DENNIS M. FAIRCHILD, Plaintiff/Appellant,
v.
JOEY
SWEARINGEN, dba Swearingen Remodeling, Defendant/Appellee.
JOHN F. FISCHER, PRESIDING JUDGE:
¶1 Dennis M. Fairchild filed this small claims action against his roofing
contractor Swearingen Remodeling, Inc., who admittedly installed shingles of a
lesser value than required by the parties' contract. After the case was tried to
the district court, Judgment was entered in Fairchild's favor. The Judgment
provided alternative forms of relief and permitted Swearingen to choose which
form of relief to provide: (1) replace the non-conforming shingles with the
shingles specified in the contract, (2) return Fairchild's partial payment.
Swearingen elected the former and Fairchild appealed. We find no error by the
district court and affirm.
BACKGROUND
¶2 After storms damaged the roofs of two houses, Fairchild contracted with
Swearingen to remove the damaged roofs and replace the roofs with new shingles.
The roof on the first house was replaced to Fairchild's satisfaction and
according to the parties' contract by July 22, 2011. It is not an issue in this
case. The second house is Fairchild's personal residence. The contract for the
roof on this house was signed on July 7, 2011. With respect to that contract,
Fairchild specified impact resistant shingles, in part, to obtain a discount on
his homeowner's insurance premium. After work began on the second house,
Fairchild paid $6,000 of the $12,036.12 contract price. Swearingen completed
reroofing that house in late July 2011. On August 6, 2011, Swearingen discovered
that thirty-year laminated shingles had been installed rather than the impact
resistant shingles required by the contract. Swearingen notified Fairchild of
this mistake on August 11, 2011. The parties, with the involvement of
Fairchild's insurance company, attempted to resolve the dispute but were
ultimately unsuccessful. Fairchild filed this small claims action on November
11, 2011. Swearingen filed a counterclaim for the unpaid balance of the contract
price.
¶3 At the conclusion of the trial, the district court entered judgment in
favor of Fairchild on his breach of contract claim and on Swearingen's
counterclaim. The judgment provided as follows:
Judgment should be granted in favor of Plaintiff as follows (the option
of Defendant):
a. The Defendant be afforded to install the correct roof
in a workman like manner and in accordance with installation standards, i.e.
weather etc. within a reasonable time, weather permitting, or
b. to
refund the amount of $5,484.091 to Plaintiff.
Swearingen elected the first option and notified Fairchild that he would
install the impact resistant shingles in March of 2012. Fairchild appealed,
contending he should have been placed in the position he was in before the
contract breach occurred and refunded the $6,000 he paid minus the amount
attributable to replacement of the window screens and guttering.
STANDARD OF REVIEW
¶4 Fairchild's appeal raises only questions of law. Issues of law are
reviewed by an appellate court pursuant to a de novo standard.
Christian v. Gray, 2003 OK
10, ¶ 41, 65 P.3d 591,
608.
ANALYSIS
¶5 Fairchild filed this appeal arguing three propositions: (1) Swearingen was
not entitled to "cure" the breach of contract by replacing the non-conforming
shingles; (2) the district should have given him, not Swearingen, the option to
select the form of relief provided by the Judgment; and (3) Fairchild was
entitled to rescind the contract.
I. Applicability of the Oklahoma Uniform Commercial Code
¶6 The first issue raised by Fairchild concerns the applicability of the
Oklahoma Uniform Commercial Code (UCC), 12A O.S.2011 §§ 1-101 to 15-121.
Fairchild contends that Swearingen does not have the right to now install the
correct shingles because he cannot do so "seasonably." Swearingen points to
section 2-508(1) of the UCC: "Where any tender or delivery by the seller is
rejected because nonconforming and the time for performance has not yet expired,
the seller may seasonably notify the buyer of his intention to cure and may then
within the contract time make a conforming delivery." The validity of this
argument depends on whether the UCC is applicable to this transaction.
