Grismac Corp. v. United States

556 F.2d 494, 23 Cont. Cas. Fed. 81,336, 214 Ct. Cl. 39, 195 U.S.P.Q. (BNA) 241, 1977 U.S. Ct. Cl. LEXIS 55
CourtUnited States Court of Claims
DecidedMay 18, 1977
DocketNo. 4-72
StatusPublished
Cited by23 cases

This text of 556 F.2d 494 (Grismac Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grismac Corp. v. United States, 556 F.2d 494, 23 Cont. Cas. Fed. 81,336, 214 Ct. Cl. 39, 195 U.S.P.Q. (BNA) 241, 1977 U.S. Ct. Cl. LEXIS 55 (cc 1977).

Opinion

Nichols, Judge,

delivered the opinion of the court:

This case is before the court on defendant’s exceptions to fact findings, conclusion of law, and proposed opinion filed by Trial Judge C. Murray Bernhardt in accordance with Rule 134(h). The facts found by the court are those stated in this opinion. It is unnecessary to pass on both parties’ exceptions to the trial judge’s fact findings, as they would not change the result if sustained. We differ with the trial judge’s legal conclusions, though we are greatly aided by his able analysis of the novel and interesting problem presented. We conclude that the action cannot be maintained and the petition must be dismissed.

The suit is under the Tucker Act, 28 U.S.C. § 1491, to enforce an alleged contract or contracts "implied in fact.” The parties have not discussed, nor do we consider, whether the action is maintainable in face of 31 U.S.C. § 200. Our conclusion is reached on other grounds.

Our legal conclusion considerably diminishes the amount of detail as to the facts that need be stated.

In the spring of 1969 plaintiff submitted proposals 63314 and 63316 to the Army Ammunition Procurement and Supply Agency at Joliet, Illinois ("APSA”), and proposal 63313 to the Savanna Army Depot in Savanna, Illinois. Proposal 63313 was handled by APSA along with the other two. Each proposal was headed "Unsolicited Value Engineering Proposal.” No. 63313, dated March 20, 1969, recommended that the decks for wooden pallets used as a base for storing and handling boxed ammunition employ a cheaper CD grade of plywood instead of the prevailing CC grade. No. 63314, dated March 21, 1969, recommended the same plywood substitution for wirebound ammunition crates. No. 63316, dated June 18, 1969, recommended reduction of the standard deck size of the pallet from 27-%“ x 34-%" to a deck of smaller dimensions, so that five rather than three decks could be obtained from a standard size 48" x 96" plywood sheet and at the same time accommodate the varying stacked dimensions of ammunition boxes loaded thereon, with an obvious saving from waste reduction.

[42]*42Each of the three proposals bore the following restrictive legend:

Notice: The data contained herein shall not be disclosed outside the government, or duplicated, used, or disclosed in whole or in part, for any purpose other than to evaluate this value engineering proposal; except that if this proposal be accepted by the government, the government shall have the rights to the use of the data, and may duplicate or disclose, in whole or in part, in any manner and for any purpose whatsoever, and shall have or permit others to do so, to the extent necessary to fully utilize the proposal.

Each proposal also expressed the plaintiffs desire to negotiate compensation in the form of a share in the Government’s present and future contract savings attributable to use of the proposal.

Because of the "value engineering” title on each of plaintiffs proposals, all three when received by APSA’s Value Engineering Office ("VEO”) were forwarded to appropriate Army offices charged with the evaluation of value engineering change proposals ("VECP”). VECP’s were (and are) cost reduction proposals offered to the Government under existing express contracts pursuant to Armed Services Procurement Regulation ("ASPE”) 1-1701 et seq., 32 C.F.R. §§ 1.1701 et seq. (1969). If a proposal was deemed meritorious, i.e., technically adequate, beyond existing contract requirements, and cost-saving, the cognizant office was to incorporate it into current procurement specifications for that item. Since a compensable VECP could be submitted by a contractor only under an existing contract containing a "value engineering incentive clause,” he would be compensated if at all by an adjustment under his existing contract. No separate contract to compensate for use of the idea was needed.

