Airmotive Engineering Corp. v. United States

535 F.2d 8, 22 Cont. Cas. Fed. 80,287, 210 Ct. Cl. 7, 1976 U.S. Ct. Cl. LEXIS 3
CourtUnited States Court of Claims
DecidedMay 12, 1976
DocketNos. 43-74 & 151-74
StatusPublished
Cited by9 cases

This text of 535 F.2d 8 (Airmotive Engineering Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Airmotive Engineering Corp. v. United States, 535 F.2d 8, 22 Cont. Cas. Fed. 80,287, 210 Ct. Cl. 7, 1976 U.S. Ct. Cl. LEXIS 3 (cc 1976).

Opinion

Ktjnzig, Judge,

delivered the opinion of the court:

In these combined contract renegotiation cases of first impression, plaintiff comes before the court seeking a determination that certain value engineering (YE) incentive awards received from defendant are not subject to renegotiation within the provisions of the Renegotiation Act (the Act). Because the YE awards were received by 'plaintiff under a contract subject to renegotiation, we deny plaintiff’s motion for summary judgment.

On January 12,1968, plaintiff and the Department of the Air Force entered into a one-year service contract for the repair of jet engine blades. The contract contained a YE incentive clause providing for payment of a ten .percent award to plaintiff based on Government savings in property, operations or logistical support costs.1 The contract also [10]*10granted plaintiff a fifty percent award for any savings related to Government-furnished material under the contract.2

In March of 1968, plaintiff made several recommendations to defendant calculated to reduce the high amount of jet engine blade scrappage incurred during normal repair procedures. Defendant adopted the recommendations and reaped a considerable savings. After years of disagreement and three Armed Services Board of Contract Appeals decisions, plaintiff received some $6.2 million in YE awards.

Subsequently, the Renegotiation Board (the Board) concluded that the YE awards constituted renegotiable “receipts and accruals” subject to the Act. The Board determined that plaintiff had realized $2.2 million in excessive profits for fiscal years 1969 and 1970. Plaintiff then brought the present action before the Court of Claims for da novo determination of excessive profits represented by the YE awards.

Plaintiff enters a motion for summary judgment contending that the YE awards are not subject to the Act. Plaintiff also requests oral argument. Defendant opposes the summary judgment motion, arguing that the YE awards are contract payments contemplated by the Renegotiation Act. The court agrees with defendant at this stage of the case and, therefore, denies plaintiff’s summary judgment motion.

Plaintiff enters a multi-phased argument that the YE awards should not be held subject to renegotiation primarily on the basis that the YE awards are not “profits” subject to the Act. In support of this premise, plaintiff contends: (1) the payments were not contractually required, (2) the awards were merely a “unilateral” compensation made to plaintiff by defendant, (3) the YE incentives were merely a part of Government savings, (4) to subject the VE awards to renegotiation would destroy contractor incentive and (5) any interpretation subjecting the awards to renegotiation would conflict with Armed Service Procurement Regulations (ASPRs).

[11]*11Plaintiff’s theory cannot prevail.

Plaintiff’s main argument is that the YE awards are not “profits” subject to the Renegotiation Act. However, such a contention “glosses over” the clear terms of the Act itself. Renegotiation specifically applies to contracts with (among others) the Department of the Air Force (50 U.S.C. App. § 1213(a) (1970)) “to the extent of the amounts received or accrued by a contractor * * * on or after the first day of January 1951.” 50 U.S.C. App. § 1212(a) (1970). Neither party disputes the fact that plaintiff’s contract with the Air Force was subject to the provisions of the Act.

Under the Act, “excessive profits” are to be eliminated by including a “renegotiation clause” in each Government contract. Contractors are thereby required to agree “to the elimination of excessive profits through renegotiation.” 50 U.S.C. App. §1214(1) (1970). In the instant case, neither party claims that such an agreement was excluded from the January 12,1968 contract. The question presented for resolution then becomes whether or not plaintiff’s YE awards were “excessive profits” subject to renegotiation.