¶7 As relevant to this appeal, the UCC applies to "transactions in goods." 12A O.S.2011 § 2-102. It does not
apply to contracts for labor and services. Moore v. Vanderloo Eyeglasses,
386 N.W.2d 108, 1 U.C.C. Rep.Serv.2d 1442 (Iowa 1986).2 The high impact shingles involved in
this case satisfy the UCC's definition of goods. "'Goods' means all things
(including specially manufactured goods) which are movable at the time of
identification to the contract for sale. . . ." 12A O.S.2011 § 2-105(1). The
determinative question, however, is whether the parties' contract which also
called for the removal of the old shingles, installation of the new shingles and
other items necessary to the installation of a new roof, is a transaction in
goods. This issue has not been previously decided in Oklahoma.3
¶8 In those jurisdictions that have addressed the issue, the court considers
the transaction in its entirety and determines whether the goods or services
aspect of the contract predominates. See, e.g., Paramount
Aviation Corp. v. Agusta, 288 F.3d 67, 72 (3rd. Cir. 2002) (applying
New Jersey's version of the UCC).4 To determine that question: "[C]ourts look to the
language and circumstances surrounding the contract, the relationship between
the goods and services, the compensation structure and the intrinsic worth of
the goods provided." Id. (citing Integrity Material Handling Sys.,
Inc. v. Deluxe Corp., 722 A.2d 552, 555 (N.J. Super. Ct. App. Div. 1999)).
We are persuaded that this is the correct analytical framework for determining
the applicability of the UCC in this case and will apply it here.
¶9 However, the record in this small claims action is not well developed.
There is no transcript of the trial nor was a narrative statement of the trial
proceedings prepared pursuant to Rule 1.30 of the Oklahoma Supreme Court Rules.
12 O.S.2011, ch. 15, app. 1. The district court's judgment does contain findings
of fact, two of which are helpful: ¶ 2: "[T]he parties entered into an agreement
for the tear off and replacement of Plaintiff's roof's [sic] among other repairs
and services;" ¶ 3: "'[I]mpact resistant' shingles . . . are considered to be an
upgrade from regular shingles and Plaintiff had agreed to pay the additional
amount to have the 'impact resistant' shingles installed." However, these facts
are insufficient to determine whether the "goods" aspect of the parties'
contract predominates over the services aspect.
¶10 From the exhibits introduced at trial, it can be established that the
total contract price for reroofing Fairchild's residence was $12,036.12. There
are nine "specifications" included in that contract describing the scope of work
to be done for the contract price. For example, in addition to removing and
hauling off the old shingles and installing the new ones, the contract called
for the installation of 30- weight felt to the entire roof, the installation of
ice and water shield around "stacks," and the installation of various vents and
gutters and six window screens. However, there is no segregation of the cost for
the materials, including the shingles, from the cost of the labor to complete
the work required by the contract. Consequently, the cost of the shingles as a
percentage of the total contract price cannot be determined. Swearingen contends
in his appellate brief that the cost of upgrading to impact resistant shingles
was $1,000. And, his counterclaim was for $1,000 less than the remaining balance
due on the contract. In his appellate briefs, Fairchild does not dispute that
the difference in the cost of the two kinds of shingles was $1,000. "Admissions
in a brief may be regarded as a supplement to the appellate record." Tyler v.
Shelter Mut. Ins. Co., 2008 OK 9, ¶ 11, n.9, 184 P.3d 496, 499.
¶11 Even considering the relatively minimal price differential between the
shingles installed and the shingles bargained for as that might reflect on the
cost of the shingles, we are unable to determine with certainty the value of the
shingles as a percentage of the entire contract. Consequently, the main purpose
of this contract cannot be determined from a cost comparison of the price of the
goods to the total price of the contract. It is clear, however, from the scope
of work described in the contract that much of this contract required labor and
services to remove the old shingles and install the new ones and provide the
various other services to install the new roof on Fairchild's residence. And, we
are guided by the principle announced by one court: "Construction contracts are
not governed by the UCC." Urban Dev., Inc. v. Evergreen Bldg. Prod., LLC,
59 P.3d 112, 116, (Wash. Ct. App. 2002). We conclude that the primary purpose of
the parties' contract was to provide the services required to install a new roof
and the shingles, although an important term of the contract, were incidental to
the main purpose of the contract. Consequently, this contract is not a
transaction in goods and the UCC does not apply. Fairchild's arguments based on
the UCC fail to show any error by the district court in granting the
Judgment.
