WATERS EDGE BUILDERS, LLC v. Longa

715 S.E.2d 193, 214 N.C. App. 350, 2011 N.C. App. LEXIS 1623, 2011 WL 3276642
CourtCourt of Appeals of North Carolina
DecidedAugust 2, 2011
DocketCOA10-1389
StatusPublished
Cited by10 cases

This text of 715 S.E.2d 193 (WATERS EDGE BUILDERS, LLC v. Longa) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
WATERS EDGE BUILDERS, LLC v. Longa, 715 S.E.2d 193, 214 N.C. App. 350, 2011 N.C. App. LEXIS 1623, 2011 WL 3276642 (N.C. Ct. App. 2011).

Opinion

BRYANT, Judge.

Where a claim of lien cannot be premised upon a contract implied in law wherein the theory of recovery is quantum meruit, the trial court erred in granting plaintiff’s claim of lien on defendant’s property and awarding plaintiff attorney’s fees on the basis of plaintiff’s status as the prevailing party. Where the evidence is not conclusive that the final arrangement between the parties required plaintiff to perform some act indicating a promise to complete defendant’s staircase for a cost of $9,000.00, the trial court was not compelled to find that the contractual relationship between the parties was unilateral.

Plaintiff Waters Edge Builders, LLC, was hired by defendant Oscar Longa to construct a staircase in a home he and his wife (collectively “defendants”) were renovating in Watauga County. This matter arises from a disagreement regarding the final amount plaintiff was owed for the work. On 8 September 2008, plaintiff filed a claim of lien on defendants’ real property which stated that labor or materials were last furnished upon the property on 13 August 2008. On 5 February 2009, plaintiff filed a complaint seeking recovery on the basis of breach of contract, mechanics and materialman’s lien, and quantum meruit. On 1 April 2009, defendant answered plaintiff’s complaint and counterclaimed on the basis of breach of contract, fraud, deceptive acts or practices affecting commerce, and action to quiet title. On 25 June 2010, defendants filed a motion to dismiss the claim of lien and for summary judgment as to the contract claim against *352 Jenifer Longa. On 8 July 2010, after considering the affidavits of the parties and the arguments of counsel presented in open court on 6 July 2010, the trial court denied defendants’ motion to dismiss the claim of lien and motion for summary judgment. On 11 August 2010, the trial court entered its order awarding plaintiff $5,000.00 under the theory of quantum meruit and granting plaintiff a materialman’s lien against defendants’ property. Pursuant to the lien, the court ordered that defendants’ property be sold in accordance with N.C. Gen. Stat. § 44A-13(b) to satisfy the lien. Further, the trial court concluded that there was an unreasonable refusal by defendants to fully resolve the matter, constituting bad faith. On this basis and in its discretion, the trial court awarded plaintiff $8,625.00 in attorney’s fees. Defendants appeal.

On appeal, defendants raise four issues: did the trial court err (I) in enforcing plaintiff’s claim of lien; (II) in granting plaintiff attorney’s fees; (III) in awarding recovery on the theory of quantum meruit; and (IV) in concluding that no unilateral contract existed between the parties.

/

Defendants first argue that the trial court erred in enforcing plaintiff’s claim of lien when the trial court also found that there existed no express contract between the parties and allowed plaintiff’s recovery on the theory of quantum meruit. Defendants contend that absent an express contract or one implied-in-fact, plaintiff is precluded from placing a lien on real property. We agree.

“The materialman’s lien statute is remedial in that it seeks to protect the interests of those who supply labor and materials that improve the value of the owner’s property.” O & M Indus. v. Smith Eng’g Co., 360 N.C. 263, 268, 624 S.E.2d 345, 348 (2006) (citations omitted). “A remedial statute must be construed broadly in the light of the evils sought to be eliminated, the remedies intended to be applied, and the objective to be attained.” Carolina Bldg. Servs.’ Windows & Doors, Inc. v. Boardwalk, LLC, 362 N.C. 262, 264, 658 S.E.2d 924, 926 (2008) (citation and internal quotations omitted). Under North Carolina General Statutes, section 44A-8,

[a]ny person who performs or furnishes labor or professional design ... or furnishes materials . . . pursuant to a contract, either express or implied, with the owner of real property for the making of an improvement thereon shall, upon complying with the provisions of this Article, have a right to file a claim of lien on real property on the real property to secure payment of all debts *353 owing for labor done or professional design or surveying services or material furnished or equipment rented pursuant to the contract.

N.C. Gen. Stat. § 44A-8 (2009) (emphasis added). “There are at least three variations of contract theory . . . : express contract, contract implied in fact, and contract implied in law. The first two theories are based on ‘real’ contracts, genuine agreements between the parties.” Ellis Jones, Inc. v. Western Waterproofing Co., 66 N.C. App. 641, 645, 312 S.E.2d 215, 217 (1984). A contract implied-in-law is not based upon an actual agreement. Paul L. Whitfield, P.A. v. Gilchrist, 348 N.C. 39, 42, 497 S.E.2d 412, 415 (1998). “[A]nd quantum meruit is not an appropriate remedy when there is an actual agreement between the parties.” Id. “In order to prevent unjust enrichment, a plaintiff may recover in quantum meruit on an implied contract theory for the reasonable value of services rendered to and accepted by a defend- ant.” Horack v. S. Real Estate Co., 150 N.C. App. 305, 311, 563 S.E.2d 47, 52 (2002) (citation omitted).

Here, the trial court denied plaintiff’s claim for breach of contract. Specifically, the trial court found that “Plaintiff failed to submit evidence sufficient to prove that there was a meeting of the minds as to the amount and manner in which Plaintiff was to be paid for work performed for Defendants and therefore Plaintiff failed to prove that there was an express contract between the parties.” Instead, the trial court found that there were sufficient grounds to award plaintiff a recovery for the value of materials and labor under the theory of quantum meruit.

[While] quantum meruit is a measure of recovery for the reasonable value of services rendered in order to prevent unjust enrichment. It operates as an equitable remedy based upon a quasi contract or a contract implied in law. A quasi contract or a contract implied in law is not a contract.

Gilchrist, 348 N.C. at 42, 497 S.E.2d at 414-15 (internal citations and quotations omitted). A contract implied-in-law is nothing more than a term of art used to express an equitable remedy used by the court to prevent unjust enrichment. To establish a valid claim of lien under section 44A-8, an enforceable contract must exist between the parties. As quantum meruit is not a theory based upon an actual agreement, it may not establish the contractual relationship necessary to form the basis for filing a claim of lien pursuant to N.C.G.S. § 44A-8. Accordingly, the trial court’s order granting plaintiff a lien on defendants’ real property is reversed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barnes Electric Construction, Inc. v. Forsythe
2025 IL App (2d) 240479-U (Appellate Court of Illinois, 2025)
Lannan v. Bd. of Governors of the Univ. of N.C.
Court of Appeals of North Carolina, 2022
Cabrera v. Harvest Street Holdings
Court of Appeals of North Carolina, 2022
Kixsports, LLC v. Munn
2021 NCBC 23 (North Carolina Business Court, 2021)
Augustson v. Bank of America, N.A.
864 F. Supp. 2d 422 (E.D. North Carolina, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
715 S.E.2d 193, 214 N.C. App. 350, 2011 N.C. App. LEXIS 1623, 2011 WL 3276642, Counsel Stack Legal Research, https://law.counselstack.com/opinion/waters-edge-builders-llc-v-longa-ncctapp-2011.