Posada Investments v. Eliakim Enterprises

CourtSuperior Court of Pennsylvania
DecidedFebruary 13, 2026
Docket3377 EDA 2024
StatusUnpublished
AuthorMcLaughlin

This text of Posada Investments v. Eliakim Enterprises (Posada Investments v. Eliakim Enterprises) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Posada Investments v. Eliakim Enterprises, (Pa. Ct. App. 2026).

Opinion

J-S38015-25

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT O.P. 65.37

POSADA INVESTMENTS, INC. : IN THE SUPERIOR COURT OF : PENNSYLVANIA : v. : : : ELIAKIM ENTERPRISES, LLC, : BROTHER MORENO CONSTRUCTION, : LLC, A & A CONTRACTORS PRIDE, : No. 3377 EDA 2024 INC., MICHAEL A. BRADLEY, TEROX : ELECTRIC & CONSTRUCTION : CORPORATION : : : APPEAL OF: ELIAKIM ENTERPRISES, : LLC :

Appeal from the Judgment Entered January 17, 2025 In the Court of Common Pleas of Philadelphia County Civil Division at No(s): 211101452

BEFORE: McLAUGHLIN, J., KING, J., and BENDER, P.J.E.

MEMORANDUM BY McLAUGHLIN, J.: FILED FEBRUARY 13, 2026

Eliakim Enterprises, LLC (“Eliakim”) appeals from the judgment of

$299,785.19 entered against it and in favor of Posada Investments, Inc.

(“Posada”) for breach of contract. Eliakim argues the court applied the wrong

standard to calculate damages, the evidence of damages was speculative, and

the court erred in relying on the expert’s opinion of damages. We affirm.

Posada purchased a residential property on Federal Street in

Philadelphia. Posada and Eliakim entered into a contract in November 2019

whereby Eliakim would act as project manager and oversee the property’s

rehabilitation. Eliakim was to be responsible for the hiring and payment of J-S38015-25

contractors and agreed to rehabilitate the property within seven months.

Posada paid Eliakim between $224,000 and $230,000 for the project.

Eliakim thereafter contracted with Brother Moreno Construction LLC

(“Brother Moreno”) to complete the scope of work identified in Eliakim’s

contract with Posada. Eliakim paid Brother Moreno the entirety of the money

Posada had provided for the project.

A few months into the contract period, the principal of Posada, Maria

Posada (“Maria”), inspected the property. She identified several serious issues

with the construction, including that the floor was not level, the windows were

not properly installed, and water was infiltrating the property. Trial Court

Decision, filed 8/28/24, at 5 (citing N.T., 4/11/24, at 23-24). Nestor Colon,

who owns Eliakim, assured Posada that he would have Brother Moreno fix the

problems. A month later, when Maria made another visit to the property, she

saw the problems had not been fixed. Colon told her it was because Brother

Moreno’s staff was sick or had been working on other properties.

Brother Moreno left the job in late summer or early fall 2020, without

completing the rehabilitation. It informed Posada that the blueprints Eliakim

had given it were incorrect, which resulted in a wall being built in the wrong

place, and that the wall needed to be demolished and rebuilt. It also told

Posada that it was leaving the job because it was in an unrelated dispute with

Colon regarding a different project. Brother Moreno asked Posada to pay it

another $40,000 to complete the work, and Posada refused.

-2- J-S38015-25

Eliakim filed a claim against Brother Moreno’s insurance policy and

advised Posada not to hire a new contractor until the claim had been resolved.

Posada waited six or seven months. The insurance company denied the claim.

Posada fired Eliakim in February or March 2021. It hired a new contractor to

inspect the property, which informed it that Brother Moreno’s work would have

to be removed and redone.

Posada brought this action against Eliakim and Brother Moreno for

breach of contract, negligence, fraudulent misrepresentation, and unjust

enrichment.1 Brother Moreno failed to respond to the complaint, and the court

entered default judgment against it.

