Grynberg v. Questar Pipeline Co.

2003 UT 8, 70 P.3d 1, 50 U.C.C. Rep. Serv. 2d (West) 171, 469 Utah Adv. Rep. 13, 2003 Utah LEXIS 14, 2003 WL 1408204
CourtUtah Supreme Court
DecidedMarch 21, 2003
Docket20010731
StatusPublished
Cited by70 cases

This text of 2003 UT 8 (Grynberg v. Questar Pipeline Co.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grynberg v. Questar Pipeline Co., 2003 UT 8, 70 P.3d 1, 50 U.C.C. Rep. Serv. 2d (West) 171, 469 Utah Adv. Rep. 13, 2003 Utah LEXIS 14, 2003 WL 1408204 (Utah 2003).

Opinion

WILKINS, Justice:

11 Jack J. Grynberg, Celeste C. Gryn-berg, and L & R Exploration (collectively "Grynbergs") appeal the district court's order granting summary judgment to Questar Pipeline Company and its affiliates (collectively "Questar") on all of the CGrynbergs' contract and. tort claims for breach of several natural gas purchase agreements. We affirm in part and reverse in part.

FACTUAL AND PROCEDURAL HISTORY

12 For over thirty years, Questar has been purchasing, gathering, and/or transporting natural gas owned by the Grynbergs. While heavily regulated when the contracts were signed in 1974, deregulation has since transformed the natural gas industry. Since 1987, Questar and the Grynbergs have been embroiléd in multiple lawsuits under the gas purchase agreements governing their relationship. This case is the fifth, and hopefully final, effort to resolve the many disputes that stem from their relationship. We recite the facts of this case, and all reasonable inferences to be drawn therefrom, in the light most favorable to the Grynbergs. Seq, eg., Norman v. Arnold, 2002 UT 81, 1 2, 57 P.3d 997.

I. FACTUAL HISTORY

A. The Contracts

T3 The Grynbergs own working interests in natural gas wells located in Wyoming and Colorado. In 1971, the Grynbergs signed a gas purchase agreement with Mountain Fuel Supply Company, predecessor in interest to Questar Pipeline Company, for the sale of gas from the Colorado wells (Colorado Contract). In April and June of 1974, the Ciryn-bergs signed three more gas purchase agreements with Mountain Fuel for the sale of gas from their Wyoming wells (Wyoming Contracts). All four were twenty year contracts, continuing year to year after that if not terminated according to their terms.

14 Under the Wyoming Contracts, the ultimate gas price paid by Questar was determined by a formula with three variables: price, volume, and gross heating value (BTU adjustment). The contracts obligated Ques-tar to gather, measure, analyze, and transport the natural gas they were purchasing, and to provide monthly statements and payments to the Grynbergs. Questar's responsibilities also included measuring the volume and gross heating value of the gas according to formulas set forth in the contracts and performing regular equipment tests. The Grynbergs were authorized to demand periodic equipment tests and to participate in all gas or equipment tests performed routinely or on demand.

' 5 The Colorado Contract was terminated January 1, 1992. After raising concerns about Questar's adherence to take-or-pay obligations under the Colorado Contract, the Grynbergs signed a new, 96-day gas purchase agreement with Questar on February 11, 1992 that contained a general settlement and release of all claims from the Colorado Contract. Questar attempted to terminate the Wyoming Contracts on June 28, 19983, and again on January 1, 1994; the final termination date, however, remains in dispute.

T6 Sometime after Questar's attempted termination of the Wyoming Contracts, the Grynbergs contracted with their well operator, Hunt Oil Company (Hunt), to sell the natural gas from the Wyoming wells on their behalf. Hunt, in turn, contracted with Ques-tar affiliates to purchase, gather, and/or transport the natural gas from the Wyoming wells (Hunt Contracts). According to the Grynbergs, Questar affiliates purchased natural gas from the Wyoming wells through the end of 1997, and continue to gather and transport natural gas from the Wyoming wells to this day.

B. Prior Litigation

1. Questar I

17 In 1987, the Grynbergs brought their first suit against Questar in Wyoming federal *5 district court under all four contracts (Ques-tar I). The complaint alleged, inter alia, fraud, misrepresentation, conversion, and breach of contract based upon take-or-pay obligations, and covered gas sales transactions from 1974 through 1988. The parties eventually settled this case, agreeing to a mutual general release of all claims before December 1988.

2. Questar II

T8 In 1992, Questar brought a declaratory judgment action in Wyoming federal district court to determine the appropriate price, after deregulation, of natural gas sold under the Colorado and Wyoming Contracts (Ques-tar II). The Grynbergs counterclaimed, alleging intentional interference with contractual relations, breach of the duty of good faith and fair dealing, and numerous breach-eg of contract including failing to take or pay, underreporting gas volume, and making gas payments "using incorrect btu adjustments."

T9 The district court granted Questar's summary judgment motion on the Giryn-bergs' claim that Questar was "stealing gas," but allowed the remaining claims to go to trial. After discovery, and immediately before the trial was to begin, the Grynbergs informed Questar and the court that the "incorrect [BTU] adjustment" claim was far greater than previously understood. In a February 28, 1994 hearing, the district court stated that it "would construct a dismissal [of the BTU claim] in this case without prejudice," allowing the parties to resolve the BTU adjustment issue in another suit. However, it was not until October 1, 1998 that the district court issued a final order dismissing without prejudice "defendants' claim against plaintiff for paying for gas using incorrect [BTU] adjustments (the [BTU] claims)."

{10 The deregulation price question and all remaining counterclaims were tried before the jury, who returned a verdict for the Grynbergs on all counts. Four years later, after Questar's request for judgment as a matter of law, the district court reduced the jury's deregulation price determination and granted judgment for Questar on all of the Grynbergs' counterclaims. The Tenth Circuit reversed the district court's price reduction and substantially reinstated the jury verdict in Questar Pipeline Co. v. Grynberg, 201 F.3d 1277, 1281 (10th Cir.2000). A final judgment following remand was entered March 20, 2000.

3. Questar III

11 A third lawsuit was filed in Wyoming federal district court by the Grynbergs against Questar in 1997, alleging pricing and take-or-pay claims under the four contracts for the time period following Questar II (Questar III). The suit was filed to preserve claims that would otherwise be barred by the four-year statute of limitations for gas sales in Wyoming, and does not include the BTU adjustment claim from Questar II.

T12 Questar moved for summary judgment, seeking a determination of the Wyoming Contracts' termination date. On December 11, 1998, the district court granted partial summary judgment to Questar, ruling that the Wyoming Contracts terminated on July 1, 1994 (Termination Ruling). No final judgment has been issued in that case.

II. PROCEDURAL HISTORY

T 13 The current case against Questar was filed by the Grynbergs in Utah's Third District Court on September 29, 1999 (Questar IV). The first amended complaint alleges in detail improper measurement and analysis of the gross heating content of natural gas under the Wyoming Contracts, and also alleges that Questar fraudulently induced the Gryn-bergs to release all claims under the Colorado Contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2003 UT 8, 70 P.3d 1, 50 U.C.C. Rep. Serv. 2d (West) 171, 469 Utah Adv. Rep. 13, 2003 Utah LEXIS 14, 2003 WL 1408204, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grynberg-v-questar-pipeline-co-utah-2003.