City of Lennox v. Mitek Industries, Inc.

519 N.W.2d 330, 25 U.C.C. Rep. Serv. 2d (West) 1118, 1994 S.D. LEXIS 102, 1994 WL 363921
CourtSouth Dakota Supreme Court
DecidedJuly 13, 1994
Docket18440
StatusPublished
Cited by31 cases

This text of 519 N.W.2d 330 (City of Lennox v. Mitek Industries, Inc.) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Lennox v. Mitek Industries, Inc., 519 N.W.2d 330, 25 U.C.C. Rep. Serv. 2d (West) 1118, 1994 S.D. LEXIS 102, 1994 WL 363921 (S.D. 1994).

Opinion

TIMM, Circuit Judge.

City of Lennox appeals the circuit court’s granting of summary judgment on its negligence and implied warranty claims. We affirm.

FACTS

In 1982 the City of Lennox (City) was interested in constructing a public works building for its maintenance vehicles. Breuer and Snyders Construction (Breuer and Snyders) was awarded the bid on the construction project on September 27, 1982. Breuer and Snyders contracted with Harvest States Cooperatives, d/b/a Great Plains Supply (GPS), for the purchase of materials they used to construct the building. The materials included trusses which were delivered to the job site sometime between September 29 and November 1, 1982. The building plans and specifications were prepared by GPS.

Mitek Industries, Inc., d/b/a Hydro-Air (Mitek), provided design specifications and component parts for the trusses to GPS. GPS then constructed or manufactured the trusses. On or about June 1992, one of the employees for the city noticed a failed truss on the east end of the building. A closer examination revealed that all of the trusses had failed. The City subsequently brought suit against GPS and Mitek based upon the theories of breach of implied warranties and negligence and against Breuer and Snyders based upon breach of contract. Part of the damages claimed were the expenses involved in removing old insulation, sheet metal, and having to disconnect heating, plumbing, and electrical connections before replacing the trusses.

Summary judgment was granted for Mitek and GPS because the circuit court found that the action was governed under the provisions of the Uniform Commercial Code and therefore beyond the statute of limitations found *332 at SDCL 57A-2-725. City appeals that decision.

ISSUE

DOES THE STATUTE OF LIMITATIONS IN UNIFORM COMMERCIAL CODE (SDCL 57A-2-725) GOVERN THE TRANSACTION AND, IF SO, ARE ECONOMIC DAMAGES STILL RECOVERABLE UNDER NEGLIGENCE THEORIES?

STANDARD OF REVIEW

Summary judgment is appropriate where the pleadings, depositions, answers to interrogatories, and admissions, together with any affidavits, show that there is no genuine issue as to any material fact and the moving party is entitled to judgment as a matter of law. Breen v. Dakota Gear & Joint Co., Inc., 433 N.W.2d 221, 223 (S.D.1988). The evidence must be viewed most favorably to the non-moving party and reasonable doubts should be resolved against the moving party. Du-Al Mfg. Co., v. Sioux Falls Const. Co., 487 N.W.2d 29, 31 (S.D.1992). The non-moving party, however, must present specific facts that demonstrate a genuine, material issue for trial. Id. When no genuine issue of material fact exists, summary judgment is looked upon with favor. Id.

DECISION

The first question to be addressed is whether the transaction is a sales transaction which brings it within the scope of the Uniform Commercial Code. In order for the UCC to govern the transaction, the sale must be for a sale of goods. SDCL 57A-2-106(l) states in pertinent part:

In this chapter unless the context otherwise requires ‘contract’ and ‘agreement’ are limited to those relating to the present or future sale of goods. ‘Contract for sale’ includes both a present sale of goods and a contract to sell goods at a future time, [emphasis added].

Goods are defined as all things which are movable at the time of identification to the contract for sale. SDCL 57A-2-105(l). The trusses which were involved in this transaction were movable and thus fall within the definition of goods under the UCC.

When goods and services are sold together, however, as is the case with GPS and Mitek, a special inquiry must be made. Jandreau v. Sheesley, 324 N.W.2d 266 (S.D.1982). The test is what is the predominate purpose of the contract. Id. Is it for the rendition of a service with goods incidentally involved or is it a transaction of sale with labor incidentally involved? Id.

