Dillingham-Ray Wilson v. City of Los Angeles

182 Cal. App. 4th 1396, 106 Cal. Rptr. 3d 691, 2010 Cal. App. LEXIS 350
CourtCalifornia Court of Appeal
DecidedMarch 18, 2010
DocketB192900
StatusPublished
Cited by25 cases

This text of 182 Cal. App. 4th 1396 (Dillingham-Ray Wilson v. City of Los Angeles) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dillingham-Ray Wilson v. City of Los Angeles, 182 Cal. App. 4th 1396, 106 Cal. Rptr. 3d 691, 2010 Cal. App. LEXIS 350 (Cal. Ct. App. 2010).

Opinion

Opinion

ASHMANN-GERST, J.

The City of Los Angeles (City) obtained millions of dollars worth of construction work that it does not want to pay for. It believes it is absolved of any obligation to pay by Public Contract Code section 7107 1 and Amelco Electric v. City of Thousand Oaks (2002) 27 Cal.4th 228 [115 Cal.Rptr.2d 900, 38 P.3d 1120] (Amelco) on the theory that they dictate a method of proving contract damages, a method that the contractor, Dillingham-Ray Wilson (DRW), says is impossible under the circumstances. Below, DRW asserted its own claims and pass-through claims of subcontractors against the City for breach of a public works contract and obtained an award in excess of $36 million for delays, unpaid contract retention, prompt pay penalties, prejudgment interest and attorney fees. But prior to that, the trial court granted in limine motions and excluded $25 million of DRW’s claims on the theory that it could not document its actual costs as required by contract, it was not permitted to prove damages with engineering estimates, and it was not entitled to prove damages using a modified total cost theory. In the published portion of this opinion, we conclude that the trial court erred because section 7107 and Amelco impact the measure of damages, not the method of proving them, and also because a modified total cost theory is permissible. Further, DRW is entitled to litigate whether it was required to document its actual costs as a condition of payment.

*1400 By cross-appeal, the City requests reversal of the judgment on the theory that the trial court committed evidentiary and jury instruction error. Also, the City argues that the trial court erred when it granted prompt pay penalties and attorney fees pursuant to section 7107, subdivision (f), and attorney fees pursuant to California’s False Claims Act (Gov. Code, § 12650 et seq.). In the unpublished portion of this opinion, we conclude that these arguments lack merit. However, we also conclude that the City raises at least one valid point, which is that the trial court lacked statutory authority to grant continuing prompt pay penalties after judgment was entered. 2

Because prompt pay penalties cannot continue after judgment is entered, we modify the award in favor of DRW to reflect that interest on the prompt pay penalties shall accrue at 7 percent legal interest postjudgment. As modified, the award in favor of DRW is affirmed. The judgment, however, is reversed and remanded for a trial on DRW’s excluded claims. 3

FACTS

After competitive bidding, DRW was awarded a public works contract (C-741 contract) by the City to expand the digester capacity at the Hyperion Wastewater Treatment Plant. The City was permitted to retain up to 10 percent of each progress payment (retention) and hold those funds in an interest-bearing escrow account. Additionally, it could deduct liquidated damages for delays from any payments made. During construction, the City issued over 300 change orders containing more than 1,000 changes to the plans and specifications. On rare occasions, the City directed DRW to perform changes on a time and materials basis. In general, the City requested an estimate of the cost of work, told DRW to commence work and agreed the parties would negotiate a lump-sum payment at a later date. Though the parties agreed on the compensation payable for some of the time and materials change orders and lump-sum change orders, not all the change orders were settled. When DRW completed the project, it asked for an equitable adjustment to compensate it for work performed without a price, and for the expenses and losses incurred due to the City’s interference and delays. The City refused. In addition, the City assessed liquidated damages against DRW for delays and did not release the retention funds from escrow.

