O & M INDUSTRIES v. Smith Engineering Co.

624 S.E.2d 345, 360 N.C. 263, 2006 N.C. LEXIS 6
CourtSupreme Court of North Carolina
DecidedJanuary 27, 2006
Docket502PA04
StatusPublished
Cited by39 cases

This text of 624 S.E.2d 345 (O & M INDUSTRIES v. Smith Engineering Co.) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O & M INDUSTRIES v. Smith Engineering Co., 624 S.E.2d 345, 360 N.C. 263, 2006 N.C. LEXIS 6 (N.C. 2006).

Opinion

PARKER, Justice.

O & M Industries (“plaintiff’) instituted this action against Smith Engineering (“Smith”) and Kurz Transfer Products, LP (“defendant”) under N.C.G.S. § 44A-18, the materialman’s statutory lien. The issue before the Court for review is whether the Court of Appeals properly reversed the trial court’s entry of summary judgment for plaintiff under N.C.G.S. § 44A-20. For the reasons stated herein, we reverse the decision of the Court of Appeals and remand for consideration of additional issues.

Defendant operates a manufacturing facility in Lexington, North Carolina, on property leased from an affiliate company. On or about 14 December 2000, defendant contracted with Smith for the design and construction of a regenerative thermal oxidizer system. Smith subcontracted with plaintiff for the construction and delivery of a three canister thermal oxidizer. Plaintiff performed by shipping the oxidizer in June 2001. Believing Smith to be in financial difficulty, plaintiff served a Notice of Claim of Lien on defendant on 8 *265 June 2001 in the amount of $113,655.00. The evidence tends to show that defendant was aware of Smith’s financial position.

After receiving the Notice, defendant made two payments to Smith, one for $164,831.25 on 6 July 2001, and one for $150,000.00 on 1 August 2001. Smith ceased work on the project on 13 August 2001, and defendant’s estimates of its costs to complete ranged at various times from $25,000 to over $415,000. On 22 August 2001, Smith informed defendant that it had filed for bankruptcy. Plaintiff served another Notice of Claim of Lien on defendant on 23 August 2001 in the amount of $127,392.12. Plaintiff instituted this action when it did not receive payment from either defendant or Smith. Plaintiff obtained a default judgment against Smith.

Thereafter, plaintiff moved for summary judgment, alleging that defendant was personally liable as the result of the two post-Notice payments to Smith. Defendant also moved for summary judgment, arguing inter alia that the additional costs necessary to complete the project barred plaintiff from recovery. The trial court denied defendant’s motion, allowed plaintiff’s motion, entered judgment against defendant in the amount of $113,655.00 plus interest, and awarded plaintiff attorney’s fees and costs.

On appeal to the Court of Appeals, defendant argued that unsettled questions concerning the sufficiency of its retained funds and its costs to complete the project raised issues of material fact, thereby making summary judgment improper. Defendant specifically claimed that it was not obligated to pay plaintiff in that the cost to complete the project would exceed the amount otherwise owed to Smith. Defendant also argued issues of estoppel and novation based on a letter sent by plaintiff to Smith dated 15 June 2001, and on plaintiff’s 23 August 2001 Notice of Claim of Lien sent to defendant, respectively. Relying upon Lewis-Brady Builders Supply, Inc. v. Bedros, 32 N.C. App. 209, 231 S.E.2d 199 (1977) and Watson Electrical Construction, Co. v. Summit Cos., 160 N.C. App. 647, 587 S.E.2d 87 (2003), the Court of Appeals agreed with defendant that a determination of defendant’s costs to complete the project was necessary to calculate the appropriate setoff amount and reversed the trial court’s entry of summary judgment for plaintiff. The Court of Appeals opinion did not reach defendant’s estoppel or novation arguments.

In its appeal to this Court, plaintiff contends that the Court of Appeals failed to address and properly apply the applicable lien statutes. We agree. We note, however, that we express no opinion on *266 defendant’s estoppel or novation arguments and assume arguendo for purposes of our discussion herein that plaintiff’s 8 June 2001 notice of lien was valid.

