March 6, 2012, Bonneville submitted for FERC approval a temporary Oversupply Management Protocol (“OMP I”). The OMP I, to be effective until March 2013, permitted Bonneville to unilaterally redispatch wind generation during oversupply conditions, but called for “compensation to renewable generators for the costs they incur from being displaced,” at a rate of 50% of the costs they incurred. On December 20, 2012, FERC conditionally approved the OMP I “as a balanced interim measure that addressed Bonneville’s oversupply problems,” but found that the cost-sharing arrangement was not equitable and ordered Bonneville to propose a different scheme.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kimball Wind, LLC v. FERC
140 F.4th 496 (D.C. Circuit, 2025)
Johnson v. LMT Foods, Inc.
N.D. California, 2022
Johnson v. Right Crons Inc.
N.D. California, 2022
City of Oakland v. Oakland Raiders
20 F.4th 441 (Ninth Circuit, 2021)
Tobias v. NVIDIA Corporation
N.D. California, 2021
Whitaker v. Tesla Motors, Inc.
S.D. California, 2021
Robin Hall v. Usda
Ninth Circuit, 2020
In re: Serapio Venegas
Ninth Circuit, 2020
National Family Farm Coalition v. Usepa
966 F.3d 893 (Ninth Circuit, 2020)
In re Delaware Public Schools Litigation
Court of Chancery of Delaware, 2020
Dawson v. Asher
W.D. Washington, 2020
Williams v. Apple, Inc.
N.D. California, 2020

Cite This Page — Counsel Stack

Bluebook (online)
798 F.3d 796, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northwest-requirements-utilities-v-federal-energy-regulatory-commission-ca9-2015.