The problem here is that despite the fact that plaintiff had no express contract with the Army containing a value engineering incentive clause as a basis for its proposals, the proposals themselves were nevertheless incorporated into Army procurement specifications as if they were VECP’s, and were thereafter used throughout the Army. At the outset APSA’s VEO noted that the proposals were "unsolicited,” i.e., without an existing contract as a predicate, but [43]*43raised no questions and did not alter its procedures on that account. The thought of procedural deficiencies did not occur to VEO until after the Army had adopted and used the suggestions. Instead, as stated, VEO routed the proposals upon receipt to the cognizant offices for processing. No. 63314 went to Picatinny Arsenal at Dover, New Jersey ("Picatinny”), and Nos. 63313 and 63316 went to APSA’s Technical Data Division ("TDD”). After processing clearance through a chain of technically cognizant offices the proposals were changed in minor respects, adopted, and thereupon distributed to all Government-owned, contractor operated ("Go-co”) load plants as official changes (mostly mandatory) in the applicable technical instructions and/or engineering orders, so that thereafter all such pallets had to conform to the changes suggested by plaintiff (changes in material for wirebound boxes were optional), with minor amendments.

In point of fact the ideas were not entirely new. Some Army installations had arrived at similar ones, unknown to plaintiff and the officials with which it dealt, and had put them into effect. Details as to this are not necessary as it is not the ground of our decision, though defendant has argued lack of novelty at length and denies that plaintiff actually brought about the changes in practice above-mentioned. We do not pass on this.

Having, as it supposed, put plaintiffs ideas to extensive use, VEO belatedly turned its attention to the question of compensation. Plaintiff obviously never expected to make its contribution for nothing, and the effective immediate seizure and use of it with the failure to compensate or even discover a basis of compensation, caused and still causes the Army to cut a bruta figura, as an Italian would say. Initially, the problem was a dispute among Army lawyers as to whether 10 U.S.C. § 2386 (further discussed below) and implementing regulations (as to which also see below) permitted the expenditure of procurement funds to pay plaintiff for its ideas. Then surfaced the issue of originality, and other matter throwing doubt on the value of the ideas. Plaintiff wanted $1,500,000, and is demanding $3,519,761 here, with a percentage of future savings. Ultimately APSA decided to work up a proposal to pay $50,000 under [44]*44the present statutory successor to the First War Powers Act, now 50 U.S.C. §§ 1431-1435, as the effectuation of an informal commitment. Implementing regulations under this authority, as they were then, are in ASPR § 17-000 and ff., 32 C.F.R. § 17.000 and ff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carter v. United States
Federal Claims, 2021
Anderson v. United States
73 Fed. Cl. 199 (Federal Claims, 2006)
Garza v. United States
34 Fed. Cl. 1 (Federal Claims, 1995)
Scope Enterprises, Ltd. v. United States
18 Cl. Ct. 875 (Court of Claims, 1989)
Roberts v. United States
13 Cl. Ct. 774 (Court of Claims, 1987)
John J. Kirlin, Inc. v. The United States
827 F.2d 1538 (Federal Circuit, 1987)
John J. Kirlin, Inc. v. United States
33 Cont. Cas. Fed. 74,823 (Court of Claims, 1986)
First National Bank v. United States
8 Cl. Ct. 774 (Court of Claims, 1985)
Western Pioneer, Inc. v. United States
32 Cont. Cas. Fed. 73,617 (Court of Claims, 1985)
Rider v. United States
32 Cont. Cas. Fed. 73,473 (Court of Claims, 1985)
Phelps v. United States
32 Cont. Cas. Fed. 72,715 (Court of Claims, 1984)
City of Alexandria v. The United States
737 F.2d 1022 (Federal Circuit, 1984)
Schuhl v. United States
3 Cl. Ct. 207 (Court of Claims, 1983)
American Hoist & Derrick, Inc. v. United States
31 Cont. Cas. Fed. 71,392 (Court of Claims, 1983)
Grundy v. United States
2 Cl. Ct. 596 (Court of Claims, 1983)
City of Klawock v. United States
31 Cont. Cas. Fed. 71,244 (Court of Claims, 1983)
Ofria v. Commissioner
77 T.C. 524 (U.S. Tax Court, 1981)
Kania v. United States
650 F.2d 264 (Court of Claims, 1981)
Radioptics, Inc. v. United States
621 F.2d 1113 (Court of Claims, 1980)
Centron Corp. v. United States
585 F.2d 982 (Court of Claims, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
556 F.2d 494, 23 Cont. Cas. Fed. 81,336, 214 Ct. Cl. 39, 195 U.S.P.Q. (BNA) 241, 1977 U.S. Ct. Cl. LEXIS 55, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grismac-corp-v-united-states-cc-1977.