Ericsson Properties v. Bulle Construction

Superior Court of Pennsylvania·Decided January 10, 2025·No. 1516 EDA 2021·Unpublished

Opinion

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

ERICSSON PROPERTIES, LLC : IN THE SUPERIOR COURT OF : PENNSYLVANIA

:

v. :

:

:

BULLE CONSTRUCTION, LLC :

:

Appellant : No. 1516 EDA 2021

Appeal from the Judgment Entered August 31, 2021 In the Court of Common Pleas of Philadelphia County Civil Division at No(s): 0809 Oct. Term 2017

BEFORE: PANELLA, P.J., DUBOW, J., and SULLIVAN, J. MEMORANDUM BY SULLIVAN, J.: FILED JANUARY 10, 2025 Bulle Construction, LLC (“Bulle”) appeals from the judgment entered against it and in favor of Ericsson Properties, LLC (“Ericsson”) following a non- jury trial. We affirm in part, vacate in part, and remand for the trial court to recalculate damages consistent with this decision.

This appeal arises out of a poorly drafted construction contract to renovate a building in Philadelphia (“the property”) and the delays and disputes that led to Ericsson, the owner of the property, to declare a breach and terminate Bulle, the general contractor. Ericsson and Bulle each asserted the other breached the contract and their duties of good faith and fair dealing. Ericsson sought to recover the costs to renovate the property after terminating Bulle (“Ericsson’s costs”). Bulle sought to recover the outstanding balance Ericsson owed under the contract, the costs of the extra, or “add-on,” work Bulle performed, as well as interest, attorney’s fees, and other penalties under

the Contractor and Subcontractor Payment Act (“CASPA”). 1 A more detailed summary of the factual and procedural history of this matter follows.

In October 2017, Ericsson hired Bulle to renovate the property to include a first-floor commercial space, two upstairs apartments, a brick front exterior, and a stucco rear exterior. See N.T., 5/19/21, at 156-75; N.T., 5/18/21, at 97. Ericsson submitted plans from its architect, YCH Architect LLC (“YCH”), and Bulle drafted the renovation contract, which the parties executed. See Final Estimate, signed 10/26/17, unnumbered at 1-9 (hereinafter “the renovation contract”) (admitted as Exhibit P-9 at trial); N.T., 5/19/21, at 156- 75.

The renovation contract set forth a twenty-one-to-twenty-four-week schedule to complete the project. See Renovation Contract at 8 (outlining the work schedule). However, the renovation contract stated that Bulle was not responsible for delays in inspections by the Philadelphia Department of

1 See 73 P.S. §§ 501-517. The purpose of CASPA is to protect contractors and subcontractors and encourage fair dealing among parties to a construction contract. See El-Gharbaoui v. Ajayi, 260 A.3d 944, 954 (Pa. Super. 2021). “Performance by either a contractor or subcontractor pursuant to a contract entitles [it] to payment from the party with whom [it] contracted.” Scungio Borst & Associates v. 410 Shurs Lane Developers, LLC, 106 A.3d 103, 109 (Pa. Super. 2014) (internal citation omitted). CASPA “provides rules and deadlines to ensure prompt payments under construction contracts, to discourage unreasonable withholding of payments, and to address the matter of progress payments and retainages.” Id. (internal citations and quotations omitted).

Licenses and Inspections (“L&I”). See id. at 5 (stating, verbatim: “On Schedule Time Tables . . . In Accordance With [L&I]. Will not be held Accountable for lapses in the city inspectors time tables. if inspector is delayed”).

The renovation contract had a total contract price of $226,000 to be paid by Ericsson over four draws: $75,333, payable in October 2017, to cover fencing, demolition, masonry, roofing, framing, and electrical; $75,333, payable in December 2017, to cover plumbing, HVAC, sprinkler, and fire suppression systems; $48,967, payable in January 2018, to cover drywall, painting, kitchen, tile and flooring, and appliances; and a final payment of $26,367 due upon completion. See id. at 1-9. The renovation contract provided allowances to complete specific items; as to add-on work, the renovation contracts stated that Bulle would discuss with Ericsson “add-ons . . . for resolution” and charge “[a]ny action taken on discussed items to the completion balance.” Id. at 1-5, 9. Ericsson was responsible for the costs of permits. See id. at 1 (stating, verbatim: “Permits . . . (owner will pay for the cost of Building Permit . . .)”). The renovation contract did not specify when Ericsson had to pay for permits, address delays in L&I’s permitting process caused by third-parties, or allow Bulle to accelerate payments for add-ons.

