The B. F. Goodrich Company v. The United States

398 F.2d 843, 185 Ct. Cl. 14, 1968 U.S. Ct. Cl. LEXIS 145
CourtUnited States Court of Claims
DecidedJuly 17, 1968
Docket328-66
StatusPublished
Cited by7 cases

This text of 398 F.2d 843 (The B. F. Goodrich Company v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The B. F. Goodrich Company v. The United States, 398 F.2d 843, 185 Ct. Cl. 14, 1968 U.S. Ct. Cl. LEXIS 145 (cc 1968).

Opinion

COLLINS, Judge.

This case is before the court on cross-motions for summary judgment. The facts are not in dispute.

On March 18, 1963, plaintiff was awarded contract No. AF33 (657) 10560 for the manufacture of a quantity of brake and wheel adjuster assemblies with separate parts and data at a price of $230,849.50. The contract, however, *845 stipulated that its effective date was January 18, 1963. Plaintiff had signed the contract on February 27, 1963, although there obviously had been negotiations between the parties for some time before then. The contract was made on behalf of the Government by the Aeronautical Systems Division, Wright-Patterson Air Force Base, Ohio. Delivery was to be completed by December 31,1963.

Sometime before December 26, 1962, while negotiations were still going on between the parties and prior to the award of the contract, plaintiff received a telephone call from an official at the Hill Air Force Base, Ogden, Utah, a future consignee of some of the material to be manufactured under the proposed contract. This official asked plaintiff to study the possibility of modifying the heat shield of the assemblies so as to allow removal of certain tie bolts without removing the heat shield. This change involved semicircular slots for the bolts and thicker material for stability of the heat shield assembly. The record does not show what was said in that phone conversation. The correspondence between the parties indicates that the Hill Air Force Base official requested data on how his suggested modification of the heat shield would affect its structural stability. On January 25, 1963, Hill Air Force Base was notified by plaintiff that the proposal was practicable, and that a prototype was being manufactured. On March 20, 1963, plaintiff forwarded to Hill Air Force Base a drawing incorporating various modifications of the heat shield. Plaintiff asked defendant to review the drawing since plaintiff desired to include the modified heat shield on all new wheel assemblies. On April 16, 1963, Hill Air Force Base approved the drawing with the recommendation that the revision be included in all future procurement.

Plaintiff incorporated this revision in the units manufactured and delivered under this contract, and the units were accepted and paid for by defendant. Of the 1,373 assemblies called for in the contract, 1,349 were finally accepted prior to November 29, 1963. Seventeen of the remaining 24 assemblies were accepted on January 9, 1964, and 7 on January 31, 1964. The final payment to plaintiff under the contract was made April 14, 1964.

By letter dated January 8, 1964, the contracting officer advised plaintiff that the revision had “resulted in a cost savings,” of which the Government was entitled to a 50-pereent share under the Value Engineering Incentive clause. 1 That letter read as follows:

1. The revision of Part No. 72-155 and incorporation of Part No. 72-155-1 in Part No. 3-945, Wheel Assembly for the T-38 aircraft, resulted in a cost savings in the 825 units concerned on subject contract. In accordance with the Value Engineering Clause in AF-10650, this savings shall *846 be shared at a rate of 50% by the contractor and the Government.
2. It is therefore requested that the contractor submit information to the Government indicating the amount of savings involved, and the amount proposed to be credited to the Government. Your response is requested immediately in order to prevent further delay of the contemplated amendment to this contract.

Plaintiff contested defendant’s claim for 50 percent of the savings, pointing out that, since the modification had been initiated by the Government, and not by plaintiff, the Value Engineering Incentive clause (provision 48) did not apply.

The parties maintained their positions in further correspondence. On May 22, 1964, the contracting officer wrote plaintiff a letter stating, in part, that “[t]he change in part number of a heat shield, a class I change, under this contract should have been accomplished under Engineering Change proposal provisions * * *. Approval of the new heat shield by Ogden Air Materiel Area did not constitute proper authorization to make this change.” The contracting officer still insisted that no change order could have been made, and he again attempted to invoke clause 48, asking that 50 percent of the savings be paid to the Government.

On July 22, 1964, the contracting officer wrote to plaintiff that, “[a]pproval of the new heat shield by Ogden Air Materiel Area did not constitute proper authorization to make this change.” He further stated, however, that “[t]he change as directed has been approved by the Contracting Officer. The change thus approved appears to have resulted in decreased cost of performing the contract and therefore, under the Changes clause of the contract, a downward equitable adjustment is due the government.” The contracting officer also requested plaintiff to “submit within thirty days your proposal for the equitable adjustment to which the government is entitled.” This was his first suggestion for an adjustment under the Changes clause.

On September 22, 1964, the contracting officer entered his “final decision” on plaintiff’s claim. In that decision, he stated that “[ajpproval of the new heat shield by Ogden Air Materiel Area did not constitute proper authorization” to make the change. Then the decision continued:

* * * Under the provisions of the Changes Clause the Contracting Officer determines that the Government is entitled to an equitable adjustment by way of adjustment in contract price in the amount of $14,-908. As a result the Contractor has been overpaid on subject contract in the amount of $14,908, demand for which is hereby made.

Plaintiff then filed an appeal with the Armed Services Board of Contract Appeals, which rendered its decision on June 15, 1965. ASBCA No. 10373, 65-2 BCA |f 4910. That opinion concluded:

We agree with the appellant that this modification was not within the Value Engineering Incentive clause of this contract. * * * [T]he modification was in fact originally initiated by the Government, although the actual format of its development came from the appellant.
After the modification had been approved by the Government, it was incorporated in the units manufactured for this contract. It does not appear who determined that this should be done, but they were so accepted and paid for at the contract price. The contracting officer has never rejected them or objected to them. This constitutes an acceptance of a deviation. It is well established that this constitutes a change under the Changes article, and that an equitable adjustment may be made in the contract price for the increase or decrease in costs thereby incurred. No question has been raised as to the amount of the claim. It is therefore our conclusion *847 that the Government is entitled to an equitable adjustment for the entire cost reduction of $14,908.00. Appellant is, however, entitled to a credit against this amount for its costs of $317.49.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Herman JCG Co. JV¹
Armed Services Board of Contract Appeals, 2024
Robin Industries, Inc. v. United States
29 Fed. Cl. 122 (Federal Claims, 1993)
John J. Kirlin, Inc. v. The United States
827 F.2d 1538 (Federal Circuit, 1987)
John J. Kirlin, Inc. v. United States
33 Cont. Cas. Fed. 74,823 (Court of Claims, 1986)
Derrick Electric Co.
618 F.2d 122 (Court of Claims, 1979)
Grismac Corp. v. United States
556 F.2d 494 (Court of Claims, 1977)
Airmotive Engineering Corp. v. United States
535 F.2d 8 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
398 F.2d 843, 185 Ct. Cl. 14, 1968 U.S. Ct. Cl. LEXIS 145, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-b-f-goodrich-company-v-the-united-states-cc-1968.