Cornell & Co. v. Seaway Painting, Inc. (In Re Cornell & Co.)

229 B.R. 97, 1999 Bankr. LEXIS 47, 1999 WL 27262
CourtUnited States Bankruptcy Court, E.D. Pennsylvania
DecidedJanuary 21, 1999
Docket19-11343
StatusPublished

This text of 229 B.R. 97 (Cornell & Co. v. Seaway Painting, Inc. (In Re Cornell & Co.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cornell & Co. v. Seaway Painting, Inc. (In Re Cornell & Co.), 229 B.R. 97, 1999 Bankr. LEXIS 47, 1999 WL 27262 (Pa. 1999).

Opinion

OPINION

DAVID A. SCHOLL, Chief Judge.

A. INTRODUCTION

Presently before us is the disposition of hopefully the last adversary proceeding (“the Proceeding”) arising out of the complex bankruptcy case of a contractor, CORNELL & COMPANY, INC. (“the Debtor”). In the Proceeding the Debtor seeks to eliminate a proof of claim filed by DELBERT L. SMITH COMPANY (“the Defendant”), the assignee of the painting subcontractor on a large project on which the Debtor was the general contractor, and to further recover damages for costs and delay of completion of the project from the Defendant.

We hold, consistent with the Debtor’s position, that the Defendant materially breached its contractual duties under the subcontract agreement, justifying the striking of the Defendant’s proof of claim in its entirety. However, consistent with the Defendant’s position, we further hold that contractually-approved pay-request forms for work actually performed resulted in final acceptance of the work in question; that no back-charges against the Defendant are justified; and that the Defendant has not been proven liable for delay of the entire project. Concluding that the Defendant performed about 86.4 percent of the contracted work rather than 70 percent, as the Debtor claims, or 96 percent as the Defendant claims, we measure the Debt- or’s damages for completing the unfinished contracted work at but $1,160.00.

B. PROCEDURAL AND FACTUAL HISTORY

The Debtor is a construction company which was awarded, between February 12, 1991, and June 30, 1993, after competitive bidding, four contracts as the general contractor in performance of rehabilitation work on a main public transportation artery in the City of Philadelphia (“the City”), the Market-Frankford Elevated Railroad (“the El”), by the SOUTHEASTERN PENNSYLVANIA TRANSPORTATION AUTHORITY (“SEPTA”). These contacts were designated as SCB-1, CB-2, CL-2D, CL-3S. A joint venture formed by the Debtor and another contractor, Buckley & Company, was awarded a fifth contract, designated as CL — ID.

On March 1, 1994, the Debtor entered into a subcontract agreement with SEAWAY PAINTING, INC. (“Seaway”) for the structural steel painting work on, inter alia, the CL-2D project. During the performance of Seaway’s subcontract work on other El projects Seaway advised the Debtor of its desire to assign, to the Defendant, the CL-2D project, for which the contracted price was $975,000, to which the Debtor consented.

On September 1, 1994, the Defendant began working on the CL-2D project and *100 worked continuously until just before Thanksgiving 1994, when SEPTA imposed an annual moratorium through Christmas to allow shoppers to fully utilize the El over the holidays. However, after the moratorium ended, weather restrictions inimical to the use of paint and primer prevented the Defendant from remobilizing to return to the project until March 14,1995.

Shortly thereafter, the project experienced problems and delays associated with design errors, changes in federal lead-abatement standards, extra work, and changes in SEPTA’S acceptance criteria for certain items of work. Because of the unforeseen added expenses due in large part to the lead-abatement standard charges, the Debtor began to experience the financial difficulties which led to its bankruptcy filing. As a result, it failed to make timely payments to the Defendant. Nevertheless, the Defendant continued to work on the project until advised by the Debtor to demobilize for that year’s moratorium in late November 1995.

By March 1996, the Debtor became current on' its payments to the Defendant, paying all sums due except for allowed re-tainage. On August 12, 1996, the Debtor installed the last precast deck sections and track work on the CL-2D project. Shortly after that, the Debtor asked the Defendant to remobilize to finish all of the remaining contracted work. The Defendant returned to the project in October 1996, but at that proceeded only to complete the punch lists produced by SEPTA. On October 3, 1996, the Defendant demanded a reduction in its outstanding retainage, as had allegedly been verbally agreed upon by the Debtor, as a condition of continuing its work. The Debtor refused, contending that the Defendant had not completed enough work on the project to warrant the requested reduction.