II. The Judgment
¶12 Fairchild's second assignment of error argues the district court erred in
the form of relief granted in the Judgment. As discussed, the Judgment provided
alternative relief. The first option would have given Fairchild the roof with
high impact shingles that the parties' contract required. The second option
would have returned his down payment, the relief Fairchild requested in his
small claims petition. Nonetheless, Fairchild contends that the district court
erred in permitting Swearingen to select the form of relief to be provided.
Fairchild cites Keith v. Reid d/b/a Gold Spot Flooring, No. 107,405, slip
op. (Okla. Civ. App. July 12, 2011), in support of this proposition. That case
involved the installation of non-conforming carpet and applicable provisions of
the UCC governing the buyer's remedies pursuant to the UCC. As we held in Part I
of this Opinion, the UCC does not apply to the parties' contract in this
case.
¶13 Fairchild cites no other authority supporting this proposition
demonstrating any error by the district court, and we find none. First, the
district court may enter a judgment that provides alternate forms of relief.
Church v. Welch, 1918 OK
108, 170 P. 1168 (judgment
for plaintiff for return of house or the value of the house affirmed). Second,
the relief eventually received by the plaintiff may depend on the decision of
others and not the choice of the plaintiff. Id. ¶ 1, 170 P. at 1169
(affirming a judgment, after modification of the amount to conform to the
evidence, which provided: "[I]n the event the house could not be returned, the
plaintiff have and recover from the defendant the sum of $ 250, the value of
said house. . . ."). Third, the district court's Judgment in this case provided
that Fairchild would receive either what he originally contracted to receive
(new impact resistant roof), or what he sued to recover (his partial payment).
Clearly, the alternate forms of relief included in the Judgment were reasonable,
supported by the evidence at trial and well within the discretion of the
district court to award. In re Stackman, 1963 OK 264, ¶ 29, 388 P.2d 305, 311 (abuse does not
occur when discretion is exercised to an end or purpose justified by, and
clearly supported by, reason and evidence).
III. Rescission
¶14 Fairchild's final proposition argues he is entitled to rescind his
contract with Swearingen pursuant to Title 15 O.S.2011 § 233(2) and (4):
A party to a contract may rescind the same in the following cases
only:
* * *
2. If through the fault of the party as to whom he rescinds, the
consideration for his obligation fails in whole or in part.
4. If such consideration, before it is rendered to him, fails in a
material respect, from any cause. . . .
Even assuming installation of the non-conforming shingles would constitute a
failure of consideration warranting rescission of the parties' contract,
Fairchild's claim for rescission fails as a matter of law. A party seeking to
rescind a contract must return "everything of value" received pursuant to the
contract. Ware v. City of Tulsa, 1957 OK 148, ¶ 10, 312 P.2d 946, 950. Further,
Rescission, when not effected by consent, can be accomplished only by the
use, on the part of the party rescinding, of reasonable diligence to comply
with the following rules:
1. He must rescind promptly, upon discovering the facts which entitle him
to rescind, if he is free from duress, menace, undue influence, or
disability, and is aware of his right to rescind; and,
2. He must restore to the other party everything of value which he has
received from him under the contract; or must offer to restore the same,
upon condition that such party shall do likewise, unless the latter is
unable, or positively refuses to do so.
15 O.S.2011 § 235. There are
no facts in this record showing that Fairchild has offered to or can return the
materials used to install the roof, guttering and other items previously
installed on his house. Further, with respect to some of those items such as the
window screens, Fairchild intends to retain the benefit of that portion of the
contract. "A partial rescission cannot be had." Ware, 1957 OK 148, ¶ 10, 312 P.2d at 950.
Fairchild is not entitled to rescind his contract with Swearingen.
CONCLUSION
¶15 In this breach of contract action, the predominant purpose of the
contract was the labor and services required to remove a damaged roof and
install a new roof and items related thereto. The shingles used on the new roof
were incidental to the main purpose of the contract. Consequently, the contract
did not involve a transaction in goods and the Oklahoma Uniform Commercial Code
does not apply. The alternative forms of relief provided in the Judgment are
reasonable and within the power and discretion of the district court to order.
The district court did not err in leaving to Swearingen the selection of which
form of relief to provide. Finally, Fairchild is not entitled to rescind the
contract. The Judgment of the district court is affirmed.
BARNES, V.C.J., and WISEMAN, J., concur.