May v. First Rate Excavate, Inc.

2025 S.D. 17
CourtSouth Dakota Supreme Court
DecidedMarch 12, 2025
Docket30579
StatusPublished

This text of 2025 S.D. 17 (May v. First Rate Excavate, Inc.) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
May v. First Rate Excavate, Inc., 2025 S.D. 17 (S.D. 2025).

Opinion

#30579-r-JMK 2025 S.D. 17

IN THE SUPREME COURT OF THE STATE OF SOUTH DAKOTA

****

JAMES AND AMBER MAY, Plaintiffs and Appellants,

v.

FIRST RATE EXCAVATE, INC., Defendant and Appellee.

APPEAL FROM THE CIRCUIT COURT OF THE SECOND JUDICIAL CIRCUIT LINCOLN COUNTY, SOUTH DAKOTA

THE HONORABLE DOUGLAS E. HOFFMAN Judge

JUSTIN T. CLARKE of Davenport, Evans, Hurwitz & Smith, LLP Sioux Falls, South Dakota Attorneys for plaintiffs and appellants.

RYLAND L. DEINERT RENE CHARLES LAPIERRE of Klass Law Firm, LLP Sioux City, Iowa Attorneys for defendant and appellee.

ARGUED JUNE 6, 2024 OPINION FILED 03/12/25 #30579

KERN, Justice

[¶1.] James and Amber May retained RES Construction (RES) to construct

their home in Sioux Falls. RES hired First Rate Excavate, Inc. (First Rate), a

subcontractor, to install the septic system for the home and construct the home’s

foundation, which the Mays allege was installed several feet below grade level. The

Mays claim this resulted in significant drainage and septic issues that caused

damage to the Mays’ new house and yard and neighboring yards. The Mays sued

First Rate for negligence sounding in tort. The circuit court dismissed the Mays’

claim based on the economic loss doctrine and the Mays appeal. We reverse.

Factual and Procedural Background

[¶2.] Construction on the Mays’ home began in 2015. RES hired First Rate

“to perform dirt work associated with the construction of the home, including

digging and placement of the foundation, and placing the septic system for the home

in accordance with the original engineer’s renderings.” The Mays moved into the

home soon after it was completed in 2016.

[¶3.] Shortly thereafter, on September 6, 2016, heavy rain fell in the Sioux

Falls area and the Mays “noticed a creek running through their back yard.”

Further, on May 8, 2017, and in early April 2018, the basement was “infiltrated”

with water. Additionally, during the infiltration event in April 2018, the septic

system was “under water and quit working.” Consequently, First Rate attempted to

regrade the yard and installed a second septic system, which ultimately failed as

well. As a result of the drainage and septic issues, “a lagoon exists in [the Mays’]

yard and drains into their neighbors’ property, causing significant issues.” In

-1- #30579

addition, “the concrete work around the house has been damaged due to moisture

sitting against the house and failing to drain away.”

[¶4.] According to the Mays, these issues “are all directly related to the

digging and placement of the foundation for the home, which is multiple feet lower

than the original plans intended.” The Mays claim that the “only way to fix their

home . . . is to pick up the home, move it, and put in a new foundation that is

multiple feet higher, where it was originally supposed to be, and put the home back

down on the new foundation.”

[¶5.] The Mays brought suit against First Rate, alleging only negligence. 1

The Mays sought damages “including the costs of repairing the home . . . and all

other compensation to which Plaintiffs are entitled.” The Mays also sought attorney

fees and requested “such other and further relief as the Court deems just and

equitable.” In response, First Rate filed a motion to dismiss, arguing that because

the parties lacked privity of contract, the Mays could not sue First Rate under the

terms of the Mays’ contract with RES and that the Mays’ claims were barred by the

six-year statute of limitations set forth in SDCL 15-2-13.

1. The Mays entered into a settlement agreement with RES and signed a Pierringer release. See Pierringer v. Hoger, 124 N.W.2d 106 (Wis. 1963); Schick v. Rodenburg, 397 N.W.2d 464, 467 (S.D. 1986). “Pierringer releases are settlement agreements between a plaintiff and some, but not all, defendants in a case. A Pierringer release satisfies ‘that portion of the plaintiff’s cause of action for which the settling joint tortfeasor is responsible, while at the same time reserving the balance of the plaintiff’s cause of action against a nonsettling joint tortfeasor.’” Allsop Venture Partners III v. Murphy Desmond SC, 991 N.W.2d 320, 332 (Wis. 2023) (quoting Imark Indus., Inc. v. Arthur Young & Co., 436 N.W.2d 311, 318 (Wis. 1989)).

