Cohen, M. v. JS Associated Service

CourtSuperior Court of Pennsylvania
DecidedDecember 15, 2017
Docket390 WDA 2017
StatusUnpublished

This text of Cohen, M. v. JS Associated Service (Cohen, M. v. JS Associated Service) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cohen, M. v. JS Associated Service, (Pa. Ct. App. 2017).

Opinion

J-A24025-17

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

MYRNA COHEN IN THE SUPERIOR COURT OF PENNSYLVANIA Appellant

v.

JS ASSOCIATED SERVICE, T/D/B/A SERVICEMASTER OF GREATER PITTSBURGH

Appellee No. 390 WDA 2017

Appeal from the Judgment Entered April 17, 2017 In the Court of Common Pleas of Westmoreland County Civil Division at No(s): 4775 of 2009

BEFORE: MOULTON, J., SOLANO, J., and MUSMANNO, J.

MEMORANDUM BY SOLANO, J.: FILED DECEMBER 15, 2017

Appellant Myrna Cohen appeals from the judgment following a bench

trial in her action for breach of contract against Appellee JS Associated

Service, trading and doing business as ServiceMaster of Greater Pittsburgh

(“ServiceMaster”). Cohen prevailed in the action, but was awarded only

$154.1 Her appeal contends that she was entitled to recover additional

damages. We affirm.

In late February 2007, Cohen discovered a water leak in the first-floor

bathroom of her home. N.T. Trial, 9/14/16, at 31, R.R. at 148a. 2 A

____________________________________________ 1 The judgment also denied ServiceMaster’s claim for fees associated with Cohen’s alleged delay of trial, but ServiceMaster has not appealed that aspect of the decision. 2 The certified record transmitted to this Court did not include the complete trial transcript, but additional portions of the transcript were included in the (Footnote Continued Next Page) J-A24025-17

repairman, Scott Steel, discovered that the leak resulted from a failed trap

in the sink and repaired the trap. Steel N.T., 9/14/16, at 4–6, R.R. at 269a–

71a. Steel pointed out that some mold had resulted from the leak, and

Cohen therefore notified her homeowner’s insurer, Travelers Insurance

Company, and made a claim. N.T. at 31–32, R.R. at 148a. On April 3,

2007, ServiceMaster, which had been recommended by Travelers, presented

Cohen with two estimates for the mold remediation work and for “pulling up

the floor and baseboards,” “putting the plywood back in the bathroom,” and

“moving around the appliances and content.” Pl.’s Ex. 3. In a cover e-mail,

ServiceMaster’s project manager, Johnny Samek, stated: “We will not be

doing the repairs beyond the remediation because it is a far distance from

our office. We will leave the site when the remediation is done ready for

you[r] contractor to start the rebuild.” Id.

After obtaining Travelers’ approval, Cohen hired ServiceMaster for the

job. N.T. Trial at 32, R.R. at 148a. Both parties agree that ServiceMaster’s

revised combined estimate — Pl.’s Ex. 2a (hereinafter, “the Agreement”) —

became the governing contract in this case. See Cohen’s Brief, 6/29/17, at

_______________________ (Footnote Continued) reproduced record. Because no party has challenged the accuracy of the transcript in the reproduced record, we rely on it here. See Pa.R.A.P. 1921 (noting, “where the accuracy of a pertinent document is undisputed, the Court could consider that document if it was in the Reproduced Record, even though it was not in the record that had been transmitted to the Court” (citing Commonwealth v. Brown, 52 A.3d 1139, 1145 n.4 (Pa. 2012)).

-2- J-A24025-17

19; ServiceMaster’s Brief, 7/31/17, at 13.3 The Agreement stated:

This estimate does not include any repairs at this time with the exception of installing new subfloor in the bathroom so that there will not be a hole there. The repairs are going to be done by someone other than ServiceMaster and the repair estimate should be done after the remediation due to the possibility of more or less building materials needing to be removed.

Agreement at 1 (unpaginated). The Agreement explained that a different

contractor was to install permanent flooring, in contrast to subflooring,

sometime after ServiceMaster finished its work —

The [future] contractor can put other layers in and final floor covering later. The goal is not to bring the floor completely level[;] it is to cover the plank flooring and cracks which would be letting air in from the basement and possibly cause air testing to fail and make the floor safe to walk on.

Agreement at 3.

Cohen left her house during the remediation work because she was

told it would be unsafe for her to be there while ServiceMaster removed

mold. N.T. Trial at 32–34, R.R. at 148a–49a. ServiceMaster used glue and

screws to install the subflooring. N.T. Trial at 7, 55, R.R. at 142a, 154a.