Congress carefully defined what it intended by use of the phrase “excessive profits.” Subsection 1213 (e) provides:

The term ‘excessive profits’ means the portion of the profits derived from contracts with the Departments and subcontracts which is determined in accordance * * * [with the Act] to be excessive * * *. [50 U.S.C. App. § 1213(e) (1970)].

Subsection 1213(f) further clarifies the meaning of profits:

The term ‘profits derived from contracts with the Departments and subcontracts’ means the excess of the amowit received or accrued wnder such contracts and subcontracts over the costs paid or incurred with respect thereto and determined to be allocable thereto. [50 U.S.C. App. § 1213(f) (1970) (emphasis added)].

In short, the Act clearly contemplates that all “receipts and accruals” obtained as a result of performance of renegotiable contracts will be part of the renegotiation formula.

An early interpretation of the Renegotiation Board further buttresses the conclusion that Congress intended to subject value engineering incentive awards to renegotiation. [12]*12Renegotiation Ruling No. 3, 32 CFR § 1499.1-3. (1975) (originally promulgated June 1,1961) provides:

when a value engineering recommendation made by a contractor is adopted, the contract price is adjusted upward to allow the contractor a greater profit than he would otherwise have realized. The amount of the award thus becomes a receipt or accrual to the contractor pursuant to the terms of the contract, and, if the contract is subject to the [A]ct, the amount of the award is a renegotiable receipt or accrual * * *. [32 CFR § 1499. 1-3(b) (1975)].

Indeed, such a “long standing administrative interpretation” is entitled to a great deal of weight, Commissioner v. Noel's Estate, 380 U.S. 678, 682 (1965); Fox v. United States, 145 Ct. Cl. 186 (1959), cert. denied, 361 U.S. 887 (1959), particularly, as in the instant case, where it clearly follows statutory guidelines.

In the present action, the YE award payments obviously constituted amounts received or accrued by plaintiff under the terms of a renegotiable contract for the repair of jet engine blades. Under the clear provisions of the Act, plaintiff’s YE awards were subject to renegotiation and plaintiff’s argument that the YE awards were not excessive profits must fail.

Plaintiff’s remaining arguments represent guides to interpretation of the Renegotiation Act. As defendant properly points out, where a statute is unambiguous, such “wording * * * shall be given its plain and commonly understood meaning.” Sharples v. United States, 209 Ct. Cl. 509, 533 F. 2d 550 (1976). See also Sode v. United States, 209 Ct. Cl. 180, 531 F. 2d 531 (1976); Selman v. United States, 204 Ct. Cl. 675, 680, 498 F. 2d 1354, 1356 (1974); and Prudential Ins. Co. v. United States, 162 Ct. Cl. 55, 65, 319 F. 2d 161, 166 (1963).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern New Eng. T. v. Dept., Pub. Ut., No. Cv 99 0497867s (Feb. 9, 2001)
2001 Conn. Super. Ct. 2379 (Connecticut Superior Court, 2001)
United States v. Gutierrez-Gonzalez
184 F.3d 1160 (Tenth Circuit, 1999)
Edwards v. United States
36 Cont. Cas. Fed. 75,822 (Court of Claims, 1990)
Sanders-Midwest, Inc. v. United States
35 Cont. Cas. Fed. 75,548 (Court of Claims, 1988)
Hazeltine Corp. v. United States
10 Cl. Ct. 417 (Court of Claims, 1986)
United States v. John Val Browning
630 F.2d 694 (Tenth Circuit, 1980)
Faith Hospital Ass'n v. United States
634 F.2d 526 (Court of Claims, 1980)
CRF v. United States
624 F.2d 1054 (Court of Claims, 1980)
Grismac Corp. v. United States
556 F.2d 494 (Court of Claims, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
535 F.2d 8, 22 Cont. Cas. Fed. 80,287, 210 Ct. Cl. 7, 1976 U.S. Ct. Cl. LEXIS 3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/airmotive-engineering-corp-v-united-states-cc-1976.