On November 13, 1996, having what it contended was only two days of work left to finish, but which it allegedly could not finish because certain tasks which had to precede the remaining work were undone, the Defendant permanently departed from the project. The Defendant refused thereafter to return in 1997, and the Debtor was compelled to hire Seaway to complete the work. Seaway ultimately completed the work, but billed the Debtor an additional $307,000 for its labors.

On December 2, 1996, the Debtor filed the voluntary petition for reorganization underlying the Proceeding pursuant to Chapter 11 of the Bankruptcy Code. Shortly thereafter, on February 4, 1997, Seaway filed a general unsecured claim in the amount of $342,053 for unpaid contractual balances on certain of the projects. About a year later, Seaway filed an amended general unsecured claim which included all of its work done on all of the projects in the amount of $571,026.08.

On April 15, 1998, the Debtor obtained confirmation of a plan of reorganization which compensated general unsecured creditors under one of two options: (1) an immediate payment of 25 percent of the claim; or (2) payment in full with interest over approximately ten years in installments. On or about May 14, 1998, the Defendant filed a general unsecured claim in the amount of $80,374.83 for unreleased retainage monies in the CL-2D project. In response to these claims, in the process of filing what appears to be the last of its objections to disputed claims, the Debtor, on July 2, 1998, filed objections to the claims of both Seaway and the Defendant and counterclaims thereto against the Defendant all together in the Proceeding.

Upon requests by Seaway to continue the trial and to stay it pending resolution of a proceeding in the District Court involving the same three parties and the Debtor’s bonding company, this court, in an order of August 12, 1998, rescheduled the trial of the Proceeding on a must-be-heard basis for November 18, 1998. Two days before the trial, in an Order/Memorandum reported as Seaway Painting, Inc. v. Cornell & Company, Inc., 1998 WL 800343 (E.D.Pa. Nov. 16, 1998), the District Court, per the Honorable Louis C. Bechtle, denied Seaway’s motion to withdraw the reference of the Proceeding to the District Court.

At the outset of the trial, the Debtor and Seaway reported a settlement between them which, while not yet formally approved, we assume remains valid in rendering our within *101 decision. Apparently treating Seaway as having selected the first plan payment option, the Debtor agreed to pay Seaway $80,-525.85 on account of Seaway’s unsecured claim of approximately $307,000 on the CL-2D project. Further, the Debtor agreed that any recovery of the remaining balance of the approximately $307,000, i.e., the next $226,-474.15, from the Defendant, would be paid to Seaway.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mellon Bank, N.A. v. Aetna Business Credit, Inc.
619 F.2d 1001 (Third Circuit, 1980)
Steinhauer v. Wilson
485 A.2d 477 (Supreme Court of Pennsylvania, 1984)
Polito v. Polito
655 A.2d 587 (Superior Court of Pennsylvania, 1995)
Ecksel v. Orleans Construction Co.
519 A.2d 1021 (Supreme Court of Pennsylvania, 1987)
Dept. of Transp. v. Manor Mines, Inc.
565 A.2d 428 (Supreme Court of Pennsylvania, 1989)
Ott v. Buehler Lumber Co.
541 A.2d 1143 (Supreme Court of Pennsylvania, 1988)
Trosky v. Civil Service Commission
652 A.2d 813 (Supreme Court of Pennsylvania, 1995)
Z & L LUMBER OF ATLASBURG v. Nordquist
502 A.2d 697 (Supreme Court of Pennsylvania, 1985)
Gene & Harvey Builders, Inc. v. Pennsylvania Manufacturers' Ass'n
517 A.2d 910 (Supreme Court of Pennsylvania, 1986)
In Re Northup-Johnson, Inc.
15 B.R. 767 (D. Maryland, 1981)
Douglass v. LICCIARDI CONST. CO., INC.
562 A.2d 913 (Supreme Court of Pennsylvania, 1989)
Oelschlegel v. Mutual Real Estate Investment Trust
633 A.2d 181 (Superior Court of Pennsylvania, 1993)
Marcinak v. Southeastern Greene School District
544 A.2d 1025 (Superior Court of Pennsylvania, 1988)
Maxwell v. Schaefer
112 A.2d 69 (Supreme Court of Pennsylvania, 1955)
Brourman v. Bova
182 A.2d 245 (Superior Court of Pennsylvania, 1962)
Harman Et Ux. v. Chambers
57 A.2d 842 (Supreme Court of Pennsylvania, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
229 B.R. 97, 1999 Bankr. LEXIS 47, 1999 WL 27262, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cornell-co-v-seaway-painting-inc-in-re-cornell-co-paeb-1999.