Chaney v. Fetterly

100 Wash. App. 140
CourtCourt of Appeals of Washington
DecidedMarch 31, 2000
DocketNo. 23728-8-II
StatusPublished
Cited by19 cases

This text of 100 Wash. App. 140 (Chaney v. Fetterly) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chaney v. Fetterly, 100 Wash. App. 140 (Wash. Ct. App. 2000).

Opinion

Morgan, J.

— The main question in this appeal is whether the doctrine of exhaustion of administrative remedies applies when a superior court and a quasi-judicial administrative agency have concurrent original jurisdiction. The answer is no.

The Chaneys and the Fetterlys own adjacent waterfront lots in Pierce County. The Fetterlys’ lot lies north of the [142]*142Chaneys’ lot. Each lot is long and narrow, irregularly shaped, and subject to the Pierce County Code’s administrative land use scheme.

The Pierce County Code (PCC) generally requires that a house be set back from the property line of the lot. It also contains procedures for obtaining variances and building permits, and procedures for appealing the decisions of County Wilding officials. PCC 15.01.060 states that “[a]ny person(s) or party directly aggrieved by the approval or denial of a building permit or application or by any administrative decision or order of the Building Official or his designee, pursuant to Chapter 1 of the Uniform Building Code [UBC] . . . may appeal to the Pierce County Hearing Examiner by filing a notice of appeal within 20 calendar days of the building permit or written decision or order, of the Building Official.”1 PCC 15.01.060 also states that “[t]he Decision of the Pierce County Hearings Examiner is final” unless an appropriate person “brings an action appealing ... to Superior Court.” ÍJBC ch. 1, § 108.5.2 provides that a foundation inspection shall “be made after excavations for footings are complete.” UBC ch. 1, § 108.1 states that when construction work is inspected by a building official, “[a] survey of the lot may be required by the building official to verify that the structure is located in accordance with approved plans.”2

In 1994, the Fetterlys wanted to build a house on their [143]*143lot. They wanted to locate it where their north and south boundaries were about 68 feet apart. The Pierce County Code required a north-side setback of 25 feet and a south-side setback of 30 feet. The result was a lawful buildable area of only 13 feet.

The Fetterlys applied for a variance, and a hearing was held. Ms. Chaney attended but did not speak. A hearing examiner granted the variance, which reduced the north-side setback to eight feet and the south-side setback to eight feet. No one appealed, and the propriety of the variance is not now disputed.

In April 1997, the Fetterlys obtained a building permit based in part on the eight-foot south-side setback. No one appealed, and the propriety of the building permit is not genuinely disputed.3

In late May or early June 1997, workers poured foundation footings for the new house. On June 4, 1997, a Pierce County building official approved the location of the foundation. On July 4 and July 5, 1997, the Chaneys notified the Fetterlys that the new house was encroaching into the eight-foot south-side setback area. The Fetterlys continued with construction. At present, however, the Fetterlys acknowledge that the house does indeed encroach into the eight-foot south-side setback area; according to a survey, it is within 2.6 feet of the Fetterly-Chaney boundary at one point, and no more than 7.88 feet from the Fetterly-Chaney boundary at any point.4

Later in July, while construction was still going on, the [144]*144Chaneys complained to Pierce County that the house was encroaching into the south-side setback. By letter dated July 30, 1997, the County declined to act. It said that the matter was “a property line dispute”; that “[resolution may be pursued as a [c]ivil [a]ction”; and that “Pierce County is not a party to property line disputes between neighbors.”5

Notwithstanding its letter of July 30, 1997, the County issued a stop work order on August 18, 1997. Two days later, on August 20, it lifted the order and stated again that the “[sjetback dispute is a civil matter[.]”6

On September 16, 1997, the Chaneys filed this original action in superior court. They prayed for an injunction and damages.

On January 22, 1998, the Fetterlys moved for summary judgment. They claimed that the Chaneys could not sue in superior court because the Chaneys had failed to exhaust their administrative remedies. The Fetterlys also claimed laches and equitable estoppel. The trial court granted the motion on the ground that the Chaneys had failed to exhaust their administrative remedies. After it dismissed the complaint with prejudice,7 the Chaneys brought this appeal.