The North Carolina Constitution mandates that the General Assembly “shall provide by proper legislation for giving to mechanics and laborers an adequate lien on the subject-matter of their labor.” N.C. Const. art. X, § 3. To satisfy this mandate the legislature enacted statutes which are now codified in Chapter 44A of the General Statutes. In Electric Supply Co. of Durham v. Swain Electrical Co., 328 N.C. 651, 403 S.E.2d 291 (1991), this Court, recognizing the central role played by credit in the construction industry, articulated the importance of an adequate lien for subcontractors and suppliers of materials and labor:

Suppliers . .. provide labor and materials to contractors and subcontractors who perform their portion of the work on a project. Since the contractor or subcontractor is generally not paid until the job, or a portion of it, is completed (and is probably unable to pay until it, in turn, is paid), their suppliers extend labor and materials to them on credit. An adequate lien is necessary to encourage responsible extensions of credit, which are necessary to the health of the construction industry.

Id. at 659, 403 S.E.2d at 296.

The statutory provisions at issue in this case are N.C.G.S. §§ 44A-18 and 44A-20. 1 Section 44A-18 provides in relevant part:

Upon compliance with this Article:

(1) A first tier subcontractor who furnished labor, materials, or rental equipment at the site of the improvement shall be entitled to a lien upon funds which are owed to the contractor with whom the first tier subcontractor dealt and which arise out of the improvement on which the first tier subcontractor worked or furnished materials.
(5) The liens granted under this section shall secure amounts earned by the lien claimant as a result of his having furnished labor, materials, or rental equipment at the site of the im~ *267 provement under the contract to improve real property, whether or not such amounts are due and whether or not per- ■ formance or delivery is complete.
(6) A lien upon funds granted under this section is perfected upon the giving of notice in writing to the obligor as provided in G.S. 44A-19 and shall be effective upon the obligor’s receipt of the notice. The subrogation rights of a first, second, or third tier subcontractor to the lien of the contractor created by Part 1 of Article 2 of this Chapter are perfected as provided in G.S. 44A-23.

N.C.G.S. § 44A-18 (2003).

Section 44A-20 sets forth the duties of an owner upon receipt of a Notice of Claim of Lien:

(a) Upon receipt of the notice provided for in this Article the obligor shall be under a duty to retain any funds subject to the lien or liens under this Article up to the total amount of such liens as to which notice has been received.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wardson Constr., Inc. v. City of Raleigh
Supreme Court of North Carolina, 2026
State v. Smathers
Court of Appeals of North Carolina, 2026
Legal Impact for Chickens v. Case Farms
Court of Appeals of North Carolina, 2025
Zander v. Orange Cnty.
Court of Appeals of North Carolina, 2023
C Invs. 2, LLC v. Auger
Supreme Court of North Carolina, 2022
Belmont Ass'n v. Farwig
Supreme Court of North Carolina, 2022
Belmont Ass'n
Court of Appeals of North Carolina, 2021
Davis & Taft Architecture, P.A. v. DDR-Shadowline
Court of Appeals of North Carolina, 2019
Wilkie v. City of Boiling Spring Lakes
809 S.E.2d 853 (Supreme Court of North Carolina, 2018)
Arnesen v. Rivers Edge Golf Club and Plantation, Inc.
781 S.E.2d 1 (Supreme Court of North Carolina, 2015)
Thomas v. Williams
773 S.E.2d 900 (Court of Appeals of North Carolina, 2015)
United States v. Dish Network, L.L.C.
75 F. Supp. 3d 942 (C.D. Illinois, 2014)
Pete Wall Plumbing Co. v. Sandra Anderson Builders, Inc.
721 S.E.2d 663 (Court of Appeals of North Carolina, 2011)
WATERS EDGE BUILDERS, LLC v. Longa
715 S.E.2d 193 (Court of Appeals of North Carolina, 2011)
Gaines & Co. v. Wendell Falls Residential, LLC
714 S.E.2d 179 (Court of Appeals of North Carolina, 2011)
Baumann-Chacon v. Baumann
710 S.E.2d 431 (Court of Appeals of North Carolina, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
624 S.E.2d 345, 360 N.C. 263, 2006 N.C. LEXIS 6, Counsel Stack Legal Research, https://law.counselstack.com/opinion/o-m-industries-v-smith-engineering-co-nc-2006.