Posada Investments v. Eliakim Enterprises

Superior Court of Pennsylvania·Decided February 13, 2026·No. 3377 EDA 2024·Unpublished·McLaughlin

Opinion

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT O.P. 65.37

POSADA INVESTMENTS, INC. : IN THE SUPERIOR COURT OF : PENNSYLVANIA

:

v. :

:

:

ELIAKIM ENTERPRISES, LLC, : BROTHER MORENO CONSTRUCTION, : LLC, A & A CONTRACTORS PRIDE, : No. 3377 EDA 2024 INC., MICHAEL A. BRADLEY, TEROX : ELECTRIC & CONSTRUCTION : CORPORATION :

:

:

APPEAL OF: ELIAKIM ENTERPRISES, : LLC :

Appeal from the Judgment Entered January 17, 2025 In the Court of Common Pleas of Philadelphia County Civil Division at No(s): 211101452

BEFORE: McLAUGHLIN, J., KING, J., and BENDER, P.J.E. MEMORANDUM BY McLAUGHLIN, J.: FILED FEBRUARY 13, 2026 Eliakim Enterprises, LLC (“Eliakim”) appeals from the judgment of $299,785.19 entered against it and in favor of Posada Investments, Inc. (“Posada”) for breach of contract. Eliakim argues the court applied the wrong standard to calculate damages, the evidence of damages was speculative, and the court erred in relying on the expert’s opinion of damages. We affirm.

Posada purchased a residential property on Federal Street in Philadelphia. Posada and Eliakim entered into a contract in November 2019 whereby Eliakim would act as project manager and oversee the property’s rehabilitation. Eliakim was to be responsible for the hiring and payment of

contractors and agreed to rehabilitate the property within seven months. Posada paid Eliakim between $224,000 and $230,000 for the project.

Eliakim thereafter contracted with Brother Moreno Construction LLC (“Brother Moreno”) to complete the scope of work identified in Eliakim’s contract with Posada. Eliakim paid Brother Moreno the entirety of the money Posada had provided for the project.

A few months into the contract period, the principal of Posada, Maria Posada (“Maria”), inspected the property. She identified several serious issues with the construction, including that the floor was not level, the windows were not properly installed, and water was infiltrating the property. Trial Court Decision, filed 8/28/24, at 5 (citing N.T., 4/11/24, at 23-24). Nestor Colon, who owns Eliakim, assured Posada that he would have Brother Moreno fix the problems. A month later, when Maria made another visit to the property, she saw the problems had not been fixed. Colon told her it was because Brother Moreno’s staff was sick or had been working on other properties.

Brother Moreno left the job in late summer or early fall 2020, without completing the rehabilitation. It informed Posada that the blueprints Eliakim had given it were incorrect, which resulted in a wall being built in the wrong place, and that the wall needed to be demolished and rebuilt. It also told Posada that it was leaving the job because it was in an unrelated dispute with Colon regarding a different project. Brother Moreno asked Posada to pay it another $40,000 to complete the work, and Posada refused.

Eliakim filed a claim against Brother Moreno’s insurance policy and advised Posada not to hire a new contractor until the claim had been resolved. Posada waited six or seven months. The insurance company denied the claim. Posada fired Eliakim in February or March 2021. It hired a new contractor to inspect the property, which informed it that Brother Moreno’s work would have to be removed and redone.

Posada brought this action against Eliakim and Brother Moreno for breach of contract, negligence, fraudulent misrepresentation, and unjust enrichment.1 Brother Moreno failed to respond to the complaint, and the court entered default judgment against it.

At a bench trial, Posada presented testimony establishing the above facts. It also presented the testimony of an expert in engineering and the proper methods of construction, repair, and removal, Jospeh Keil, P.E. Keil testified that he inspected the property in February 2022. He stated that due to large gaps surrounding the window frames and external vents and the positioning of the roof drain, water had infiltrated the stucco. Keil opined that the entire stucco veneer would therefore need to be replaced. He also found water had been entering the property through an unattached roofing membrane, an unsealed pilot house door, and the improperly sloping roof deck and basement window well. Keil observed mold on every floor of the property as well as water stains on the ceilings and walls. He opined that the work

1 The other claims and parties in the litigation are not at issue in this appeal.

performed was “[n]ot even close” to industry standards and that the only way to make the property habitable was to “strip it down to the studs.” N.T., 4/11/24, at 130-31. His report stated,

Based upon my inspection and experience, it is my professional opinion that the work initially performed at 2215 Federal Street was of poor quality, deviated from the contract drawings and was not in accordance with applicable codes. Failed to maintain a water-tight structure during construction and was generally substandard. Based upon the above, much of the work needed to be repaired, relocated, removed or replaced.

