Transmission Agency of Northern California v. Sierra Pacific Power Company, Bonneville Power Administration, Pacificorp, and Portland General Electric

295 F.3d 918, 2002 Daily Journal DAR 7643, 2002 U.S. App. LEXIS 13591, 2002 WL 1453668
Court of Appeals for the Ninth Circuit·Decided July 8, 2002·No. 01-15449·Published·Cited by 109 cases

Opinion

ORDER

DAVID R. THOMPSON, Circuit Judge.

The opinion filed April 16, 2002 is amended as follows:

At slip opinion page 5765, in the first full paragraph, the fourth sentence that begins “TANC cannot obtain state law money-damages ...” is amended to read: “TANC cannot obtain state law money damages allegedly resulting from the operation of an interstate electricity intertie expressly approved by FERC, where the manner of operation was necessarily contemplated at the time of approval.”

At slip opinion page 5766, in the first full paragraph, the fifth sentence that begins “Offering an analogy of our own ...” is amended to read: “Offeidng an analogy of our own, allowing TANC to sue under state law for damage allegedly caused to its transmission system by an interconnected interstate system approved by FERC would be akin to allowing an airline to sue under state law for economic damages caused by another airline’s FAA-approved flight plans.”

With these amendments, the panel named above has voted to deny the petition for rehearing. Judges W. Fletcher and Berzon have voted to deny the petition for rehearing en banc, and Judge Thompson has recommended denial of that petition.

The full court has been advised of the petition for rehearing en banc, and no judge has requested a vote on that petition.

The petition for rehearing and petition for rehearing en banc are DENIED.

OPINION

The Transmission Agency of Northern California (TANC) is a joint exercise of powers agency composed of over a dozen Northern and Central California municipalities. It brought suit against the Bonneville Power Administration (BPA), a federal power marketing agency of the United States Department of Energy, 1 and the defendant regional utility companies. TANC asserted claims for equitable relief and damages allegedly incurred as a result of the BPA and the other defendants constructing, and interconnecting with, an electricity intertie known as the Alturas Intertie.

The district court did not reach the merits of TANC’s claims. It dismissed the claims against the BPA for lack of subject matter jurisdiction, concluding that those claims challenged final agency action by the BPA and fell within the Ninth Circuit *923 Court of Appeals’ exclusive original jurisdiction. See 16 U.S.C. § 839f(e)(5). It also dismissed, as preempted under the Federal Power Act, 16 U.S.C. §§ 791— 828c, TANC’s claims against the defendant utility companies. TANC appeals. We have jurisdiction under 28 U.S.C. § 1291, and we affirm.

I

Facts and Proceedings

Because this case comes before us on appeal from a dismissal under Federal Rule of Civil Procedure 12(b)(6), all facts alleged in TANC’s complaint are taken as true and construed in the light most favorable to it. Epstein v. Wash. Energy Co., 83 F.3d 1136, 1140 (9th Cir.1996).

TANC alleged that in 1991 it entered into an “Interim Interconnection Agreement” and “Schedule and Coordination Agreement” (collectively the “Agreements”) with the defendants BPA, Portland General Electric, and PacifiCorp (collectively the “Northwest Parties”) to jointly construct and operate an interconnection of two electricity interties. Under the Agreements, the Northwest Parties agreed to upgrade from 3200 MW to 4800 MW an existing intertie that they own in Oregon, known as the Northwest AC In-tertie. TANC, in turn, agreed to construct a new 1600 MW line known as the California-Oregon Transmission Project. TANC also agreed to connect the California-Oregon Transmission Project to an already existing intertie in California, the 3200 MW Pacific AC Intertie, 2 to form the 4800 MW California-Oregon Intertie. Finally, TANC and the Northwest Parties agreed to join the California-Oregon In-tertie with the Northwest AC Intertie, creating a transfer capability of 4800 MW north-to-south at the California-Oregon Border between the two interties. The parties performed under the Agreements, and the Federal Energy Regulatory Commission (FERC) allocated to TANC’s Cal-ifomia-Oregon Transmission Project one-third of the newly-created transfer capability.

In 1996, the BPA announced its decision to join the Northwest AC Intertie with the new 300 MW Alturas Intertie, which was to be constructed by defendant Sierra Pacific. See Decision to Interconnect with Sierra Pacific Power Company’s Alturas Transmission Line Project, 61 Fed.Reg. 7095 (Feb. 26, 1996). Sierra Pacific completed construction of the Alturas Intertie in late 1998.

The Alturas Intertie stretches from Nevada through northern California and into Oregon, where it connects with the Northwest AC Intertie. When operational, the Alturas Intertie causes a megawatt-for-megawatt reduction in the ability of the Northwest AC Intertie to deliver power to the California-Oregon Intertie. As a result, if the Alturas Intertie is operating at its maximum 300 MW capacity, then the California-Oregon Intertie has 300 MW of excess capacity.

Prior to the Alturas Intertie commencing operations, TANC (and other companies and instrumentalities not parties to this litigation) filed an unsuccessful protest with FERC, alleging that the Alturas Intertie would create a megawatt-for-megawatt reduction in the capacity of the California-Oregon Intertie. In that proceeding, TANC requested that FERC ensure that procedures were put in place to protect the “then existing” contractual relationships, including the California-Ore *924 gon Intertie’s alleged first-priority access to 4800 MW of transfer capability under the Agreements. Alternatively, TANC asked FERC to delay operation of the Alturas Intertie until either Congress approved the intertie, or the Northwest AC Intertie’s capacity was increased to 5100 MW. FERC denied these requests and, on November 30, 1998, it approved operation of the Alturas Intertie. See 85 F.E.R.C. ¶ 61,314 (Nov. 30, 1998).

In February 1999, however, after operation of the Alturas Intertie had commenced, FERC initiated a hearing into the connection agreement creating the Alturas Intertie. FERC considered the hearing necessary to address allegations regarding the megawatt-for-megawatt reduction in the California-Oregon Intertie’s capacity, the inconsistency between the Alturas scheduling agreement and the California-Oregon Intertie’s scheduling needs, and related issues.

Free access — add to your briefcase to read the full text and ask questions with AI