When Cohen returned, she was unhappy with what she found:

Q. When you returned to the house following the work, what did you discover?

A. Look at the alcoved area, not by the powder room, across. That floor, the waferboard floor that was left, that ServiceMaster ____________________________________________ 3 The agreement was attached as an exhibit to Cohen’s original and amended complaint, and it is reproduced multiple times in the reproduced record. See, e.g., Pl.’s Ex. 2a, R.R. at 159a-66a, R.R. at 167a-74a. The record contains two similar documents marked as Exhibits 2 and 2a. The parties do not dispute that the governing contract is Exhibit 2a.

-3- J-A24025-17

installed, wasn't even. It was off by a decent distance that somebody could trip over it; I could trip over it, ‘cause I did. Then, there -- where the wood left off, different parts of the room, there was spaces. So you could see what I call, I don’t know, ceiling, floor, what I call the original floor, you could see spaces between the waferboard floor and the wall, and you could see the -- what I call the original floor. There were also areas that you could see from. If you look down, you’re looking from the kitchen area to the ceiling, there was nothing. So -- oh, and where the powder room is, there was a piece of wood extending the -- this (indicating) part, the corner, the outside corner of the powder room, there was a piece of wood extending, and then between the kitchen and what would be a small hall there was a space. That was it, pretty much it.

Q. What was your reaction to what you saw?

A. I thought that there was something that was really off.

N.T. Trial at 35–36, R.R. at 149a.

Cohen called Steel for assistance, but he told her to “call the people

who did this job because this isn’t my work.” N.T. Trial at 37, R.R at 150a.

Cohen claims that she then made several efforts to obtain relief from

ServiceMaster, but was unsuccessful. N.T. Trial at 38–45, R.R. at 150a–52a.

Cohen therefore obtained estimates from other contractors for the cost to

complete the remaining repair work in her home. The estimates included

work to repair other damages resulting from the water leak. Trial Ct. Op.,

2/3/17, at 3, 4. Among those providing estimates was Steel, who estimated

a cost of $6,038. He submitted that estimate with an intention that Cohen

would send it to Travelers for possible reimbursement. Steel N.T. at 23,

R.R. at 288a; Pl.’s Ex. 10.

-4- J-A24025-17

On August 7, 2009, Cohen sued ServiceMaster for breach of contract,

contending that it had performed “improper and unworkmanlike installation

of the subflooring.” Compl., 8/7/09, at ¶ 22. Cohen alleged that

ServiceMaster had told her that “the subflooring was only temporary,” but

that other contractors informed her that “the subflooring installed by

ServiceMaster would have to be removed and replaced with new

subflooring,” due to its permanent installation. Id. at ¶¶ 19-20.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glomb v. Glomb
530 A.2d 1362 (Supreme Court of Pennsylvania, 1987)
Smith v. Penbridge Associates, Inc.
655 A.2d 1015 (Superior Court of Pennsylvania, 1995)
Christian v. Yanoviak
945 A.2d 220 (Superior Court of Pennsylvania, 2008)
Hart v. Arnold
897 A.2d 458 (Supreme Court of Pennsylvania, 2006)
Frank B. Bozzo, Inc. v. Electric Weld Division
423 A.2d 702 (Superior Court of Pennsylvania, 1980)
Douglass v. LICCIARDI CONST. CO., INC.
562 A.2d 913 (Supreme Court of Pennsylvania, 1989)
Davis v. Mullen
773 A.2d 764 (Supreme Court of Pennsylvania, 2001)
Viener v. Jacobs
834 A.2d 546 (Superior Court of Pennsylvania, 2003)
Bolus v. United Penn Bank
525 A.2d 1215 (Supreme Court of Pennsylvania, 1987)
Gadbois v. Leb-Co. Builders, Inc.
458 A.2d 555 (Superior Court of Pennsylvania, 1983)
TruServ Corp. v. Morgan's Tool & Supply Co.
39 A.3d 253 (Supreme Court of Pennsylvania, 2012)
Epstein v. Saul Ewing LLP
7 A.3d 303 (Superior Court of Pennsylvania, 2010)
Nicholas, J. v. Hofmann, D.
158 A.3d 675 (Superior Court of Pennsylvania, 2017)
Wujcik v. Yorktowne Dental Associates, Inc.
701 A.2d 581 (Superior Court of Pennsylvania, 1997)
Hart v. Arnold
884 A.2d 316 (Superior Court of Pennsylvania, 2005)
Commonwealth v. Brown
52 A.3d 1139 (Supreme Court of Pennsylvania, 2012)
Cresci Construction Services, Inc. v. Martin
64 A.3d 254 (Superior Court of Pennsylvania, 2013)
McEwing v. Lititz Mutual Insurance
77 A.3d 639 (Superior Court of Pennsylvania, 2013)
Newell v. Montana West, Inc.
154 A.3d 819 (Superior Court of Pennsylvania, 2017)
Burly Construction Corp. v. Commonwealth
284 A.2d 841 (Commonwealth Court of Pennsylvania, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
Cohen, M. v. JS Associated Service, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cohen-m-v-js-associated-service-pasuperct-2017.