During the renovation, Bulle applied and paid for permits with L&I. See N.T, 5/19/21, at 189; N.T., 5/18/21, at 57, 114, 118, 126. Between October 2017 and January 2018, Bulle completed demolition and began working on the exterior masonry, roof, basement, windows, framing, and rough-ins. See

N.T., 5/18/21, at 53, 56, 59. Bulle performed add-on work and encountered unforeseen expenses including: having an engineer assess a beam which had been damaged during a prior fire that Ericsson had not disclosed to Bulle (“the fire-damaged beam”); waterproofing the basement; installing a storm drain in the rear yard; developing plans to add a beam to support the front exterior brick work and then changing the front exterior to brick veneer; installing new sub-flooring for the upstairs apartments; and levelling a stairway. See Production Report, dated 1/8/18, unnumbered at 1-2 (admitted at trial as Exhibit D-20); Cost Summary and Completion Funding, dated 9/18/18, unnumbered at 2 (admitted at trial as Exhibit D-31); see also N.T., 5/19/21, at 182-202. Bulle requested the first two draws, which Ericsson paid in full and on time. See N.T., 5/18/21, at 125; see also id. at 22.

Bulle also applied for a mechanical permit, but beginning in January 2018, L&I rejected plans prepared by YCH, Ericsson’s architect. See Production Report, dated 1/8/18, unnumbered at 2. Between January and July 2018, L&I demanded additional information and revisions to the plans, as well as statements by an engineer (“the permitting delay”), and Bulle communicated with YCH to resolve those issues. See N.T., 5/19/21, at 202- 13; N.T., 5/18/21, at 133-42. Bulle stopped work in February or March 2018 (“the work stoppage”), and emailed Ericsson about the difficulties working with YCH and asserting that work had to stop until the mechanical permit issued. See N.T., 5/19/21, at 202-13; N.T. 5/18/21, at 133-42. In March 2018, Ericsson made a late payment of $37,667 toward the third draw. See

N.T., 5/18/21, at 22, 66-672 L&I approved the mechanical permit in July 2018, but Bulle waited for four weeks to pick up and pay for the permit. See N.T., 5/19/21, at 213-16.

In September 2018, Bulle sent Ericsson a document summarizing its costs and requesting completion funding. See Cost Summary and Completion Funding, unnumbered at 1-3. Bulle represented that it spent $32,240 for add- ons, unforeseen expenses, and all permits and estimated the renovation would require an additional $98,700 and twelve to sixteen more weeks to complete. See id. at 2-3; see also N.T., 5/19/21, at 229-33. Shortly thereafter, Ericsson sent Bulle a cease-and-desist letter effectively terminating the renovation contract. See N.T., 5/19/21, at 234. Ericsson ultimately hired new contractors and paid them approximately $169,000 to renovate the property. See N.T., 5/18/21, at 79.

Ericsson commenced the underlying action against Bulle in October 2018, asserting breach of contract, negligence, and other claims. Bulle

2 Bulle asserts that the March 2018 payment by Ericsson was a late and partial

Free access — add to your briefcase to read the full text and ask questions with AI

Ericsson Properties v. Bulle Construction, (Pa. Ct. App. 2025).

Ericsson Properties v. Bulle Construction (Ericsson Properties v. Bulle Construction) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Thomas Jefferson University v. Wapner
903 A.2d 565 (Superior Court of Pennsylvania, 2006)
Spang & Co. v. United States Steel Corp.
545 A.2d 861 (Supreme Court of Pennsylvania, 1988)
Department of General Services v. Pittsburgh Building Co.
920 A.2d 973 (Commonwealth Court of Pennsylvania, 2007)
LJL Transportation, Inc. v. Pilot Air Freight Corp.
962 A.2d 639 (Supreme Court of Pennsylvania, 2009)
Douglass v. LICCIARDI CONST. CO., INC.
562 A.2d 913 (Supreme Court of Pennsylvania, 1989)
Coatesville Contractors & Engineers, Inc. v. Borough of Ridley Park
506 A.2d 862 (Supreme Court of Pennsylvania, 1986)
Oelschlegel v. Mutual Real Estate Investment Trust
633 A.2d 181 (Superior Court of Pennsylvania, 1993)
International Diamond Importers, Ltd. v. Singularity Clark, L.P.
40 A.3d 1261 (Superior Court of Pennsylvania, 2012)
Johnston the Florist, Inc. v. TEDCO Construction Corp.
657 A.2d 511 (Superior Court of Pennsylvania, 1995)
Gillard v. Martin
13 A.3d 482 (Superior Court of Pennsylvania, 2010)
Scungio Borst v. 410 Shurs Lane Developers, LLC
106 A.3d 103 (Superior Court of Pennsylvania, 2014)
Seneca Resources Corp. v. S & T Bank
122 A.3d 374 (Superior Court of Pennsylvania, 2015)
Gamesa Energy United States, LLC v. Ten Penn Ctr. Assocs., L.P.
181 A.3d 1188 (Superior Court of Pennsylvania, 2018)
Wag-Myr Woodlands Homeowners Ass'n v. Guiswite
197 A.3d 1243 (Superior Court of Pennsylvania, 2018)
Coulter v. Ramsden
94 A.3d 1080 (Superior Court of Pennsylvania, 2014)
Luria Engineering Co. v. Aetna Casualty & Surety Co.
213 A.2d 151 (Superior Court of Pennsylvania, 1965)
El-Gharbaoui, A. v. Ajayi, A.
2021 Pa. Super. 146 (Superior Court of Pennsylvania, 2021)
Francis, J. v. LCP North Third, LLC
293 A.3d 273 (Superior Court of Pennsylvania, 2023)