Icsd Corporation v. The United States

934 F.2d 313, 37 Cont. Cas. Fed. 76,096, 1991 U.S. App. LEXIS 10705, 1991 WL 86240
CourtCourt of Appeals for the Federal Circuit
DecidedMay 28, 1991
Docket90-1515
StatusPublished
Cited by3 cases

This text of 934 F.2d 313 (Icsd Corporation v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Icsd Corporation v. The United States, 934 F.2d 313, 37 Cont. Cas. Fed. 76,096, 1991 U.S. App. LEXIS 10705, 1991 WL 86240 (Fed. Cir. 1991).

Opinion

BENNETT, Senior Circuit Judge.

ICSD Corporation (ICSD) appeals the decision of the Armed Services Board of Contract Appeals (Board) rejecting ICSD’s challenge to the Contracting Officer’s final decision on several issues relating to ICSD’s share of cost savings resulting from a Value Engineering Change Proposal. ICSD Corporation, ASBCA No. 28028, 90-3 BCA ¶ 23,027 (Delman, A.J.). We affirm.

BACKGROUND

ICSD contracted with the Army for the sale of night vision gun sights. The sights required special purpose military mercury batteries to operate. Under ICSD’s contract, the batteries were deemed to be a “major component” of the sights but were not manufactured or delivered to the Army under the contract.

The contract included a standard Value Engineering Incentive clause. See ASPR 7-104.44(a)(l) (1974 APR); 32 C.F.R. § 7.104-44(a)(l) (1974). Under that clause, the government invites contractors to submit cost savings ideas in the form of Value Engineering Change Proposals (VECPs). If a VECP is accepted by the government, the contractor may receive a share of the cost savings. If the savings are characterized as contract savings, the award is a 50% share. If, on the other hand, the savings are characterized as collateral savings, the award is a 20% share.

ICSD submitted a VECP suggesting the use of standard “AA” size alkaline batteries instead of the special mercury batteries. Alkaline batteries were much cheaper to acquire and use. After some reluctance on the part of the government, ICSD’s VECP was accepted.

While ICSD’s VECP was under consideration, the government was independently considering the use of lithium batteries instead of mercury batteries. Like alkaline batteries, lithium batteries provided many advantages over mercury batteries. For example, lithium batteries operated well over all military temperature ranges, eliminating the need for cold weather adapters, and they were believed to have no special storage or disposal requirements.

The switch to “AA” alkaline batteries resulted in significant savings for the government. The alkaline batteries cost less than both mercury batteries and lithium batteries. The Contracting Officer determined that the savings were over $1 million per year and awarded ICSD a share of those savings. However, the Contracting Officer determined that the savings were “collateral” to the contract and that *315 the award share was 20%, not the 50% that ICSD sought. In addition, ICSD had alleged that the government realized other collateral cost savings due to the increased safety of alkaline batteries, reduced disposal costs, reduced logistics costs, and elimination of the need for a cold weather adapter. No award was made for those savings.

While ICSD’s proposal was under consideration, another company, Numax Electronics, Inc. (Numax), submitted a similar VECP. The government evaluated both proposals and determined that ICSD’s was superior in three areas while Numax’s was superior in one. Therefore, the government split the savings share award, giving 75% of the award to ICSD and 25% to Numax.

On appeal to the Board, ICSD challenged the Contracting Officer’s characterization of the cost savings as collateral savings. The Board affirmed, holding that the value engineering incentive clause provided for a 50% award on future purchases of “the item” or of “essentially the same” item as that to be acquired by the government under the subject procurement. The Board held that the battery was an item related to the contract, rather than the subject of the contract. Therefore, the savings on the battery cost were collateral savings, and ICSD was entitled to a 20% award.

The Board also rejected ICSD’s challenge to the Contracting Officer’s determination not to make an award for the other collateral cost savings. The Board held that some of the alleged savings were not “ascertainable,” as required by the incentive clause. Other savings would have been realized using the new lithium battery planned by the government and so were not attributable to the VECP. Finally, the Board rejected ICSD’s appeal of the decision to split the award between ICSD and Numax as no abuse of discretion had been shown. *

DISCUSSION

Our review of the Board’s decisions is limited. Under 41 U.S.C. § 609(b) (1988), factual findings “shall be final and conclusive and shall not be set aside unless the decision is fraudulent, or arbitrary, or capricious, or so grossly erroneous as to necessarily imply bad faith, or if such decision is not supported by substantial evidence.” Legal conclusions are freely reviewable. Afro-Lecon, Inc. v. United States, 820 F.2d 1198, 1200-1201 (Fed.Cir.1987). The Board’s interpretation of a contract, while freely reviewable as a question of law, is afforded careful consideration and great respect. See Alvin, Ltd. v. United States Postal Service, 816 F.2d 1562, 1564 (Fed.Cir.1987).

A. “Acquisition” Savings Versus Collateral Savings

The Board correctly determined, as a matter of law, that the cost savings due to the lower acquisition cost of alkaline batteries were collateral savings under ICSD’s contract.

The Value Engineering Incentive clause of ICSD’s contract provided for a 50% savings share award for savings realized under (1) the instant contract, (2) concurrent contracts, or (3) future contracts. Instant contract savings were defined as “the unit cost reduction times the number of units affected in the instant contract.” Concurrent contract savings are those realized when “the VECP accepted under this contract is used on concurrent contracts of the purchasing office for essentially the same item." (Emphasis added.) The future contracts provision, on which ICSD bases its 50% award claim, states:

If the VECP accepted under this contract is used on future purchases of essentially the same item by the purchasing office, or its successor, the Contractor shall share in the savings....

(Emphasis added.) When read as a whole, it is clear that the incentive clause provides for a 50% cost savings share when the VECP reduces the cost of “the item” or *316 “essentially the same item” as that to be acquired under the contract. Because batteries were not acquired by the government under ICSD’s contract, battery cost savings are not subject to the 50% share award.

In contrast to the 50% contract savings award provisions, the collateral savings provision of the incentive clause awards a 20% share of collateral savings. That award applies:

[i]f an accepted VECP results in a measurable net reduction in the cognizant Military Department’s overall document-able projected costs of maintenance, operation,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Herman JCG Co. JV¹
Armed Services Board of Contract Appeals, 2024
Mass Transit Administration v. CSX Transportation, Inc.
708 A.2d 298 (Court of Appeals of Maryland, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
934 F.2d 313, 37 Cont. Cas. Fed. 76,096, 1991 U.S. App. LEXIS 10705, 1991 WL 86240, Counsel Stack Legal Research, https://law.counselstack.com/opinion/icsd-corporation-v-the-united-states-cafc-1991.