Woods Petroleum Corp. v. Delhi Gas Pipeline Corp.

700 P.2d 1023
CourtCourt of Civil Appeals of Oklahoma
DecidedJune 3, 1985
Docket57398
StatusPublished
Cited by23 cases

This text of 700 P.2d 1023 (Woods Petroleum Corp. v. Delhi Gas Pipeline Corp.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Woods Petroleum Corp. v. Delhi Gas Pipeline Corp., 700 P.2d 1023 (Okla. Ct. App. 1985).

Opinion

STUBBLEFIELD, Judge.

This is an appeal in an action brought by plaintiff, Woods Petroleum Corporation, seeking damages from Delhi Gas Pipeline Company for their alleged taking of plaintiffs’ gas without compensation. Plaintiff brought suit under pure negligence, res ipsa loquitor, conversion and breach of contract theories. The jury returned a verdict finding defendant negligent and giving recovery for the amount of gas estimated taken but not paid for ($858,022.40). The trial court awarded prejudgment interest and attorney fees to plaintiffs.

I

Plaintiff Woods Petroleum Corporation, hereinafter referred to as Woods, completed the O.M. Taylor 26-2, hereinafter referred to as Taylor # 2, in Dewey County, Oklahoma, in July of 1976. The Taylor # 2 was drilled to a depth of 9,575 feet and pierced two lenticular aspects of the Morrow formation. Both zones of the Morrow were perforated and production established as a gas well with some condensate production. The top zone of production was from the 9,401 to 9,406 foot depth; the lower zone from 9,434 to 9,448. Bottom pressure of the well was established at 4,500 pounds.

Defendant Delhi Gas Pipeline Corporation, hereinafter referred to as Delhi, had a contractual agreement to purchase the gas produced from the Taylor # 2. By the terms of this agreement Delhi was to provide and operate the metering equipment which measured the volume of gas Delhi took from the Taylor # 2.

The metering device Delhi installed on the Taylor # 2 consisted of a differential pressure flow meter. Such a device works by placing a restriction of a certain known size, known as an orifice plate, in a line of a certain known size, known as the meter run, and measuring the difference in pressure on either side of the orifice plate. Due to the physical fact that for a certain volume of gas to move through such a restriction a certain percentage of the pressure of the gas is translated into velocity, it becomes possible to determine precisely the volume of gas moving through the meter by measuring this pressure drop across the orifice plate. The critical factors in determining the flow are the size of the opening in the orifice plate, the pressure on the system and the temperature of the gas. Delhi’s meter on the Taylor # 2 recorded the differential pressure, the system pressure and the gas temperature on a seven day rotating paper chart.

Delhi began taking gas from the Taylor # 2 on October 26,1976. A notation on the paper chart, accompanied by the initials of Delhi’s meterman, on this day reflected that a .75 inch orifice plate had been removed and a 1.25 inch orifice plate installed in the meter run. The Taylor # 2 operated along lines expected for a Morrow formation well in the area. It was noted, however, that the well’s production was only about one-half of what had originally been expected.

On May 17, 1978, Woods pumper for the Taylor # 2 checked the well before noon, noting the wellhead pressure, the operation of the condensate separator/heater, the choke opening on the well, the production of condensate and the readings on Delhi’s chart. On this date the pumper recorded a differential pressure of 10. The next day when the pumper checked the well he found all conditions identical to those of the day before except for the differential pressure which had jumped from 10 to 44. A note had also been made on the chart that the orifice plate had been pulled and replaced with another 1.25 inch orifice plate. This note was accompanied by the initials of Delhi’s meterman. This change in the *1026 differential pressure indicated the gas production from the Taylor # 2 had increased from approximately 880 Mcf to approximately 1,600 Mcf of gas per day.

Shortly after this occurrence Woods requested an inspection of Delhi’s metering apparatus. At this inspection the apparatus tested out to be true and the orifice plate was pulled and measured to be 1.25 inches. Delhi's explanation to Woods for the sudden jump in production was that something must have happened in the well to cause an actual increase. Woods’ theory was that a larger orifice than a 1.25 inch had been in the meter run and that Delhi’s meterman had replaced it with the proper size orifice. Since Delhi had been figuring production using the flow factor for a 1.25 inch orifice, the larger orifice, with its attendant lower pressure drop, would have resulted in Woods being paid for much less gas than was actually being produced by the Taylor # 2. Woods reached the conclusion that a 1.75 inch orifice had actually been in the line prior to May 17, 1978, on the basis that a differential pressure of 10 multiplied by the coefficient for a 1.75 inch orifice equals a differential pressure of 44 multiplied by the true coefficient for a 1.25 inch orifice.

