Wilbar Realty, Inc. v. Pennsylvania Infrastructure Investment Authority (In Re Wilbar Realty, Inc.)

325 B.R. 354, 2005 Bankr. LEXIS 829, 2005 WL 1050711
CourtUnited States Bankruptcy Court, M.D. Pennsylvania
DecidedMarch 16, 2005
DocketBankruptcy No. 5-00-01242, Adversary No. 5-01-ap-00088
StatusPublished
Cited by1 cases

This text of 325 B.R. 354 (Wilbar Realty, Inc. v. Pennsylvania Infrastructure Investment Authority (In Re Wilbar Realty, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, M.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilbar Realty, Inc. v. Pennsylvania Infrastructure Investment Authority (In Re Wilbar Realty, Inc.), 325 B.R. 354, 2005 Bankr. LEXIS 829, 2005 WL 1050711 (Pa. 2005).

Opinion

OPINION

JOHN J. THOMAS, Chief Judge.

This litigation was initiated by the Debt- or, Wilbar Realty, Inc., against the Pennsylvania Infrastructure Investment Authority (“PENNVEST”). While arising prepetition, the parties agreed that this Court should have jurisdiction to issue a final decision pursuant to 28 U.S.C.A. § 1334(b), 28 U.S.C.A. § 157(c)(2), and Standing Order 00-3 of the United States District Court of the Middle District of Pennsylvania.

Wilbar is a small, locally-owned water company servicing approximately 230-300 customers in Luzerne County, Pennsylvania. (Transcript of 6/4/02 at 18 and 220 (Doc. # 40).) Wilbar was subject to oversight by the Pennsylvania Public Utility Commission (PUC). Due to its deteriorating infrastructure, Wilbar found itself required to upgrade but unable to obtain conventional funding.

PENNVEST is a governmental authority established to come to the aid of various governmental or regulated entities by assisting with funding projects where conventional funding may be either unavailable or inordinately expensive. Moneys loaned by PENNVEST are returned to PENNVEST on an amortized schedule and recirculated to others in need of similar assistance. (Transcript of 8/23/02 at 67 (Doc. # 45).) Typically these PENN-VEST loans are on terms favorable to the borrower.

It was under these circumstances that PENNVEST found itself extending $1,381,549 1 in funds to Wilbar to allow reconstruction of its water system. In addition to this loan, Wilbar was also the recipient of a $250,000 PENNVEST grant toward the installation of water lines and the treatment facility. It was the very manner in which the transfer of funds occurred that led Wilbar to initiate this litigation on the principle grounds that PENNVEST breached the covenant of “good faith” in the manner in which it dealt with Wilbar.

The trial took place over four days stretched sporadically throughout the Court’s calendar. Eight witnesses testified. The Plaintiff presented the testimony of Wilbar principal, Carl Kresge, and Plaintiffs expert, Gary Shambaugh. The evidence that emerged was that: (1) the Wilbar project was constructed by Carl Kresge and Sons, Incorporated; (2) Carl Kresge was the principal of both Wilbar Realty, Inc. and Carl Kresge and Sons, Inc.; (3) payments made by the lender PENNVEST were typically untimely per the contract; (4) Carl Kresge was a difficult individual to communicate with and succeeded in alienating much of the PENNVEST staff; and (5) the most significant concern of Wilbar was the failure of PENNVEST to provide a “final amortization schedule” so that the schedule could be used, by Wilbar, to justify a rate hike request before the PUC.

Much testimony was presented regarding the acrimony and constant disputes that arose between the parties as to the work performed and the supporting documentation furnished by Wilbar in support of requests for advances on the loan. This dispute was presumably resolved by agreement on April 26, 1995 when the parties agreed to be bound by a valuation to be *357 performed by the independent consultant, Buchart-Horn, Inc. (Defendant’s Exhibit No. 26.) That report, referenced as a “Post Construction Review and Cost Estimate Report”, was finalized on June 14, 1995 and concluded that the value of the system was $1,323,318 2 , excluding profit and cost of bond. (Defendant’s Exhibit No. 27.) The cost of bond was not added because Carl Kresge and Sons did not purchase a bond and profit was disallowed since profit was not contemplated by the parties. (Defendant’s Exhibit No. 89.) A review of the Report makes apparent that the “value”, as utilized by Buchart-Horn, equated with its cost estimate. Having agreed to be bound by the Buchart-Horn estimate, Wilbar effectively capped its demand for funding by PENNVEST at that base number. Together with additional adjustments, PENNVEST calculated that Wilbar had “final project costs” of $1,594,450.80, together with unpaid interest through August 1, 1996 of $23,299.22, less the $250,000 grant so as to allow for a total PENNVEST loan of $1,367,750.02. (Defendant’s Exhibit No. 36, Attachment No. 1.) It was, roughly, this sum that was amortized by PENNVEST on August 16, 1996. (Defendant’s Exhibit No. 36.)

Liability

While the testimony was sketchy, Wilbar categorizes four general areas of liability as follows: (1) untimely advances on the loan by PENNVEST; (2) failure to make the final advance on the loan by PENN-VEST; (3) failure to certify completion so that final amortization could be provided and eventually submitted by the Plaintiff to the PUC in support of a rate hike; and (4) breach of the implied covenant of good faith.

This action involves a Pennsylvania contract, and as such, implicates Pennsylvania law. See F.D.I.C. v. Firemen’s Ins. Co. of Newark, NJ, 109 F.3d 1084, 1087 (5th Cir.1997)(“We look to state law for rules governing contract interpretation.”). Moreover, the contract specifies that it shall be governed by Pennsylvania law. (Defendant’s Exhibit No. 1, page 33.)

Untimely Payments

Much of Wilbar’s case complains of the “untimély” progress payments ostensibly made by PENNVEST, which had the immediate result of forcing Kresge to secure and utilize a personal line of credit to fund continuing construction.

The Loan Agreement between PENN-VEST and Wilbar dated September 4, 1991, (Defendant’s Exhibit No. 1), provides, on page 22 thereof, that “On or about twenty-one (21) business days after receipt of an Application [for disbursement], the Authority [PENNVEST] will disburse or advance the amount requested provided that any inspections by consulting engineers or architects satisfactory to the Authority verify those representations and certifications required to be set forth in the Applications pursuant to subpara-graph (b) hereof and provided that all other conditions precedent to such disbursements and advances set forth in this agreement have been satisfied.”

During the trial, the Plaintiff put forth vague testimony as to specific delays attendant with each payment. Nevertheless, PENNVEST submitted Defendant’s Exhibit No. 40 demonstrating the time lapse between receipt of the Wilbar Application and the date PENNVEST sent the Application to the Pennsylvania Comptroller for payment. The Exhibit also sets forth the *358 time the Comptroller had the Application before it was paid.

Specific testimony on the timeliness of these payments was offered at trial by PENNVEST witness, Heather Myers. The parties agreed that at least eight of the twenty-one payments were timely 3 , eight others were late 4 , one was not paid 5 , and disputes existed regarding the timeliness of four of the payments 6 . (Transcript of 7/24/02 at 114-145 (Doc. # 42).)

PENNVEST argues that the delay in paying Payment Request No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re: TK Holdings, Inc.
D. Delaware, 2023

Cite This Page — Counsel Stack

Bluebook (online)
325 B.R. 354, 2005 Bankr. LEXIS 829, 2005 WL 1050711, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilbar-realty-inc-v-pennsylvania-infrastructure-investment-authority-in-pamb-2005.