Brasel & Sims Construction Co. v. State Highway Commission of Wyoming

655 P.2d 265, 1982 Wyo. LEXIS 418
CourtWyoming Supreme Court
DecidedDecember 14, 1982
Docket5678
StatusPublished
Cited by27 cases

This text of 655 P.2d 265 (Brasel & Sims Construction Co. v. State Highway Commission of Wyoming) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brasel & Sims Construction Co. v. State Highway Commission of Wyoming, 655 P.2d 265, 1982 Wyo. LEXIS 418 (Wyo. 1982).

Opinions

RAPER, Justice.

The jurisdiction of the district court to entertain a petition for review under the provisions of the Wyoming Administrative Procedure Act, § 9-4-101, et seq., W.S. 1977, from the findings of fact, conclusions of law and final order made following a claim procedure provided for by a highway construction contract between Brasel and Sims Construction Company (appellant) and the State Highway Commission of Wyoming (appellee) is the issue upon which this court will make disposition. The district court affirmed the appellee’s denial of appellant’s claim.

This is not the issue presented by either of the parties in their briefs or during oral argument on the appeal to this court, but originated during the course of the court’s conference following oral argument. We became concerned about jurisdiction and therefore requested supplemental briefs on the following question:

“Does the Wyoming Administrative Procedure Act, § 9-4-101, W.S.1977, et seq., confer upon the district courts of this state jurisdiction to review the denial of a claim made upon a contract with the Wyoming State Highway Department which has been presented and denied in accordance with the rules and regulations of the Wyoming State Highway Department, and, if so, what is the impact upon such review jurisdiction of the right of the claimant to bring suit against the Wyoming State Highway Department based upon the claim?”

We will dismiss the appeal for the ultimate reason that the district court had no jurisdiction to entertain a petition for review, and, therefore, neither do we. Pritchard v. State, Division of Vocational [266]*266Rehabilitation, Department of Health and Social Services, Wyo., 540 P.2d 523 (1975); Snell v. Ruppert, Wyo., 541 P.2d 1042 (1975).

In September, 1978, the appellee called for bids to do construction work on a two-lane highway between Midwest and Reno Junction. Appellant’s low bid of $4,011, 221.70 was accepted by appellee and a contract dated October 19, 1978, was entered into. Part VII of the contract provided:

“VII. Any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Engineer, who shall reduce his decision to writing and mail or otherwise furnish a copy thereof to the Contractor. The decision of the Engineer shall be final and conclusive unless, within 30 days from the date of receipt of such conclusion, the Contractor mails or otherwise furnishes the Wyoming State Highway Commission written appeal. In connection with any appeal proceeding under this clause, the Contractor shall be afforded an opportunity to be heard and to offer evidence in support of his appeal.”

Wyoming Highway Department Specifications for Road and Bridge Construction, 1974, were, by reference, made a part of the contract. Section 105.17 of those specifications set out a claim procedure:

“105.17 CLAIMS FOR ADJUSTMENTS AND DISPUTES. If in any case the Contractor deems that additional compensation is due him for work or material not clearly covered in the contract or not ordered as extra work as defined herein, or that contract time be extended, the Contractor shall notify the Engineer in writing within a reasonable time of his intention to make claim for such additional compensation or extended time. This notification should also specify the basis for the claim. The Engineer will acknowledge receipt of said intention and advise the Contractor that consideration will be given the claim when it is submitted in a formal manner with complete and thorough justification for every item. “Within sixty (60) days from the date of the Contractor’s formal claim, the Department will render to the Contractor a judgment in writing. This judgment shall be final and binding upon both parties to the contract unless the Contractor files within thirty (30) days of the date of said judgment a written notice of appeal with the Secretary of the Highway Commission. Subsequent to the filing of the notice of appeal, the claim will be pursued according to the Contractor’s Claim Procedure adopted by the Highway Commission.
“Under no circumstances will a claim be considered if submitted later than sixty (60) days after publication of first notice of advertisement that work has been accepted as complete.
“If the claim is found to be just, it will be paid on the basis of actual costs to which no percentage will be added. The justification for payment may be based upon an audit by the Department of the Contractor’s project records and cost accounting system. Nothing in this subsection should be construed as establishing any claim contrary to the terms of subsection 104.02.”

Pursuant to the above provision, appellant filed a claim in the amount of $2,323, 635.00 for additional compensation, allegedly not clearly covered by the 1978 contract. The claim was denied by the State Highway Department whereupon an appeal was taken to appellee. An extensive hearing was held before the appellee in accordance with the rules of practice adopted by the appel-lee for hearings “as authorized and required by Chapter 108, Session Laws of Wyoming, 1965 [Wyoming Administrative Procedure Act, § 9-4-101, et seq., W.S.1977].”

The dispute involved water, excavation, gravel pits, fencing, revegetation, removal and stockpiling of old road surface, guardrail and cost calculations. After the hearing, comprehensive findings of fact, conclusions of law and an order, dated September 18, 1981, were adopted by the chairman of the appellee deciding that the appellant “recover none of the additional compensation sought * * The claim was denied by appellee primarily because of failure of proof and was held to be an effort to convert a fixed-price contract, given to the lowest bidder, into a cost-plus contract.

The appellant thereupon filed a petition for review in the district court, Fremont County, Ninth Judicial District. Following submission of briefs to the district judge, the September 18, 1981 order of the appel-lee was affirmed. This appeal on the mer[267]*267its followed. During the course of oral argument, it was revealed that a separate action had been filed by appellant in the District Court for Laramie County, First Judicial District, apparently seeking a recovery for monies claimed and arising out of the same contract now here as the subject of an administrative review. In the supplemental brief of appellant it is also disclosed that a claim had been filed with and rejected by the state auditor prior to commencement of the action in accordance with § 9-2-332, W.S.1977, Cum.Supp.1982:

“Except as provided by W.S. 1-39-101 through 1-39-119, persons having claims against the state shall exhibit the claim, with the evidence in support thereof, to the auditor, to be audited, settled and allowed, within one (1) year after the claim accrues and not afterward.”

The scope of the jurisdiction of the Wyoming State Highway Commission with respect to road construction is circumscribed by § 24-2-108, W.S.1977, in pertinent part:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

White v. State
784 P.2d 1313 (Wyoming Supreme Court, 1989)
Miller v. State
784 P.2d 209 (Wyoming Supreme Court, 1989)
Westates Construction Co. v. City of Cheyenne
775 P.2d 502 (Wyoming Supreme Court, 1989)
Scanlon v. Schrinar
759 P.2d 1243 (Wyoming Supreme Court, 1988)
Allied Fidelity Insurance Co. v. Environmental Quality Council
753 P.2d 1038 (Wyoming Supreme Court, 1988)
Trout v. Wyoming Oil & Gas Conservation Commission
721 P.2d 1047 (Wyoming Supreme Court, 1986)
City of Evanston v. Griffith
715 P.2d 1381 (Wyoming Supreme Court, 1986)
Hupp v. Employment Security Commission of Wyoming
715 P.2d 223 (Wyoming Supreme Court, 1986)
New Pueblo Constructors, Inc. v. State
696 P.2d 185 (Arizona Supreme Court, 1985)
State Highway Commission v. Brasel & Sims Construction Co.
688 P.2d 871 (Wyoming Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
655 P.2d 265, 1982 Wyo. LEXIS 418, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brasel-sims-construction-co-v-state-highway-commission-of-wyoming-wyo-1982.