City of Evanston v. Griffith

715 P.2d 1381, 1986 Wyo. LEXIS 517
CourtWyoming Supreme Court
DecidedMarch 21, 1986
Docket85-103
StatusPublished
Cited by6 cases

This text of 715 P.2d 1381 (City of Evanston v. Griffith) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Evanston v. Griffith, 715 P.2d 1381, 1986 Wyo. LEXIS 517 (Wyo. 1986).

Opinions

CARDINE, Justice.

This case was certified to this court from the district court pursuant to Rule 12.09, W.R.A.P. It involves a decision by the state auditor and treasurer to withhold impact assistance funds from the City of Ev-anston. We must decide whether those funds must be paid under §§ 39-6-411(c) and 39-6-512(d), W.S.1977 (May 1985 Replacement) even though the industrial facility to which the funds relate did not receive a permit until after construction commenced. We hold that the funds must be disbursed.

On August 7, 1981, Amoco Production Company began construction of a natural gas processing facility in Uinta County. Amoco failed to obtain a permit before commencing construction as required by § 35-12-106(a), W.S.1977 of the Industrial Development Information and Siting Act.1

Amoco finally applied to the Office of Industrial Siting Administration for a permit on July 13, 1983. An evidentiary hearing was held before the Industrial Siting Council (Council) and, on March 12, 1984, the Council issued findings of fact, conclusions of law, and an order granting Amoco the permit. In its fourth conclusion of law, the Council created a retroactive date for the permit:

“As a result of the construction commencing on the central production facility pursuant to Air Quality Permit No. CT-391 on August 7, 1981, the Council concludes that the permit issued in this matter shall be effective as of August 7, 1981, and that the permit conditions established by this Order shall be effective as of the date of execution of this Order and the permit.”

The permit itself also included the retroactive date:

“This permit is issued effective August 7, 1981, and shall remain in force throughout the useful life of the facility. The conditions and stipulations of this permit shall become effective as of the date of execution hereof.”

The decision of the Council was not appealed or collaterally attacked by the State. Instead, this dispute arose when the City of Evanston requested the state treasurer to pay impact assistance funds to the City based on the August 7, 1981 commencement of plant construction. The treasurer paid the impact assistance monies that accrued after March 12, 1984, the date upon which the Council issued the Amoco permit, but refused to make payments covering the period from August 7, 1981 to March 12, 1984. The City filed a claim for $3,201,-511.82, the amount withheld, and the treasurer formally denied it.

[1383]*1383The City next attempted to compel payment by filing in district court a combined petition for a writ of mandamus, petition for review and complaint requesting declaratory judgment.2 The court held a hearing and decided that the case should be certified directly to this court under Rule 12.09, W.R.A.P., which states:

“If after such review, the district court concludes the matter to be appropriate for determination by the Supreme Court, the district court may certify the case to the Supreme Court.” 3

PLAIN MEANING

The two statutes at issue in this case, §§ 39-6-411(c) and 39-6-512(d), W.S.1977 (May 1985 Replacement), are part of the salés and use tax distribution structure.4 They create a mechanism by which extraordinary sales and use tax revenues collected during boom times are returned to the counties of collection for impact assistance. Both statutes are identical in their relevant terms, providing:

“If any person commences after the effective date of this act to construct an industrial facility, as that term is defined in W.S. 35-12-102(a), under a permit issued pursuant to W.S. 35-12-106, * * * the state treasurer shall thereafter pay to the county treasurer * ⅜ * impact assistance payments from the monies available under W.S. 39-6-41 l(b)(i) [or W.S. 39-6-512(b)(i)].”

The State contends that the state treasurer is not authorized to make payments under these statutes for construction that takes place before a permit has actually been issued. According to the State, construction does not commence “under a permit issued pursuant to W.S. 35-12-106” just because a permit is eventually issued with an effective date covering the entire construction period.

The City, on the other hand, argues that construction commences “under a permit issued pursuant to W.S. 35-12-106” as long as a permit is eventually issued and dated to correspond to the actual commencement of construction. The City claims, in effect, that the status of a project is not frozen at the time construction takes place. Its status as permitted or unpermitted can be retroactively changed by the issuance of a permit that relates back to the date of actual construction.

It is clear from these arguments that the key statutory clause is, “under a permit issued pursuant to W.S. 35-12-106.” We must decide whether construction of Amoco’s natural gas processing plant was commenced “under a permit issued pursuant to W.S. 35-12-106” although the retroactively dated permit was issued after the actual commencement of construction.

Ironically, both parties argue that the statute is so clear that we need not resort to any rules of statutory construction. They both implore us to interpret the stat[1384]*1384ute according to contradictory “plain meanings.” We do not believe that the statute is as clear as the parties claim.

We think that the critical phrase of the statute is ambiguous because it is “uncertain and susceptible to more than one meaning.” Attletweedt v. State, Wyo., 684 P.2d 812, 814 (1984). The statute does not tell us under what circumstances construction should be held to have commenced under a permit issued pursuant to § 35-12-106. Perhaps it commences “under a permit” only if the permit is issued beforehand. Perhaps, on the other hand, construction has commenced “under a permit” as long as the permit is dated to correspond to the first day of actual construction. We must turn to the applicable rules of statutory construction to make that determination. Attletweedt v. State, supra, at 814.

STATUTORY CONSTRUCTION

“In construing statutes, legislative intent is the primary consideration. If the language is sufficiently clear, there is no need to resort to rules of construction. When the language is not clear or is ambiguous, the court must look to the mischief the statute was intended to cure, the historical setting surrounding its enactment, the public policy of the state, the conclusions of law, and other prior and contemporaneous facts and circumstances, making use of the accepted rules of construction to ascertain a legislative intent that is reasonable and consistent.” State ex rel. Motor Vehicle Division v. Holtz, Wyo., 674 P.2d 732, 736 (1983).

The aids to construction outlined in Holtz, supra, are not always helpful because we do not have published legislative debates, committee reports and other legislative materials at our disposal in this state. In the case at bar, however, we do have the luxury of a comprehensive act, closely related to the statutes at issue, to which we can turn.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Natrona County School District No. 1 v. Ryan
764 P.2d 1019 (Wyoming Supreme Court, 1988)
Department of Revenue & Taxation v. Hamilton
743 P.2d 877 (Wyoming Supreme Court, 1987)
Simons v. Laramie County School District No. One
741 P.2d 1116 (Wyoming Supreme Court, 1987)
City of Evanston v. Griffith
715 P.2d 1381 (Wyoming Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
715 P.2d 1381, 1986 Wyo. LEXIS 517, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-evanston-v-griffith-wyo-1986.