Ericsson Properties v. Bulle Construction

CourtSuperior Court of Pennsylvania
DecidedJanuary 10, 2025
Docket1516 EDA 2021
StatusUnpublished

This text of Ericsson Properties v. Bulle Construction (Ericsson Properties v. Bulle Construction) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ericsson Properties v. Bulle Construction, (Pa. Ct. App. 2025).

Opinion

J-A14031-23

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

ERICSSON PROPERTIES, LLC : IN THE SUPERIOR COURT OF : PENNSYLVANIA : v. : : : BULLE CONSTRUCTION, LLC : : Appellant : No. 1516 EDA 2021

Appeal from the Judgment Entered August 31, 2021 In the Court of Common Pleas of Philadelphia County Civil Division at No(s): 0809 Oct. Term 2017

BEFORE: PANELLA, P.J., DUBOW, J., and SULLIVAN, J.

MEMORANDUM BY SULLIVAN, J.: FILED JANUARY 10, 2025

Bulle Construction, LLC (“Bulle”) appeals from the judgment entered

against it and in favor of Ericsson Properties, LLC (“Ericsson”) following a non-

jury trial. We affirm in part, vacate in part, and remand for the trial court to

recalculate damages consistent with this decision.

This appeal arises out of a poorly drafted construction contract to

renovate a building in Philadelphia (“the property”) and the delays and

disputes that led to Ericsson, the owner of the property, to declare a breach

and terminate Bulle, the general contractor. Ericsson and Bulle each asserted

the other breached the contract and their duties of good faith and fair dealing.

Ericsson sought to recover the costs to renovate the property after terminating

Bulle (“Ericsson’s costs”). Bulle sought to recover the outstanding balance

Ericsson owed under the contract, the costs of the extra, or “add-on,” work

Bulle performed, as well as interest, attorney’s fees, and other penalties under J-A14031-23

the Contractor and Subcontractor Payment Act (“CASPA”). 1 A more detailed

summary of the factual and procedural history of this matter follows.

In October 2017, Ericsson hired Bulle to renovate the property to include

a first-floor commercial space, two upstairs apartments, a brick front exterior,

and a stucco rear exterior. See N.T., 5/19/21, at 156-75; N.T., 5/18/21, at

97. Ericsson submitted plans from its architect, YCH Architect LLC (“YCH”),

and Bulle drafted the renovation contract, which the parties executed. See

Final Estimate, signed 10/26/17, unnumbered at 1-9 (hereinafter “the

renovation contract”) (admitted as Exhibit P-9 at trial); N.T., 5/19/21, at 156-

75.

The renovation contract set forth a twenty-one-to-twenty-four-week

schedule to complete the project. See Renovation Contract at 8 (outlining the

work schedule). However, the renovation contract stated that Bulle was not

responsible for delays in inspections by the Philadelphia Department of

____________________________________________

1 See 73 P.S. §§ 501-517. The purpose of CASPA is to protect contractors and subcontractors and encourage fair dealing among parties to a construction contract. See El-Gharbaoui v. Ajayi, 260 A.3d 944, 954 (Pa. Super. 2021). “Performance by either a contractor or subcontractor pursuant to a contract entitles [it] to payment from the party with whom [it] contracted.” Scungio Borst & Associates v. 410 Shurs Lane Developers, LLC, 106 A.3d 103, 109 (Pa. Super. 2014) (internal citation omitted). CASPA “provides rules and deadlines to ensure prompt payments under construction contracts, to discourage unreasonable withholding of payments, and to address the matter of progress payments and retainages.” Id. (internal citations and quotations omitted).

-2- J-A14031-23

Licenses and Inspections (“L&I”). See id. at 5 (stating, verbatim: “On

Schedule Time Tables . . . In Accordance With [L&I]. Will not be held

Accountable for lapses in the city inspectors time tables. if inspector is

delayed”).

The renovation contract had a total contract price of $226,000 to be

paid by Ericsson over four draws: $75,333, payable in October 2017, to cover

fencing, demolition, masonry, roofing, framing, and electrical; $75,333,

payable in December 2017, to cover plumbing, HVAC, sprinkler, and fire

suppression systems; $48,967, payable in January 2018, to cover drywall,

painting, kitchen, tile and flooring, and appliances; and a final payment of

$26,367 due upon completion. See id. at 1-9. The renovation contract

provided allowances to complete specific items; as to add-on work, the

renovation contracts stated that Bulle would discuss with Ericsson “add-ons

. . . for resolution” and charge “[a]ny action taken on discussed items to the

completion balance.” Id. at 1-5, 9. Ericsson was responsible for the costs of

permits. See id. at 1 (stating, verbatim: “Permits . . . (owner will pay for the

cost of Building Permit . . .)”). The renovation contract did not specify when

Ericsson had to pay for permits, address delays in L&I’s permitting process

caused by third-parties, or allow Bulle to accelerate payments for add-ons.

