Herman JCG Co. JV¹

CourtArmed Services Board of Contract Appeals
DecidedMay 9, 2024
Docket63235
StatusPublished

This text of Herman JCG Co. JV¹ (Herman JCG Co. JV¹) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Herman JCG Co. JV¹, (asbca 2024).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Herman JCG Co. JV 1 ) ASBCA No. 63235 ) Under Contract No. N62473-18-D-5822 )

APPEARANCES FOR THE APPELLANT: Jon G. Lycett, Esq. General Counsel Escondido, CA

Steven J. Stuart, Esq. Smith, Currie, & Hancock LLP Atlanta, GA

APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq. Navy Chief Trial Attorney Michael W.S. Hayes, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE ARNETT

This appeal arises from a design-build contract awarded by the Department of the Navy (the government or Navy) to appellant Herman JCG Co. JV (Herman) and turns on whether Herman is entitled to share in savings resulting from a proposal that was initially submitted as a change and subsequently submitted as a Value Engineering Change Proposal (VECP). Herman asserts that its proposal was always a VECP and seeks to share the contract savings consistent with a VECP (app. br. at 10-15). The Navy denies that the proposal satisfies the requirements for a VECP and contends that it conditionally accepted the change proposal prior to its disclosure as a VECP (gov’t br. at 21-24; gov’t reply at 7). The Navy denies that it constructively accepted the VECP by allowing Herman to construct the project using its phased approach (gov’t br. at 2, 26-27).

1 Although this matter was originally filed and docketed under the name of Herman Construction Group, Inc., we construe this appeal as filed under the name of Herman JCG Co. JV because the joint venture (JV) is a party to the contract at issue, and appellant’s filings consistently reflect that this matter was brought on behalf of the JV. The case caption has been corrected. The Board has jurisdiction over this appeal pursuant to the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7101-7109. The parties elected to submit this appeal on the record pursuant to Rule 11 and requested that the Board decide entitlement only.

Because we conclude that the government constructively accepted Herman’s VECP, the appeal is sustained.

FINDINGS OF FACT

Background:

1. On October 25, 2017, the Navy awarded an Indefinite Delivery Indefinite Quantity Multiple Award Construction Contract (the Contract) to Herman for new construction, renovation, and repair of general building construction at various installations in the Southwest (see generally R4, tab 1). On September 18, 2019, the Navy awarded a firm-fixed price task order against the Contract for Design-Build Repair MCCES Operation Building 1737, Marine Corps Air Ground Combat Center, Twentynine Palms, California (R4, tab 9 at 113-14). 2 Design and construction of the renovation were to be completed by July 5, 2021 (id. at 115). During construction, the 27,340 SF building was to be “non-operational and vacated,” and the work was not required to be phased (R4, tab 67 at 1823, 405). Thus, the occupants of the administrative/office space (approximately 5,785 SF) and classrooms (approximately 12,633 SF) in Building 1737 would have to relocate to swing space for more than a year while construction was completed (id., R4, tab 47 at 2402).

2. For swing space, the task order required Herman to provide “temporary modular office facilities for the duration of the renovation” and included floor plans for two groups of trailers totaling 7,200 SF (R4, tabs 67 at 556, 135 at 2282-91). The trailers were intended to serve as “admin space and storage only” because the government was “consolidating down” its classrooms (R4, tab 76 at 1950). Floor plans for the trailers indicated the required configuration and furniture for offices, cubicles, work areas, conference rooms, and restrooms (R4, tab 135 at 2283-84). Based upon the size and configuration of the temporary trailers depicted in the floor plans, the trailers do not appear to be sufficient or intended to serve as swing space for the entire building (R4, tab 135 at 2283-84).

2 Documents in the Rule 4 file are numbered using a letter prefix and leading zeros. For ease, we have dropped the prefix and leading zeros in this decision. 2 Herman’s proposal:

3. On October 21, 2019, Herman verbally proposed “eliminating the trailers and their related cost by phasing the project” (R4, tab 137 ¶ 8). On October 23, 2019, Herman submitted a plan which proposed “phasing the project rather than utilizing temporary trailers to house the administration staff” (R4, tabs 41 at 1334-35, 19 at 252-53). As proposed, Phase 1 would include renovation of the classroom side of the building allowing the administration staff to remain in place throughout Phase 1 (R4, tab 19 at 252). Upon completion of Phase 1, the administration staff would temporarily occupy the newly renovated classroom side during renovation of the administration/office space in Phase 2 (id.). The phasing plan included a color-coded drawing depicting the portions of the building associated with Phases 1 and 2 (id.). Herman’s proposal identified benefits to the government arising from phasing including allowing the administration staff to “occupy their current space for a longer period of time” (id. at 253). Contemporaneous internal government emails noted that the Navy could request a credit and stated concurrence with the plan subject to a few conditions (R4, tab 41 at 1332-34). We find that Herman’s phasing plan proposed a change to the contract.

4. On November 4, 2019, the Navy responded that it would “consider” phasing subject to three conditions: 1) provision of 1,000 SF of climate-controlled storage with shelving; 2) responses to several Requests for Information (RFIs); and 3) a credit to the government for “all of the trailers and setup that are not going to now be done for this project” (R4, tab 41 at 1331-32). Indicating that it would be a “negotiated credit,” the Navy closed by stating, “If you are going to pursue this please submit an RFI with ROM solution / proposals for all of this and we can proceed forward” (id.).

5. On November 18, 2019, Herman provided an itemized list of anticipated costs and savings and estimated a potential net savings of $151,400 for phasing in lieu of temporary trailers (R4, tab 38 at 7). Government comments from the 45% design review on November 21, 2019 state, “Temporary Trailer issue needs resolution. Reasonable deduct and no extension to contract time line” (R4, tab 47 at 2446). Notes from a December 3, 2019 design meeting indicated, “HCG proposed a $150k credit to GOV to eliminate trailers. Under consideration by GOV . . . Customer prefers the phased program. GOV Asset mgr concerned about big-picture value to GOV. Some discussion needed between GOV team members” (R4, tab 43 at 1419).

6. On December 11, 2019, Herman submitted RFI 008 requesting approval to delete the temporary trailers and proceed with its phasing plan (R4, tab 20 at 254). On the RFI, Herman marked three separate boxes indicating “High” priority, potential time/cost impact, and “Critical Path” (id.). Six weeks elapsed before the Navy responded on January 23, 2020 and acknowledged a need to “negotiate this asap:”

3 The government agrees with the position of ONLY 1000 S.F. climate controlled trailers for storage and the remainder would be a credit to the government. Phasing is acceptable for this project with credit to the government. Until that is negotiated it cannot be said a definitive yes, but IF all parties can agree upon a settlement it is the way forward preferred.

(R4, tabs 41 at 1329, 20 at 254)

7.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Herman JCG Co. JV¹, Counsel Stack Legal Research, https://law.counselstack.com/opinion/herman-jcg-co-jv1-asbca-2024.