In TCF Bank & Savings v. Marshall Truss Systems, Inc., 466 N.W.2d 49 (Minn.App.1991), the court held that a contract between a subcontractor and a general contractor to manufacture and assemble wooden trusses and deliver them to the building site for installation was predominately a contract for sale of goods. Similar to the subcontractor in TCF Bank, GPS manufactured the trusses and provided them at the site of construction and therefore this Court finds the contract to be predominately for the sale of goods.

Mitek provided a component part to the trusses along with design services. Although the record is unclear as to the exact nature of the design services provided by Mitek, it appears that the contract between GPS and Mitek was primarily for the truss plates. The transaction in all likelihood would not have taken place but for the necessary addition of the component part to the trusses. This also is predominately a contract for the sale of goods and therefore governed by the UCC.

The statute of limitations for transactions covered in the Uniform Commercial Code is found in SDCL 57A-2-725. This statute provides:

(1) An action for breach of any contract for sale must be commenced within four years after the cause of action has accrued.
(2) A cause of action accrues when the breach occurs, regardless of the aggrieved party’s lack of knowledge of the breach. A breach of warranty occurs when tender of delivery is made, except that’where a warranty explicitly *333 extends to future performance of the goods and discovery of the breach must await the time of such performance the cause of action accrues when the breach is or should have been discovered, (emphasis added).

Tender of delivery was made sometime between September 29, 1982 and November 1, 1982. This action was not commenced until 1992, well after the limitations period had run. Therefore, the circuit court was correct in granting summary judgment on the implied warranty claims which are clearly governed by the UCC.

Because the UCC governs, the next inquiry is whether the losses claimed under the negligence causes of action are recoverable in tort or whether the UCC provisions are exclusive.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

May v. First Rate Excavate, Inc.
2025 S.D. 17 (South Dakota Supreme Court, 2025)
Bowes v. PACCAR Inc
W.D. Washington, 2020
S.D. Wheat Growers Ass'n v. Chief Indus., Inc.
337 F. Supp. 3d 891 (U.S. District Court, 2018)
Briggs v. Briggs
D. South Dakota, 2018
In re Syngenta AG MIR 162 Corn Litigation
131 F. Supp. 3d 1177 (D. Kansas, 2015)
Kreisers Inc. v. First Dakota Title Ltd. Partnership
2014 SD 56 (South Dakota Supreme Court, 2014)
FAIRCHILD v. SWEARINGEN
2014 OK CIV APP 50 (Court of Civil Appeals of Oklahoma, 2013)
Jorgensen Farms, Inc. v. Country Pride Cooperative, Inc.
2012 S.D. 78 (South Dakota Supreme Court, 2012)
Dean v. Barrett Homes, Inc.
8 A.3d 766 (Supreme Court of New Jersey, 2010)
Trinity Industries, Inc. v. McKinnon Bridge Co.
77 S.W.3d 159 (Court of Appeals of Tennessee, 2001)
C & W Enterprises, Inc. v. City of Sioux Falls
2001 SD 132 (South Dakota Supreme Court, 2001)
Tri County Landfill Ass'n v. Brule County
2000 SD 148 (South Dakota Supreme Court, 2000)
Northwestern Public Service v. Union Carbide Corp.
115 F. Supp. 2d 1164 (D. South Dakota, 2000)
Brookings Municipal Utilities, Inc. v. Amoco Chemical Co.
103 F. Supp. 2d 1169 (D. South Dakota, 2000)
Atwood-Kellogg, Inc. v. Nickeson Farms
1999 SD 148 (South Dakota Supreme Court, 1999)
Paint Brush Corp. v. Neu
1999 SD 120 (South Dakota Supreme Court, 1999)
State Farm Mutual Automobile Insurance v. Ford Motor Co.
592 N.W.2d 201 (Wisconsin Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
519 N.W.2d 330, 25 U.C.C. Rep. Serv. 2d (West) 1118, 1994 S.D. LEXIS 102, 1994 WL 363921, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-lennox-v-mitek-industries-inc-sd-1994.