During the renovation, Bulle applied and paid for permits with L&I. See

N.T, 5/19/21, at 189; N.T., 5/18/21, at 57, 114, 118, 126. Between October

2017 and January 2018, Bulle completed demolition and began working on

the exterior masonry, roof, basement, windows, framing, and rough-ins. See

-3- J-A14031-23

N.T., 5/18/21, at 53, 56, 59. Bulle performed add-on work and encountered

unforeseen expenses including: having an engineer assess a beam which had

been damaged during a prior fire that Ericsson had not disclosed to Bulle (“the

fire-damaged beam”); waterproofing the basement; installing a storm drain

in the rear yard; developing plans to add a beam to support the front exterior

brick work and then changing the front exterior to brick veneer; installing new

sub-flooring for the upstairs apartments; and levelling a stairway. See

Production Report, dated 1/8/18, unnumbered at 1-2 (admitted at trial as

Exhibit D-20); Cost Summary and Completion Funding, dated 9/18/18,

unnumbered at 2 (admitted at trial as Exhibit D-31); see also N.T., 5/19/21,

at 182-202. Bulle requested the first two draws, which Ericsson paid in full

and on time. See N.T., 5/18/21, at 125; see also id. at 22.

Bulle also applied for a mechanical permit, but beginning in January

2018, L&I rejected plans prepared by YCH, Ericsson’s architect. See

Production Report, dated 1/8/18, unnumbered at 2. Between January and

July 2018, L&I demanded additional information and revisions to the plans, as

well as statements by an engineer (“the permitting delay”), and Bulle

communicated with YCH to resolve those issues. See N.T., 5/19/21, at 202-

13; N.T., 5/18/21, at 133-42. Bulle stopped work in February or March 2018

(“the work stoppage”), and emailed Ericsson about the difficulties working

with YCH and asserting that work had to stop until the mechanical permit

issued. See N.T., 5/19/21, at 202-13; N.T. 5/18/21, at 133-42. In March

2018, Ericsson made a late payment of $37,667 toward the third draw. See

-4- J-A14031-23

N.T., 5/18/21, at 22, 66-672 L&I approved the mechanical permit in July

2018, but Bulle waited for four weeks to pick up and pay for the permit. See

N.T., 5/19/21, at 213-16.

In September 2018, Bulle sent Ericsson a document summarizing its

costs and requesting completion funding. See Cost Summary and Completion

Funding, unnumbered at 1-3. Bulle represented that it spent $32,240 for add-

ons, unforeseen expenses, and all permits and estimated the renovation would

require an additional $98,700 and twelve to sixteen more weeks to complete.

See id. at 2-3; see also N.T., 5/19/21, at 229-33. Shortly thereafter,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas Jefferson University v. Wapner
903 A.2d 565 (Superior Court of Pennsylvania, 2006)
Spang & Co. v. United States Steel Corp.
545 A.2d 861 (Supreme Court of Pennsylvania, 1988)
Department of General Services v. Pittsburgh Building Co.
920 A.2d 973 (Commonwealth Court of Pennsylvania, 2007)
LJL Transportation, Inc. v. Pilot Air Freight Corp.
962 A.2d 639 (Supreme Court of Pennsylvania, 2009)
Douglass v. LICCIARDI CONST. CO., INC.
562 A.2d 913 (Supreme Court of Pennsylvania, 1989)
Coatesville Contractors & Engineers, Inc. v. Borough of Ridley Park
506 A.2d 862 (Supreme Court of Pennsylvania, 1986)
Oelschlegel v. Mutual Real Estate Investment Trust
633 A.2d 181 (Superior Court of Pennsylvania, 1993)
International Diamond Importers, Ltd. v. Singularity Clark, L.P.
40 A.3d 1261 (Superior Court of Pennsylvania, 2012)
Johnston the Florist, Inc. v. TEDCO Construction Corp.
657 A.2d 511 (Superior Court of Pennsylvania, 1995)
Gillard v. Martin
13 A.3d 482 (Superior Court of Pennsylvania, 2010)
Scungio Borst v. 410 Shurs Lane Developers, LLC
106 A.3d 103 (Superior Court of Pennsylvania, 2014)
Seneca Resources Corp. v. S & T Bank
122 A.3d 374 (Superior Court of Pennsylvania, 2015)
Gamesa Energy United States, LLC v. Ten Penn Ctr. Assocs., L.P.
181 A.3d 1188 (Superior Court of Pennsylvania, 2018)
Wag-Myr Woodlands Homeowners Ass'n v. Guiswite
197 A.3d 1243 (Superior Court of Pennsylvania, 2018)
Coulter v. Ramsden
94 A.3d 1080 (Superior Court of Pennsylvania, 2014)
Luria Engineering Co. v. Aetna Casualty & Surety Co.
213 A.2d 151 (Superior Court of Pennsylvania, 1965)
El-Gharbaoui, A. v. Ajayi, A.
2021 Pa. Super. 146 (Superior Court of Pennsylvania, 2021)
Francis, J. v. LCP North Third, LLC
293 A.3d 273 (Superior Court of Pennsylvania, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
Ericsson Properties v. Bulle Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ericsson-properties-v-bulle-construction-pasuperct-2025.