Douglass v. LICCIARDI CONST. CO., INC.

562 A.2d 913, 386 Pa. Super. 292, 1989 Pa. Super. LEXIS 2553
CourtSupreme Court of Pennsylvania
DecidedAugust 14, 1989
Docket1652
StatusPublished
Cited by23 cases

This text of 562 A.2d 913 (Douglass v. LICCIARDI CONST. CO., INC.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Douglass v. LICCIARDI CONST. CO., INC., 562 A.2d 913, 386 Pa. Super. 292, 1989 Pa. Super. LEXIS 2553 (Pa. 1989).

Opinion

WIEAND, Judge:

In this action on a building contract, the jury found that the contract had been breached by the builder, Licciardi Construction Company (Licciardi), and awarded damages to the owners, Donald Douglass and Regina Douglass, in the amount of fifteen thousand ($15,000) dollars. After post-trial motions had been denied and judgment entered on the verdict, Licciardi appealed.

The case was submitted to the jury on special interrogatories. In response thereto, the jury found that appellant had failed to construct a residential dwelling for appellees in accordance with the parties’ contract and had performed some of the construction in a defective and unworkmanlike manner. The jury found further that the cost of correcting the defects and completing construction as agreed was fifteen thousand ($15,000) dollars. In answer to another interrogatory, the jury found that the dwelling house would *295 have had an increased market value of fifteen thousand ($15,000) dollars if it had been constructed according to the terms of the contract. Appellant contends that the jury’s award of damages was unsupported by the evidence and contrary to law.

The general measure of damages in breach of contract cases is set forth in Restatement (Second) of Contracts § 347 as follows:

Subject to the limitations stated in §§ 350-53, the injured party has a right to damages based on his expectation interest as measured by
(a) the loss in the value to him of the other party’s performance caused by its failure or deficiency, plus
(b) any other loss, including incidental or consequential loss, caused by the breach, less
(c) any cost or other loss that he has avoided by not having to perform.

“If defective or partial performance is rendered, the loss in value caused by the breach is equal to the difference between the value that the performance would have had if there had been no breach and the value of such performance as was actually rendered. In principle, this requires a determination of the values of those performances to the injured party himself and not their values to some hypothetical reasonable person or on some market.” Restatement (Second) of Contracts § 347, comment b (emphasis added).

Because it is sometimes difficult in building contract cases to prove with certainty the loss in value to the injured party, he or she may elect to calculate loss in value in accordance with Section 348(2) of the Restatement (Second) of Contracts. This section provides as follows:

(2) If a breach results in defective or unfinished construction and the loss in value to the injured party is not proved with sufficient certainty, he may recover damages based on
*296 (a) the diminution in the market price of the property caused by the breach, or
(b) the reasonable cost of completing performance or of remedying the defects if that cost is not clearly disproportionate to the probable loss in value to him.

This has been explained further in comment c as follows:

c. Incomplete or defective performance. If the contract is one for construction, including repair or similar performance affecting the condition of property, and the work is not finished, the injured party will usually find it easier to prove what it would cost to have the work completed by another contractor than to prove the difference between the values to him of the finished and the unfinished performance____
Sometimes, especially if the performance is defective as distinguished from incomplete, it may not be possible to prove the loss in value to the injured party with reasonable certainty. In that case he can usually recover damages based on the cost to remedy the defects____
Sometimes, however, such a large part of the cost to remedy the defects consists of the cost to undo what has been improperly done that the cost to remedy the defects will be clearly disproportionate to the probable loss in value to the injured party. Damages based on the cost to remedy the defects would then give the injured party a recovery greatly in excess of the loss in value to him and result in a substantial windfall. Such an award will not be made. It is sometimes said that the award would involve “economic waste,” but this is a misleading expression since an injured party will not, even if awarded an excessive amount of damages, usually pay to have the defects remedied if to do so will cost him more than the resulting increase in value to him. If an award based on the cost to remedy the defects would clearly be excessive and the injured party does not prove the actual loss in value to him, damages will be based instead on the difference between the market price that the property would have had without the defects and the market price *297 of the property with the defects. This diminution in market price is the least possible loss in value to the injured party, since he could always sell the property on the market even if it had no special value to him.

Pennsylvania courts, consistently therewith, have generally allowed damages for incomplete or defective performance of a building contract to be measured by the cost of completing the work or correcting the defects by another contractor. See, e.g.: Ecksel v. Orleans Construction Co., 360 Pa.Super. 119, 519 A.2d 1021 (1987); Steinhauer v. Wilson, 336 Pa.Super. 155, 485 A.2d 477 (1984); Brourman v. Bova, 198 Pa.Super. 279, 182 A.2d 245 (1962). It is only where the cost of completing performance or of remedying the defects is clearly disproportionate to the probable loss in value to the injured party that damages will be measured by the difference between the market price that the property would have had without the defects and the market price of the property with the defects. Although articulating the rule in a slightly different manner, the Court acknowledged and followed the same principle in Gadbois v. Leb-Co. Builders, Inc., 312 Pa.Super. 144, 458 A.2d 555 (1983). Where the cost of remedying the defects in construction is not clearly disproportionate to the probable loss in value to the injured party, the breaching contractor cannot require that the injured party’s damages be measured by the difference between the market price of the property without the defects and the price of the property with the defects.

The plaintiff-appellees in this case sought to recover damages measured by the cost of correcting the defects in the construction work performed by the defendant-appellant. They introduced evidence that the cost of correcting the defects would be $20,574.11. Appellant offered no evidence regarding the cost of making such repairs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Posada Investments v. Eliakim Enterprises
Superior Court of Pennsylvania, 2026
Ericsson Properties v. Bulle Construction
Superior Court of Pennsylvania, 2025
Delaware Co. Solid Waste Auth. v. Evergreen Comm.
Superior Court of Pennsylvania, 2022
Terra Firma Builders, LLC v. King, W.
Superior Court of Pennsylvania, 2020
Cohen, M. v. JS Associated Service
Superior Court of Pennsylvania, 2017
C. Worley and L. Worley, h/w v. County of Delaware and M. Gura
178 A.3d 213 (Commonwealth Court of Pennsylvania, 2017)
Beaumont Condominium Assoc. v. Brown, J.
Superior Court of Pennsylvania, 2017
Manahan v. Rhoades
10 Pa. D. & C.5th 171 (Centre County Court of Common Pleas, 2010)
Brady v. Ballay, Thornton, Maloney Medical Associates Inc.
37 Pa. D. & C.4th 501 (Montgomery County Court of Common Pleas, 1997)
Tiburzio-Kelly v. Montgomery
681 A.2d 757 (Superior Court of Pennsylvania, 1996)
Spino v. John S. Tilley Ladder Co.
671 A.2d 726 (Superior Court of Pennsylvania, 1996)
Oelschlegel v. Mutual Real Estate Investment Trust
633 A.2d 181 (Superior Court of Pennsylvania, 1993)
Commonwealth v. Bowser
624 A.2d 125 (Superior Court of Pennsylvania, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
562 A.2d 913, 386 Pa. Super. 292, 1989 Pa. Super. LEXIS 2553, Counsel Stack Legal Research, https://law.counselstack.com/opinion/douglass-v-licciardi-const-co-inc-pa-1989.