FEDERAL · 16 U.S.C. · Chapter 12B

Distribution of electricity; preference to public bodies and cooperatives

16 U.S.C. § 832c
Title16Conservation
Chapter12B — BONNEVILLE PROJECT

This text of 16 U.S.C. § 832c (Distribution of electricity; preference to public bodies and cooperatives) is published on Counsel Stack Legal Research, covering United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
16 U.S.C. § 832c.

Text

(a)General provisions In order to insure that the facilities for the generation of electric energy at the Bonneville project shall be operated for the benefit of the general public, and particularly of domestic and rural consumers, the administrator shall at all times, in disposing of electric energy generated at said project, give preference and priority to public bodies and cooperatives.
(b)Prior to January 1, 1942; subsequent thereto To preserve and protect the preferential rights and priorities of public bodies and cooperatives as provided in section 1 (a) and to effectuate the intent and purpose of this chapter that at all times up to January 1, 1942, there shall be available for sale to public bodies and cooperatives not less than 50 per centum of the electric energy produced at th

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aluminum Co. of America v. Central Lincoln Peoples' Utility District
467 U.S. 380 (Supreme Court, 1984)
148 case citations
Portland General Electric Co. v. Bonneville Power Administration
501 F.3d 1009 (Ninth Circuit, 2007)
62 case citations
Port of Astoria v. Hodel
595 F.2d 467 (Ninth Circuit, 1979)
58 case citations
Alcoa, Inc. v. Bonneville Power Administration
698 F.3d 774 (Ninth Circuit, 2012)
48 case citations
Port Of Astoria, Oregon v. Hodel
595 F.2d 467 (Ninth Circuit, 1979)
43 case citations
Southern California Edison v. United States
58 Fed. Cl. 313 (Federal Claims, 2003)
39 case citations
Association of Public Agency Customers v. Bonneville Power Administration
733 F.3d 939 (Ninth Circuit, 2013)
35 case citations
Northwest Requirements Utilities v. Federal Energy Regulatory Commission
798 F.3d 796 (Ninth Circuit, 2015)
27 case citations
Pacific Northwest Generating Cooperative v. Dept. of Energy
580 F.3d 792 (Ninth Circuit, 2009)
21 case citations
Golden Northwest Aluminum, Inc. v. Bonneville Power Administration
501 F.3d 1037 (Ninth Circuit, 2007)
19 case citations
Pacific Northwest Generating Cooperative v. Brown
822 F. Supp. 1479 (D. Oregon, 1993)
18 case citations
Natural Resources Defense Council, Inc. v. Hodel
435 F. Supp. 590 (D. Oregon, 1977)
10 case citations
Southern California Edison Co. v. Jura
909 F.2d 339 (Ninth Circuit, 1990)
8 case citations
Pacific Northwest Generating Cooperative v. Brown
25 F.3d 1443 (Ninth Circuit, 1994)
4 case citations
Atlantic Richfield Co. v. Bonneville Power Administration
818 F.2d 701 (Ninth Circuit, 1987)
4 case citations
Utility Reform Project v. Bonneville Power Administration
869 F.2d 437 (Ninth Circuit, 1989)
4 case citations
Central Lincoln Peoples' Utility District v. Johnson
673 F.2d 1076 (Ninth Circuit, 1982)
3 case citations

Source Credit

History

(Aug. 20, 1937, ch. 720, §4, 50 Stat. 733; Mar. 6, 1940, ch. 47, §3, 54 Stat. 47.)

Editorial Notes

Editorial Notes

Amendments
1940—Subsec. (b). Act Mar. 6, 1940, substituted "January 1, 1942" for "January 1, 1941" wherever appearing.

Statutory Notes and Related Subsidiaries

Transfer of Functions
Functions of Secretary of the Interior with respect to Bonneville Power Administration transferred to Secretary of Energy by section 7152(a)(1)(D), (2) of Title 42, The Public Health and Welfare, with Bonneville Power Administration to be preserved as a distinct organizational entity within Department of Energy and headed by an Administrator.

Cite This Page — Counsel Stack

Bluebook (online)
16 U.S.C. § 832c, Counsel Stack Legal Research, https://law.counselstack.com/usc/16/832c.