John J. Kirlin, Inc. v. United States

33 Cont. Cas. Fed. 74,823, 11 Cl. Ct. 199, 1986 U.S. Claims LEXIS 762
CourtUnited States Court of Claims
DecidedNovember 25, 1986
DocketNo. 624-84C
StatusPublished
Cited by1 cases

This text of 33 Cont. Cas. Fed. 74,823 (John J. Kirlin, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John J. Kirlin, Inc. v. United States, 33 Cont. Cas. Fed. 74,823, 11 Cl. Ct. 199, 1986 U.S. Claims LEXIS 762 (cc 1986).

Opinion

OPINION

MAYER, Judge.

In this direct access suit under the Contract Disputes Act of 1978, plaintiff John J. Kirlin, Inc., challenges the contracting officer’s denial of compensation under the Value Engineering Incentive Clause of its contract for work on the Pentagon. Defendant denies entitlement and the case is before the court on cross-motions for summary judgment.

Background

In 1977, an architect and engineering firm under contract with defendant made recommendations for renovation of the Pentagon. One of the objectives of this contract was to design the renovation of heating and cooling coils contained in the Pentagon’s large air handling units. In a tentative submission, the firm suggested “[t]he complete removal of the existing automatic temperature control system relating to control of the 56 major air handling units, and replacement with a new control system including dampers and control air supply system.” The firm also proposed the complete removal of the temperature control system and replacement with a new system, to design-in freeze protection for new coils, and to provide an energy conservation report for the Pentagon.

Approximately a year later, in August of ■ 1978, defendant awarded plaintiff a contract for the renovation and improvement of the heating, ventilation, and air conditioning system in the Pentagon. The amount of the contract was $2,374,000, as against defendant’s estimated contract price of $3,460,000.

The contract required that plaintiff remove existing outside air damper controls, replace them with new damper motors, and install new air handling unit coils. As designed by the architect, the contract work did not require replacement of the outside air dampers, but it did call for replacement of other dampers in renovating the air handling units and the automatic temperature control system. It consisted of removing and replacing all of the heating coil and cooling coil banks and their associated parts, including automatic temperature controls. The contract also called for plaintiff to modify some of the so-called minimum outside air dampers by blanking them off, but did not require replacement of any of the outside air dampers. Fifty-six face and bypass dampers which were part of the cooling coil banks were replaced by plaintiff.

The contract contained a standard Value Engineering Incentive Clause. On September 21, 1978, plaintiff submitted a value engineering change proposal to the contracting officer pursuant to the clause to replace what are known as maximum outside air dampers on the seventy-six air handling units in the building, with new, low leakage, tight shutoff dampers, “per the standard GSA specification.” The proposal recognized the deterioration of the existing outside air dampers and said that the installation of new ones, would result in annual energy savings to the government of $1,617,280. The proposal also predicted [201]*201significant maintenance savings. Plaintiff estimated the cost of adding the dampers at $203,946.

The value engineering change proposal was sent to the architect and engineering firm by defendant for evaluation. It disagreed with plaintiffs estimate of energy savings, but suggested that the proposal was reasonable and might be advantageous to the government “on the basis of ‘preventative maintenance.’ ” Plaintiff disagreed with the consultant’s recommendation. But by letter of December 12, 1978, the contracting officer’s representative rejected the value engineering change proposal because plaintiff's estimate of annual energy cost savings was not valid. Nothing was said about the maintenance aspect of the proposal.

By letter of December 20, 1978, plaintiff responded that it “will not be responsible for an operational ATC system unless all the D.A.D. dampers [apparently referring to outside air, return air, and fan inlet dampers] are replaced with new dampers.” Defendant replied on December 29, 1978, that it was aware of the deterioration of the dampers and the need for repair or replacement. But it believed that “failure of the dampers to close properly should not affect performance of the renovated systems.” Plaintiff protested again on January 19, 1979, writing,

These dampers as you are aware, are in need of repair and/or replacement. Not replacing or repairing these dampers compromises the operation of the automatic control system and the air balancing. In effect, we will not be responsible for a totally operational and balanced system if these dampers are not corrected.

On February 16, 1979, defendant responded,

As previously stated in our December 29, 1978 letter, we are aware that these dampers, in some cases, require repair or replacement because they will not close properly. However, their condition does not prevent installation of the specified new automatic temperature control systems. It is not possible for a change order to be issued under this contract to install new direct air dampers. Any repairs or replacement of the existing dampers must be accomplished by Government forces or a separate contract.

Plaintiff completed the contract and executed a release of defendant “from any and all claims arising under or by virtue of said contract or any modification or change thereof except [for a $500 final payment].”

Approximately three months later, defendant issued a project authorization for the replacement of outside air dampers at the Pentagon. The project became part of a contract which was awarded to a contractor other than plaintiff. Whereupon, plaintiff submitted a claim under the Contract Disputes Act of 1978, 41 U.S.C. §§ 601 et seq., alleging that defendant had “constructively accepted” its value engineering change proposal by awarding the subsequent contract. The claim was denied and plaintiff brought suit here. In defense, defendant says plaintiff’s proposal to replace outside air dampers at the Pentagon did not qualify as a value engineering change proposal. It was not a variation of existing requirements of the contract, but would have initiated an entirely new area of work. And the cost reduction proposals were not “initiated and developed” by plaintiff. Defendant also says the claim is barred by the release.

Discussion

In pertinent part, the standard Value Engineering Incentive Clause found in this contract says,

1. INTENT AND OBJECTIVES—This clause applies to any cost reduction proposal (hereinafter referred to as Value Engineering Change Proposal or VECP) initiated and developed by the Contractor for the purpose of changing any requirement of this contract____
1.1 VECP’s contemplated are those that would result in net savings to the Government by providing either: (1) a decrease in the cost of performance of this contract, or; (2) a reduction in the cost of ownership (hereinafter referred [202]*202to as collateral costs) of the work provided by this contract, regardless of acquisition costs. VECP’s must result in savings without impairing any required functions and characteristics such as service life, reliability, economy of operation, ease of maintenance, standardized features, esthetics, fire protection features and safety features presently required by this contract____

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John J. Kirlin, Inc. v. The United States
827 F.2d 1538 (Federal Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
33 Cont. Cas. Fed. 74,823, 11 Cl. Ct. 199, 1986 U.S. Claims LEXIS 762, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-j-kirlin-inc-v-united-states-cc-1986.