-2- #30579

[¶6.] In a December 2, 2022 email memo, the circuit court sua sponte raised

the issue of whether the economic loss theory—which holds that a contracting

party’s remedies for purely economic loss are limited to those specified in the

contract—would bar the Mays’ tort claim. See Kreisers Inc. v. First Dakota Title

Ltd. P’ship, 2014 S.D. 56, ¶ 29, 852 N.W.2d 413, 421; Diamond Surface, Inc. v. State

Cement Plant Comm’n, 1998 S.D. 97, ¶ 22, 583 N.W.2d 155, 160. The parties

submitted supplemental briefing on that issue, pursuant to the court’s request, and

a motion hearing was held on December 9, 2022. At this hearing, the Mays asserted

that the economic loss theory applied only to contracts involving the sale of goods

under the Uniform Commercial Code (UCC). In response, the circuit court

explained its thinking regarding the economic loss issue:

Yeah. Well, I don’t think it is a good, so I’m not worried about that, but . . . the statute, the negligence statute that you quoted sounds you know very . . . all-encompassing, but I think we would all acknowledge that at least in some circumstances the UCC, for example, or product liability . . . when we’re dealing just with damage to the good in question rather than damage to other, the good or the property that was the subject of the contract rather than other property or personal injury. The economic loss doctrine has been applied in South Dakota notwithstanding that seemingly all-encompassing neglige[nce] statutes.

So, we know that the South Dakota Supreme Court is not going to say that every single claim of loss can have a negligence tort remedy for breach of duty of reasonable care. So, that leads me, so we get back in to the, well, we’re really the economic loss doctrine in any event should be confined to instances where there’s privity of contract because we don’t want to leave people without a remedy, obviously, and that’s certainly true, but in this case there was a chain of privity because the plaintiffs were in privity with the codefendant, RES, who was in privity with our current defendant, First Rate Excavate. And so, if the fault [lies] with First Rate Excavate and RES was basically vicariously liable, maybe there’s a combination of vicarious

-3- #30579

liability because First Rate screwed it up allegedly, and RES had a duty to supervise their subs and catch it, and you know because they had a contractual obligation to provide a home that met the contract and was suitable for its intended purpose.

So, [the Mays], it seems to me intentionally stepped out of the privity chain so that they could take advantage of the more freewheeling, ah, amorphous tort remedy, and I think there’s probably some scholars that would say, yeah, that’s a good idea. That’s what we should allow people to do, you know, kind of let’s make sure that we’ve got every remedy available to make sure that every wrong is righted in the most efficient, and . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

C & W Enterprises, Inc. v. City of Sioux Falls
2001 SD 132 (South Dakota Supreme Court, 2001)
Blaha v. Stuard
2002 SD 19 (South Dakota Supreme Court, 2002)
Jorgensen Farms, Inc. v. Country Pride Cooperative, Inc.
2012 S.D. 78 (South Dakota Supreme Court, 2012)
McCarthy Well Co. v. St. Peter Creamery, Inc.
410 N.W.2d 312 (Supreme Court of Minnesota, 1987)
Giles v. General Motors Acceptance Corp.
494 F.3d 865 (Ninth Circuit, 2007)
Grams v. Milk Products, Inc.
2005 WI 112 (Wisconsin Supreme Court, 2005)
City of Lennox v. Mitek Industries, Inc.
519 N.W.2d 330 (South Dakota Supreme Court, 1994)
Imark Industries, Inc. v. Arthur Young & Co.
436 N.W.2d 311 (Wisconsin Supreme Court, 1989)
Stevens v. Wood Sawmill, Inc.
426 N.W.2d 13 (South Dakota Supreme Court, 1988)
Diamond Surface, Inc. v. State Cement Plant Commission
1998 SD 97 (South Dakota Supreme Court, 1998)
Schick v. Rodenburg
397 N.W.2d 464 (South Dakota Supreme Court, 1986)
Pierringer v. Hoger
124 N.W.2d 106 (Wisconsin Supreme Court, 1963)
Insurance Co. of North America v. Cease Electric Inc.
2004 WI 139 (Wisconsin Supreme Court, 2004)
Grynberg v. Questar Pipeline Co.
2003 UT 8 (Utah Supreme Court, 2003)
Kreisers Inc. v. First Dakota Title Ltd. Partnership
2014 SD 56 (South Dakota Supreme Court, 2014)
United States v. Sineneng-Smith
590 U.S. 371 (Supreme Court, 2020)
Tiara Condominium Ass'n v. Marsh & McLennan Companies
110 So. 3d 399 (Supreme Court of Florida, 2013)
United States v. Sineneng-Smith
140 S. Ct. 1575 (Supreme Court, 2020)
Allsop Venture Partners III v. Murphy Desmond SC
2023 WI 43 (Wisconsin Supreme Court, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
2025 S.D. 17, Counsel Stack Legal Research, https://law.counselstack.com/opinion/may-v-first-rate-excavate-inc-sd-2025.