C.A. Rasmussen, Inc. v. United States

52 Fed. Cl. 345, 2002 U.S. Claims LEXIS 88, 2002 WL 596195
CourtUnited States Court of Federal Claims
DecidedApril 16, 2002
DocketNo. 00-752C
StatusPublished
Cited by1 cases

This text of 52 Fed. Cl. 345 (C.A. Rasmussen, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C.A. Rasmussen, Inc. v. United States, 52 Fed. Cl. 345, 2002 U.S. Claims LEXIS 88, 2002 WL 596195 (uscfc 2002).

Opinion

OPINION

DAMICH, Judge.

I. Introduction

This action is before the Court on the United States (hereinafter “Defendant’s”) Motion for Partial Summary Judgment pursuant to Rule 56(b) of the Court of Federal Claims (RCFC). Defendant contends that C.A. Rasmussen, Inc. (hereinafter “Plaintiff’) did not comply with the contractual requirements necessary to establish its entitlement to compensation for value engineering change proposals (VECPs) allegedly furnished to Defendant. For the reasons stated herein, the Defendant’s Motion for Partial Summary Judgment is hereby GRANTED.

II. Background

On June 11, 1997, the United States Army Corp of Engineers (hereinafter “Corps”) awarded fixed-price Contract No. DACW09-97-C-0038 (hereinafter “contract”) to Plaintiff for the construction of channel improvements at Reach 1 of the Santa Paula Creek in Ventura County, California. The contract was part of a larger effort by the Corps to provide the City of Santa Paula with flood protection along Santa Paula Creek. The work required by the contract included the demolition of existing concrete walls, excavation of a pilot channel and construction of a stone protection channel (hereinafter “rip-rap”) and concrete structures such as retaining walls and side drain structures. Section 02600 of the contract, entitled “Stone Protection,” contained two specific paragraphs of relevance concerning the source of the grouted stone used for the rip-rap:

[347]*3472.1.3.1 Source Development

Before a proposed source or sources of stone will be considered for sampling and testing, the Contractor must demonstrate that the source has sufficient stone to fulfill the contract requirements. If sufficient amounts of stone conforming to these specifications are not available from a source or sources used in the work, the Contractor shall submit stone from another source for authorization.

2.3.2 Grouted Stone Protection

The grouted stone shall be produced by processing the material within the channel limits. Grouted stone shall be stone from the streambed which is, reasonably graded within the limits specified below____

According to Section 00010, entitled “Schedule of Payment: Supplies or Services and Prices/Costs,” Plaintiff was required to produce 9,100 cubic meters (cm) of stone for the rip-rap by excavating at least 32,800 cm of stone on-site.

The contract incorporated by reference FAR 52.248-3, the VECP clause that acts as a procurement technique to encourage contractors to reduce their costs in exchange for a share of the savings. The clause provides in pertinent part:

(b) Definitions.
‘Value engineering change proposal (VECP)’ means a proposal that—
(1) Requires a change to this, the instant contract, to implement; and
(2) Results in reducing the contract price or estimated cost without impairing essential functions or characteristics; provided, that it does not involve a change—
(i) In deliverable end item quantities only; or
(ii) To the contract type only.
(c) VECP preparation.
As a minimum, the Contractor shall include in each VECP the information described in paragraphs (c)(1) through (7) of this clause. If the proposed change is affected by contractually required configuration management or similar procedures, the instructions in those procedures relating to format, identification, and priority assignment shall govern VECP preparation. The VECP shall include the following:
(1) A description of the difference between the existing contract requirement and that proposed, the comparative advantages and disadvantages of each, a justification when an item’s function or characteristics are being altered, and the effect of the change on the end item’s performance.
(2) A list and analysis of the contract requirements that must be changed if the VECP is accepted, including any suggested specification revisions.
(3) A separate, detañed cost estimate for (i) the affected portions of the existing contract requirement and (ü) the VECP. The cost reduction associated with the VECP shall take into account the Contractor’s aUowable development and implementation costs, including any amount attributable to subcontracts under paragraph (h) of this clause.
(4) A description and estimate of costs the Government may incur in implementing the VECP, such as test and evaluation and operating and support costs.
(5) A prediction of any effects the proposed change would have on coñateral costs to the agency.
(6) A statement of the time by which a contract modification accepting the VECP must be issued in order to achieve the maximum cost reduction, noting any effect on the contract completion time or delivery schedule.
(7) Identification of any previous submissions of the VECP, including the dates submitted, the agencies and contract numbers involved, and previous Government actions, if known.
(d) Submissions.
The Contractor shah submit VECP’s to the Resident Engineer at the worksite, with a copy to the Contracting Officer.

The initial estimated value of the contract was $3,019,353 and its initial completion date was December 22, 1997. The project was actually completed on October 15, 1998. Plaintiff filed its complaint on December 12, [348]*3482000. At issue in Defendant’s Motion for Partial Summary Judgment is Plaintiffs request for compensation in the amount of $1,632,184, for alleged value engineering services rendered to the Corps.1 Specifically, Plaintiff alleges that its importation of stone compatible to that on-site from the San Gabriel River near Fish Canyon, adjacent to the City of Duarte, was a change to the contract by which Plaintiff caused a cost savings to Defendant deserving compensation.

III. Discussion

A. Law

Summary judgment is appropriate when there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. RCFC 56(c); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986); Jay v. Secretary, DHHS, 998 F.2d 979 (Fed.Cir.1993). The party moving for summary judgment bears the initial burden of demonstrating the absence of any genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 325, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). The court must resolve any doubts about factual issues in favor of the non-moving party, Chiuminatta Concrete Concepts, Inc. v. Cardinal Indus., Inc., 145 F.3d 1303, 1307 (Fed.Cir.1998), and draw all reasonable inferences in its favor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Herman JCG Co. JV¹
Armed Services Board of Contract Appeals, 2024

Cite This Page — Counsel Stack

Bluebook (online)
52 Fed. Cl. 345, 2002 U.S. Claims LEXIS 88, 2002 WL 596195, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ca-rasmussen-inc-v-united-states-uscfc-2002.