DRW sued the City for breach of contract. The City cross-complained. The City’s claim for breach of contract alleged, inter alia, that DRW was liable for *1401 liquidated damages. Other claims were asserted against DRW and a subcontractor, CBI Services, Inc. (CBI), for fraud and violation of the False Claims Act in connection with their requests for payment.

Based on Amelco and section 7105, subdivision (d)(2), 4 the City filed motions in limine to preclude DRW from presenting a total cost claim to the jury, and from proving its damages with engineering estimates. The trial court precluded a total cost theory of damages on the grounds that DRW’s evidence in support of the theory was insufficient, and ruled that a modified total cost theory was not recognized in California. Next, the trial court ruled that general conditions section 38 (GC Section 38) of the C-741 contract required DRW to proceed on a time and materials basis and document actual costs any time the parties did not agree on a lump sum. DRW was precluded from introducing evidence or presenting argument to the jury that it was entitled to recover damages resulting from changes or extra work calculated by any method other than as provided in the C-741 contract. The trial court held a hearing and found that the in limine rulings barred three of DRW’s 10 damages claims: (1) claim No. 3 for the difference between the City’s estimates and DRW’s estimates on lump-sum change orders when the parties did not agree on a price; (2) claim No. 5 for additional payments due from the City because of breaches of the implied warranty of correctness of the plans and for other breaches of contract; 5 and (3) claim No. 6 for the cost of inefficient labor caused by breach of the implied warranty of correctness of the plans.

The case proceeded to trial on DRW’s claims for delay damages, wrongfully withheld retention and prompt pay penalties, and on the City’s cross-complaint. Following the presentation of evidence, the trial court instructed the jury and tasked it with interpreting the C-741 contract.

The jury rendered a general verdict with special interrogatories. The jury found that the City breached the C-741 contract and caused DRW damages. *1402 Under section 7107, the jury concluded that the City’s assessment of liquidated damages was unreasonable. Next, the jury found that the City was not entitled to an offset for liquidated damages, and that it was not entitled to recover on its False Claims Act claims and fraud allegations. The judgment for DRW awarded $12,369,880 in contract damages; prejudgment interest on the contract damages; $15,035,533 in prompt payment penalties pursuant to section 7107, subdivision (f); and postjudgment prompt pay penalties until the retention funds were paid to DRW. In posttrial motions under the False Claims Act, DRW was awarded $1,634,188.50 in attorney fees and CBI was awarded $1,211,858 in attorney fees. Based on section 7107, subdivision (f), the trial court awarded DRW $3,799,048.74 in attorney fees expended to recover the withheld retention funds. 6

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shen v. Xia CA6
California Court of Appeal, 2025
Art Reproductive Center v. Hill CA2/3
California Court of Appeal, 2025
Garner v. BNSF Railway Co.
California Court of Appeal, 2024
Hughes v. Boris CA2/5
California Court of Appeal, 2022
Zech v. Richards CA4/3
California Court of Appeal, 2022
Earle & Reimer APC v. Klimek CA6
California Court of Appeal, 2016
Kinda v. Carpenter
247 Cal. App. 4th 1268 (California Court of Appeal, 2016)
JMR Construction Corp. v. Environmental Assessment & Remediation Management, Inc.
243 Cal. App. 4th 571 (California Court of Appeal, 2015)
United Riggers & Erectors v. Coast Iron & Steel
California Court of Appeal, 2015
United Riggers & Erectors, Inc. v. Coast Iron & Steel Co.
196 Cal. Rptr. 3d 161 (California Court of Appeals, 2nd District, 2015)
Marina Pacifica Homeowners Ass'n v. Southern California Financial Corp.
232 Cal. App. 4th 494 (California Court of Appeal, 2014)
Cal-Murphy v. MG Restaurants CA21/5
California Court of Appeal, 2014

Cite This Page — Counsel Stack

Bluebook (online)
182 Cal. App. 4th 1396, 106 Cal. Rptr. 3d 691, 2010 Cal. App. LEXIS 350, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dillingham-ray-wilson-v-city-of-los-angeles-calctapp-2010.