Dravo Corp. v. United States

480 F.2d 1331, 202 Ct. Cl. 500, 1973 U.S. Ct. Cl. LEXIS 80
CourtUnited States Court of Claims
DecidedJuly 13, 1973
DocketNo. 39-72
StatusPublished
Cited by15 cases

This text of 480 F.2d 1331 (Dravo Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dravo Corp. v. United States, 480 F.2d 1331, 202 Ct. Cl. 500, 1973 U.S. Ct. Cl. LEXIS 80 (cc 1973).

Opinions

Nichols, Judge,

delivered the opinion of the court:

This case is before the court on plaintiff’s motion for summary judgment and defendant’s cross motion for summary judgment.

Plaintiff entered into a fixed price contract (No. DACW01-68-C-0088) with the Department of the Army on April IT, 1968, for the construction of the Jones Bluff Lock and Dam on the Alabama Elver in Alabama. Article 50 of the general provisions of the contract entitled “Value Engineering Incentive” provided that the contractor and the Government would share in savings in the cost of performance of the contract which resulted from changes proposed by the contractor. On May 22, 1968, plaintiff submitted a proposal for a change in the design and construction of the cofferdam required by the contract along with a suggested adjustment in the contract price, not including any decrease in profit on the work originally included in the contract, which would now be [503]*503deleted as the result of plaintiff’s proposal. On September 25, 1968, the contracting officer informed plaintiff that its proposal was acceptable but that the decrease in the contract price must also include a decrease in plaintiff’s anticipated profits. Plaintiff proceeded to do the work as changed, under protest. On May 9, 1969, the contracting officer rendered his final decision that a reduced profit must be reflected in the contract cost reduction. Plaintiff appealed this decision to the Corps of Engineers Board of Contract Appeals (The Board) on May 27,1969. In a decision, Eng. BCA No. 3046, dated August 17,1971, the Board upheld the decision of the contracting officer, stating that the decrease in costs under Article 50 was to be calculated as an equitable adjustment and thus elimination of some profits must be added to the eliminated cost to determine the adjusted price.

The parties are in agreement as to the facts of the case and the figures used in arriving at the cost reduction. They disagree only as to whether Article 50 calls for the calculation of profit as part of the cost savings. Thus, the controversy in this case centers around the varying interpretations of Article 50 of the contract, and therefore the court is faced with a pure question of law. We hold that the plaintiff is right, and the Board in error.

Plaintiff tells us that the language of Article 50 indicates that the amount of cost reduction must be calculated from the point of view of cost savings to the contractor. Therefore, profit should not be included in arriving at the amount saved. The court’s attention is invited to the pertinent regulations involved, and to the administrative history of those regulations, all of which the plaintiff says supports its position.

Defendant tells us, to the contrary, that the only reasonable meaning that can be given Article 50 is to read its provisions from the point of view of savings to the Government. Defendant argues that the pertinent regulations and their administrative history as they relate to fixed price .contracts support its position. Finally, the defendant avers that the court should not depart from the usual method of calculating equitable adjustment under the circumstances of this case, and we [504]*504are reminded that normally the calculation of equitable adjustment includes profit.

The objective in interpreting a contract is to determine the intention of the parties. The language of the contract must be given the meaning that would be understood by a reasonably intelligent person acquainted with the contemporary circumstances. Firestone Tire & Rubber Co. v. United, States, 195 Ct. Cl. 21, 444 F. 2d 547 (1971). All provisions of the contract should be read together and so as to make none inoperative, and specific provisions should be given precedence over general ones. Morrison-Knudsen Co. v. United States, 184 Ct. Cl. 661, 397 F. 2d 826 (1968). If the contract is unambiguous its language should be implemented. Keco Industries v. United States, 176 Ct. Cl. 983, 364 F. 2d 838 (1966), cert. denied, 386 U.S. 958 (1967). As an aid to interpretation of the contract the pertinent ASPE, should be inspected and the policy behind the promulgation of these regulations should be looked into. Firestone Tire ds Rubber, sufra. Such regulations are law, binding on the contract parties, where applicable. Newfort News Shipbuilding & Dry Dock Co. v. United States, 179 Ct. Cl. 97, 374 F. 2d 516 (1967); Chris Berg, Inc. v. United States, 192 Ct. Cl. 176, 426 F. 2d 314 (1970).

That portion of the contract which is at the center of controversy in this case is Article 50 of the General Provisions of the contract. That Article reads in pertinent part:

❖ * * *
50. VALUE ENGINEERING INCENTIVE (JUNE 1967) (Applicable to dll contracts in excess of $100,000)
(a)(1) This clause applies to those cost reduction proposals initiated and developed by the Contractor for changing the drawings, designs, specifications, or other requirements of this contract. This clause does not, however, apply to any such proposal unless it is identified by the Contractor, at the time of its submission to the Contracting Officer, as a proposal submitted pursuant to this clause. * * *
(2) The cost reduction proposals contemplated are those that:
(i) would require, in order to be applied to this contract, a change to this contract; and
[505]*505(ii)would result in savings to the Government by providing a decrease in the cost of performance of this contract, without impairing any of the items’ essential functions and characteristics such as service life, reliability, economy of operation, ease of maintenance, and necessary standardized features.
(b) As a minimum, the following information shall be submitted by the Contractor with each proposal:
(i) a description of the difference between the existing contract requirement and the proposed change, and the comparative advantages and disadvantages of each;
(ii) an itemization of the requirements of the contract which must be changed if the proposal is adopted, and a recommendation as to how to make each such change (e.g., a suggested revision);
(iii) an estimate of the reduction in performance costs, if any, that will result from adoption of the proposal, taking into account the costs of development and implementation by the Contractor (including any amount attributable to subcontracts in accordance with paragraph (e) below) and the basis for the estimate;
(iv) a prediction of any effects the proposed change would have on collateral costs to the Government such as Government-furnished property costs, costs of related items, and costs of maintenance and operation;
*****
(c) (1) Cost reduction proposals shall be submitted to the Procuring 'Contracting Officer (PCO). * * *

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bay County, Florida v. United States
112 Fed. Cl. 195 (Federal Claims, 2013)
Colorado Pool Systems, Inc. v. Scottsdale Insurance Co.
2012 COA 178 (Colorado Court of Appeals, 2012)
Moreland Corp. v. United States
76 Fed. Cl. 268 (Federal Claims, 2007)
Omni Moving & Storage of Virginia, Inc. v. United States
38 Cont. Cas. Fed. 76,481 (Federal Claims, 1993)
PBI Electric Corp. v. United States
35 Cont. Cas. Fed. 75,669 (Court of Claims, 1989)
Blount Brothers Corporation v. The United States
878 F.2d 1446 (Federal Circuit, 1989)
State v. Cosgrove
442 A.2d 1320 (Supreme Court of Connecticut, 1982)
Kolar, Inc. v. United States
650 F.2d 256 (Court of Claims, 1981)
Fairfield Scientific Corp. v. United States
611 F.2d 854 (Court of Claims, 1979)
American Electric Contracting Corp. v. United States
579 F.2d 602 (Court of Claims, 1978)
Grismac Corp. v. United States
556 F.2d 494 (Court of Claims, 1977)
Airmotive Engineering Corp. v. United States
535 F.2d 8 (Court of Claims, 1976)
Pacific Architects & Engineers Inc. v. United States
491 F.2d 734 (Court of Claims, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
480 F.2d 1331, 202 Ct. Cl. 500, 1973 U.S. Ct. Cl. LEXIS 80, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dravo-corp-v-united-states-cc-1973.