General Electric Company, a Corporation v. The United States

412 F.2d 1215, 188 Ct. Cl. 620
United States Court of Claims·Decided October 17, 1969·No. 370-67·Published·Cited by 11 cases

Opinions

COLLINS, Judge.

In the court’s view of this case, the main issue for decision is whether, under the Limitation of Cost article1 included in the instant cost-plus-fixed-fee contract, a contracting officer effectively exercised his discretion in favor of allowing overrun costs to the contractor, after General Electric failed to timely notify the Government of the overrun.

The pertinent peripheral facts, as found by the Armed Services Board of Contract Appeals2 and disclosed by the record, are essentially unchallenged by the parties and can be summarized as follows:

The instant research and development contract, executed in January 1964, resulted from plaintiff’s unsolicited proposal. It primarily required General Electric to design, fabricate, and test prior to delivery to the Government two “20MM Automatic Weapons Systems.” The contracting Government agency was the Army Weapons Command, Rock Island Arsenal, Illinois. The total estimated cost of the contract (as modified and exclusive of a fixed fee of $37,300) was $510,874. Plaintiff claims to have exceeded this cost estimate by $23,934, the overage arising from field testing of the completed armaments.

As provided at page 2 of Appendix A of the contract, primary supervision and administration was delegated to the Boston Procurement District,3 with techni[1218] cal supervision reserved to the Army-Weapons Command. Although nothing in the agreement specifically contemplated it, the Command also retained funding authority.

This administrative allocation of responsibility resulted in a purported separation of contracting officer’s functions and authority. Adding to the confusion was the fact that the Boston Procurement District was administering several thousand contracts concurrently with this one, had several contracting officers, and apparently had numerous Government contract representatives in subordinate positions with varied and limited grades of delegated authority. Indicative of the situation were the different signatures on the contract documents here: A Mr. Finn signed as contracting officer on the contract and on other later papers, but Messrs. Farrell and Champion also executed contract modifications or orders as contracting officers during the course of performance. Moreover, all of these documents were countersigned by a Mr. Lindblad as contracting officer, in the capacity, as the external evidence shows, of funding supervisor for the Army Weapons Command.

The person in the Government with whom plaintiff actually dealt (through its contract administrator, Mr. Aldrich) was a Mr. John Petze. Titled a “contract specialist,” Mr. Petze had no authority to modify the contract, but acted only as a Government contact for General Electric, as plaintiff was aware.4

The particular overrun in question was brought to Mr. Petze’s attention orally by Mr. Aldrich in August 1964. Previous overruns with respect to the instant contract had been timely mentioned to the Government in writing and were subsequently funded. Mr. Petze urged Mr. Aldrich to submit his proposal in writing, but, as Mr. Aldrich testified, he “goofed,” and no written notice of the overrun was received until September 25, 1964. The estimated amount of the overage was originally stated as $20,586, but was reduced to $12,888 by a letter from plaintiff in October 1964.

Plaintiff did not stop work on the contract when it became aware of the overrun, and coneededly incurred its additional costs prior to notifying defendant in writing. The board suggests that plaintiff’s failure to stop work was partly because both plaintiff and defendant considered the contract performance urgent. However, the board considered it likely that General Electric was motivated primarily by a desire to obtain the production contract which would naturally flow from the successful completion of the research and development performance.

Plaintiff’s claim is predicated upon the correspondence between the Boston [1219] Procurement District and the Army Weapons Command subsequent to General Electric’s notice of September 1964. On October 2, 1964, Mr. Whalley, a contracting officer’s representative and Mr. Petze’s superior, wrote to the Army Weapons Command concerning the availability of funds for modification of the contract by reason of the overrun. Mr. Lindblad, who, as previously mentioned, was funding contracting officer for the Command, replied on October 22, 1964, requesting investigation and justification of the contractor’s claim in terms of the Limitation of Cost article. In January 1965, Government representatives investigated the overrun and found the costs stated in plaintiff’s submission to be reasonable. On March 9, 1965, Mr. Whalley again wrote the Command, stating that the additional costs were justified on the basis of Government analyses and recommending funding of the overrun. The reports of the investigators were included.

On June 7, 1965, the Army Weapons Command wrote asking several questions about the overage. By letter of June 30, 1965, the Boston Procurement District answered the questions and stated the legal opinion that neither advance notice nor a request for continued work was mandatory to the funding of the overrun. The letter concluded as follows:

4. It is the opinion of the undersigned that it is within the discretionary authority of the Contracting Officer under the contract article, “Limitation of Costs,” to fund the overrun of $12,880.00 [sic], and the undersigned further recommends that the Contracting Officer take such funding action.
For the Commander:
/s/ Sumner A. Marcus Sumner A. Marcus Chief, Legal Office
Concur With Recommendation:
/s/ R. F. McDermott
R. F. McDermott Lt Col, Ord Corps Contracting Officer

On August 1, 1965, the previously delegated administrative authority with respect to this contract and others was removed from the Boston Procurement District and reverted to the Army Weapons Command. Mr. Lindblad assumed the duties of procuring contracting officer. On September 29, 1965, Mr. Lind-blad wrote to the Defense Contract Administration Services Region, Boston, indicating that the June 30. letter from the Boston Procurement District did not provide justification for funding the overrun. He further stated that the request for funds was disapproved “unless a determination is made by the Administrative Contracting Officer that he had explicitly or tacitly acquiesced to the continuation of work, having full knowledge of the cost overrun.” The Region replied that no Government personnel knew of the overrun prior to September 25, 1964, but nonetheless confirmed the previous recommendation of the Boston Procurement District that the overrun be funded. After additional correspondence along the same lines, as well as letters from plaintiff further modifying its estimate of overrun costs, Mr. Lind-blad issued a final decision on September 7, 1966, denying reimbursement on the basis of the Limitation of Cost article.

Free access — add to your briefcase to read the full text and ask questions with AI

General Electric Company, a Corporation v. The United States, 412 F.2d 1215, 188 Ct. Cl. 620 (cc 1969).

412 F.2d 1215 (General Electric Company, a Corporation v. The United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sikorsky Aircraft Corp. v. United States
105 Fed. Cl. 657 (Federal Claims, 2012)
Boeing Co. v. United States
75 Fed. Cl. 34 (Federal Claims, 2007)
Johnson Controls World Services, Inc. v. United States
48 Fed. Cl. 479 (Federal Claims, 2001)
Ebasco Services, Inc. v. United States
41 Cont. Cas. Fed. 77,082 (Federal Claims, 1997)
McDonnell Douglas Corp. v. United States
41 Cont. Cas. Fed. 77,046 (Federal Claims, 1997)
Texas Instruments Incorporated v. The United States
922 F.2d 810 (Federal Circuit, 1991)
Fischbach & Moore International Corp. v. United States
617 F.2d 223 (Court of Claims, 1980)
American Electric Contracting Corp. v. United States
579 F.2d 602 (Court of Claims, 1978)