At a bench trial, Posada presented testimony establishing the above

facts. It also presented the testimony of an expert in engineering and the

proper methods of construction, repair, and removal, Jospeh Keil, P.E. Keil

testified that he inspected the property in February 2022. He stated that due

to large gaps surrounding the window frames and external vents and the

positioning of the roof drain, water had infiltrated the stucco. Keil opined that

the entire stucco veneer would therefore need to be replaced. He also found

water had been entering the property through an unattached roofing

membrane, an unsealed pilot house door, and the improperly sloping roof deck

and basement window well. Keil observed mold on every floor of the property

as well as water stains on the ceilings and walls. He opined that the work

____________________________________________

1 The other claims and parties in the litigation are not at issue in this appeal.

-3- J-S38015-25

performed was “[n]ot even close” to industry standards and that the only way

to make the property habitable was to “strip it down to the studs.” N.T.,

4/11/24, at 130-31. His report stated,

Based upon my inspection and experience, it is my professional opinion that the work initially performed at 2215 Federal Street was of poor quality, deviated from the contract drawings and was not in accordance with applicable codes. Failed to maintain a water-tight structure during construction and was generally substandard. Based upon the above, much of the work needed to be repaired, relocated, removed or replaced.

Id. at 133.

On cross-examination, Keil admitted that he did not know which party

was responsible for the conditions he observed at the property. Id. at 133-

134. Nor did he know when the substandard construction occurred. Id. at 134,

138. He also did not offer any estimate as to the cost of repairs or remediation.

Id. at 137-38. Furthermore, Keil stated he did not review any of the contracts

at issue. Id. at 138.

Maria testified that after Posada fired Eliakim, it spent $150,211.70 on

labor and $80,769.33 on materials to put the property in the condition

contemplated by the contract. Id. at 50, 59. Maria also testified her company

incurred $68,804.60 in carrying costs based on the delay in the construction.

Id. at 55-56. Maria explained the carrying costs included such items as loan

interest, utility bills, and licenses and inspections. Id. at 38-39. To

substantiate these sums, Posada provided copies of the checks, invoices, bills,

and receipts, along with charts sub-totaling the amounts and providing a brief

-4- J-S38015-25

description of each category of payments. Maria testified that it took until

2023 to finish the rehabilitation because the new contractors continued to

identify problems with the property that Eliakim and Brother Moreno had failed

to fix. See id. at 109-10.

The court found Eliakim liable for breach of contract. It awarded

damages against Eliakim and Brother Moreno, jointly and severally, in the

amount of $299,785.19.2 The court found Posada did not present sufficient

evidence to support an award of attorneys’ fees and costs and did not prove

Eliakim was liable for negligence, fraudulent misrepresentation, or unjust

enrichment. Eliakim filed a post-trial motion for judgment notwithstanding the

verdict, which the court denied.

Eliakim appealed.3 It raises the following issues:

1. Whether the trial court erred or abused its discretion by finding for [Posada] on its breach of contract claim by applying the wrong calculation of damages as applicable to the breach of contract?

[2].

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ecksel v. Orleans Construction Co.
519 A.2d 1021 (Supreme Court of Pennsylvania, 1987)
Douglass v. LICCIARDI CONST. CO., INC.
562 A.2d 913 (Supreme Court of Pennsylvania, 1989)
Pittsburgh Construction Co. v. Griffith
834 A.2d 572 (Superior Court of Pennsylvania, 2003)
Johnston the Florist, Inc. v. TEDCO Construction Corp.
657 A.2d 511 (Superior Court of Pennsylvania, 1995)
Gloviak v. Tucci Construction Co.
608 A.2d 557 (Superior Court of Pennsylvania, 1992)
El-Gharbaoui, A. v. Ajayi, A.
2021 Pa. Super. 146 (Superior Court of Pennsylvania, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
Posada Investments v. Eliakim Enterprises, Counsel Stack Legal Research, https://law.counselstack.com/opinion/posada-investments-v-eliakim-enterprises-pasuperct-2026.