Delhi persisted in their denial that any size orifice other than a 1.25 inch had ever, been in the meter run and continued to maintain that the cause of the production increase was actually in the well itself.

Woods subsequently brought suit on behalf of itself and all other parties holding interests in the Taylor # 2 in the District Court of Dewey County on December 19, 1979. Woods initially alleged causes of action in negligence and conversion, and also alleged facts to invoke the doctrine of res ipsa loquitor. Woods asked for damages of $858,022.40 for gas taken by Delhi but unpaid for, and for $1,000,000 in punitive damages. An amendment to Woods petition was later filed alleging a cause of action for breach of contract. Woods arrived at the figure for actual damages by multiplying the amount of money actually paid to Woods by Delhi by the ratio between the flow coefficient for a 1.75 inch orifice plate and a 1.25 inch orifice plate.

Trial was held before a jury starting on July 14, 1981. On July 17, 1981, the jury returned a verdict finding for plaintiffs on the negligence theory and awarding $858,-022.40 in actual damages and no punitive damages. Judgment was entered pursuant to the jury’s verdict.

Defendant on appeal argues on five grounds: (1) that the verdict is not supported by the evidence; (2) that the trial court erred in submitting alternative theories of recovery to the jury; (3) that it was error to submit the question of punitive damages to the jury; (4) that false testimony necessitated a new trial; and (5) that it was error to award plaintiffs attorney fees.

II

The first proposition of error presented by Delhi is that the jury’s verdict was not supported by the evidence produced at trial and so should now be overturned. In the case of Walker v. St. Louis-San Francisco Railway Co., Okl., 646 P.2d 593 (1982), the court adhered to this rule:

“ ‘In a law action the verdict of the jury is conclusive as to all disputed facts and all conflicting statements, and where there is any competent evidence reasonably tending to support the verdict of the jury, this court will not disturb the verdict and judgment based thereon.’ [emphasis supplied]”

In the present case Woods presented extensive evidence that the only factor that changed on the Taylor # 2 on May 17,1978, was the increase in the differential pressure.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meyer v. Newrez, LLC
N.D. Oklahoma, 2025
Ritter, Laber & Associates, Inc. v. Koch Oil, Inc.
2004 ND 117 (North Dakota Supreme Court, 2004)
Grynberg v. Questar Pipeline Co.
2003 UT 8 (Utah Supreme Court, 2003)
Boatsman v. Southwestern Bell Yellow Pages, Inc.
2001 OK CIV APP 98 (Court of Civil Appeals of Oklahoma, 2001)
Okland Oil Company v. Conoco Inc.
144 F.3d 1308 (Tenth Circuit, 1998)
Sauer v. Xerox Corp.
938 F. Supp. 155 (W.D. New York, 1996)
Beshara v. Southern National Bank
1996 OK 90 (Supreme Court of Oklahoma, 1996)
Angier v. Mathews Exploration Corp.
1995 OK CIV APP 109 (Court of Civil Appeals of Oklahoma, 1995)
JBC of Wyoming Corp. v. City of Cheyenne
843 P.2d 1190 (Wyoming Supreme Court, 1992)
Scribner v. Hillcrest Medical Center
1992 OK CIV APP 117 (Court of Civil Appeals of Oklahoma, 1992)
Lucas v. Canadian Valley Area Vocational Technical School of Chickasha
1992 OK CIV APP 1 (Court of Civil Appeals of Oklahoma, 1992)
Palazzolo v. Colclazier (In Re Colclazier)
134 B.R. 29 (W.D. Oklahoma, 1991)
McGehee v. Florafax International, Inc.
1989 OK 102 (Supreme Court of Oklahoma, 1989)
Zenith Drilling Corporation v. Internorth, Inc.
869 F.2d 560 (Tenth Circuit, 1989)
Zenith Drilling Corp. v. Internorth, Inc.
869 F.2d 560 (Tenth Circuit, 1989)
Burk v. K-Mart Corp.
1989 OK 22 (Supreme Court of Oklahoma, 1989)