I

According to the Fetterlys, the Chaneys may not sue for an injunction and damages because the Chaneys did not exhaust their administrative remedies through the County. The Fetterlys claim that the “Chaneys could have but failed to administratively appeal,” to a hearing examiner and then to superior court: (a) the County’s June 4 approval of the foundation; (b) the County’s July 30 refusal to act; and (c) the County’s August 20 withdrawal of the stop work order.8

[145]*145Describing the effect of the doctrine of exhaustion of administrative remedies, the Fetterlys say that the doctrine “prohibits a party from contesting an agency action in court unless the party has first exhausted available administrative remedies.”9 Before the effect of a doctrine can be material, however, the doctrine must apply. Here then, we examine whether the doctrine applies.

Whether the doctrine of exhaustion applies depends on the nature of the relationship between the administrative agency and the superior court. In situations where each has jurisdiction of some kind, the agency may have original jurisdiction, while the superior court has appellate jurisdiction; or, (2) the agency and the superior court may have concurrent original jurisdiction. The Supreme Court has recognized the first relationship by stating:

An appeal from an administrative tribunal invokes the appellate, rather than the general, jurisdiction of the superior court. [Union Bay Preservation Coalition v. Cosmos Dev. & Admin. Corp., 127 Wn.2d 614, 617, 902 P.2d 1247 (1995).] Acting in its appellate capacity, the superior court is of limited statutory jurisdiction, and all statutory procedural requirements must be met before jurisdiction is properly invoked. Fay v. Northwest Airlines, Inc., 115 Wn.2d 194, 197, 796 P.2d 412 (1990); Clymer v. Employment Sec. Dep’t, 82 Wn. App. 25, 27, 917 P.2d 1091 (1996).[10]

The Supreme Court has recognized the second relationship by stating that “[w]hen both a court and an agency have [146]*146jurisdiction over a matter, the doctrine of primary jurisdiction determines whether the court or the agency should make the initial decision.”11

The doctrine of exhaustion regulates the first relationship. It prevents a party from omitting to use, or starting to use but then abandoning before final conclusion, the only forum that has original jurisdiction.12 It functions much like RAP 2.213 and CR 54,14

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cost Management Services, Inc. v. City of Lakewood
310 P.3d 804 (Washington Supreme Court, 2013)
Cost Mgmt. Servs. v. City of Lakewood
Washington Supreme Court, 2013
Cost Management Services, Inc. v. City of Lakewood
284 P.3d 785 (Court of Appeals of Washington, 2012)
Spice v. Pierce County
204 P.3d 254 (Court of Appeals of Washington, 2009)
State v. Kirwin
165 Wash. 2d 818 (Washington Supreme Court, 2009)
Qwest Corp. v. City of Bellevue
166 P.3d 667 (Washington Supreme Court, 2007)
Ledgerwood v. Lansdowne
85 P.3d 950 (Court of Appeals of Washington, 2004)
Sundquist Homes, Inc. v. County of Snohomish
276 F. Supp. 2d 1123 (W.D. Washington, 2003)
SUNDERLAND FAMILY TREATMENT v. City of Pasco
26 P.3d 955 (Court of Appeals of Washington, 2001)
Sunderland Family Treatment Services v. City of Pasco
26 P.3d 955 (Court of Appeals of Washington, 2001)
Chelan County v. Nykreim
105 Wash. App. 339 (Court of Appeals of Washington, 2001)
Northwest Ecosystem Alliance v. Doe
17 P.3d 697 (Court of Appeals of Washington, 2001)
Northwest Ecosystems Alliance v. Department of Ecology
17 P.3d 697 (Court of Appeals of Washington, 2001)
Chaney v. Fetterly
995 P.2d 1284 (Court of Appeals of Washington, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
100 Wash. App. 140, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chaney-v-fetterly-washctapp-2000.