Id. at 133.

On cross-examination, Keil admitted that he did not know which party was responsible for the conditions he observed at the property. Id. at 133- 134. Nor did he know when the substandard construction occurred. Id. at 134, 138. He also did not offer any estimate as to the cost of repairs or remediation. Id. at 137-38. Furthermore, Keil stated he did not review any of the contracts at issue. Id. at 138.

Maria testified that after Posada fired Eliakim, it spent $150,211.70 on labor and $80,769.33 on materials to put the property in the condition contemplated by the contract. Id. at 50, 59. Maria also testified her company incurred $68,804.60 in carrying costs based on the delay in the construction. Id. at 55-56. Maria explained the carrying costs included such items as loan interest, utility bills, and licenses and inspections. Id. at 38-39. To substantiate these sums, Posada provided copies of the checks, invoices, bills, and receipts, along with charts sub-totaling the amounts and providing a brief

description of each category of payments. Maria testified that it took until 2023 to finish the rehabilitation because the new contractors continued to identify problems with the property that Eliakim and Brother Moreno had failed to fix. See id. at 109-10.

The court found Eliakim liable for breach of contract. It awarded damages against Eliakim and Brother Moreno, jointly and severally, in the amount of $299,785.19.2 The court found Posada did not present sufficient evidence to support an award of attorneys’ fees and costs and did not prove Eliakim was liable for negligence, fraudulent misrepresentation, or unjust enrichment. Eliakim filed a post-trial motion for judgment notwithstanding the verdict, which the court denied.

Eliakim appealed.3 It raises the following issues:

1. Whether the trial court erred or abused its discretion by finding for [Posada] on its breach of contract claim by applying the wrong calculation of damages as applicable to the breach of contract?

[2]. Whether the trial court erred or abused its discretion by finding for [Posada] on its breach of contract claim by applying the testimony of [Posada] to determine the amount of damages?

[3]. Whether the trial court erred or abused its discretion by admitting the testimony of the [e]xpert Joseph Keil regarding the

2 The three sums Posada claimed as damages total $299,785.63. Neither party has raised the 44-cent discrepancy. 3 Eliakim prematurely appealed from the order denying its post-trial motion.

See Johnston the Florist, Inc. v. TEDCO Const. Corp., 657 A.2d 511, 514 (Pa.Super. 1995). This Court ordered Eliakim to praecipe the trial court to enter judgment. The trial court’s prothonotary entered judgment on January 17, 2025, perfecting the appeal. See Pa.R.A.P. 905(a)(5).

breach of contract claim where he testified he had never read the contract?

Free access — add to your briefcase to read the full text and ask questions with AI

Posada Investments v. Eliakim Enterprises, (Pa. Ct. App. 2026).

Posada Investments v. Eliakim Enterprises (Posada Investments v. Eliakim Enterprises) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ecksel v. Orleans Construction Co.
519 A.2d 1021 (Supreme Court of Pennsylvania, 1987)
Douglass v. LICCIARDI CONST. CO., INC.
562 A.2d 913 (Supreme Court of Pennsylvania, 1989)
Pittsburgh Construction Co. v. Griffith
834 A.2d 572 (Superior Court of Pennsylvania, 2003)
Johnston the Florist, Inc. v. TEDCO Construction Corp.
657 A.2d 511 (Superior Court of Pennsylvania, 1995)
Gloviak v. Tucci Construction Co.
608 A.2d 557 (Superior Court of Pennsylvania, 1992)
El-Gharbaoui, A. v. Ajayi, A.
2021 Pa. Super. 146 (Superior Court of Pennsylvania, 2021)