United States v. Johnson, Smathers & Rollins

67 F.2d 121, 1933 U.S. App. LEXIS 4372
CourtCourt of Appeals for the Fourth Circuit
DecidedOctober 3, 1933
Docket3441
StatusPublished
Cited by42 cases

This text of 67 F.2d 121 (United States v. Johnson, Smathers & Rollins) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Johnson, Smathers & Rollins, 67 F.2d 121, 1933 U.S. App. LEXIS 4372 (4th Cir. 1933).

Opinion

SOPER, Circuit Judge.

This action at law was brought in the District Court in the name of the United States, for the use of Crane Company, against Mureh Brothers Construction Company and Southern Surety Company of New York, to recover for material furnished in the construction of the United States post office and court house building in Asheville, N. C. The suit is based upon a contractor’s performance bond, whereby the defendants, as contractor and surety, respectively, agreed to make prompt payment to all persons supplying the contractor with labor and material in the prosecution of the work; and the claim was that there was due and owing the Crane Company a balance of $6,440.45; with interest, for plumbing fixtures which it had furnished to Sluder Brothers of Asheville, with whom the contractor had entered into a subcontract.. The answer of the defendants showed that the contractor had been paid by the United States, the full amount of the contract price, and in turn had paid in full all sums due by it to every subcontractor performing work upon the building, including Sluder Brothers, and that whatever indebtedness was due to the Crane Company for material supplied in the construction of the building was due and owing by Sluder Brothers and not by the contractor; and that Sluder Brothers, as principal, and the Indemnity Insurance Company of North America, as surety, had executed a bond to the contractor for the performance of the subcontract between it and Sluder Brothers, and the payment of all material furnished and #11 labor performed under the subcontract. Thereupon Sluder Brothers and the Indemnity Insurance Company of North America were brought into the case as parties defendant, and the case proceeded against them as the sole defendants under an agreement between the parties that if the plaintiff was entitled to judgment against any of the defendants, it was entitled to judgment against the subcontractor and its surety only. Sluder Brothers admitted the purchase of materials from Crane Company for the Asheville building between September, 1929, and April, 1930, in the sum of $15,605.81, and alleged that they had paid the entire purchase price except the balance of $2,440:45, with interest, and that it had previously tendered the balance to Crane Company, which refused to accept it.

The sole question therefore in the case was whether the subcontractor was indebted for an additional sum of $4,000, claimed by the plaintiff. The answer of the defendants remaining in the case showed that a payment of $4,000 had been made by the subcontractor to the plaintiff on December 19, 1929; out of moneys paid by the contractor to the subcontractor for materials purchased for the Ashe-ville building; that the plaintiff knew the source from which these payments had been derived, but nevertheless applied the $4,000 to another account for materials sold by the plaintiff to Sluder Brothers, and used by them in the performance of other work.

Upon these pleadings, and without denial by the plaintiff of the allegations in the answer as to the application of the payment, the ease was submitted to the court and jury. The evidence showed that Sluder Brothers had had an open running account with Crane Company since February 8,1924, and that on August 7, 1929, there was a balance due the Crane Company on this old account of $3,-647.34; that on the last date named, Sluder Brothers made its first shipment of material under a contract of June 17,1929, which they had with the board of education of Easley, S. C., to furnish materials to certain sehoolhouses in that locality; that the total shipments on the Easley buildings from August 7 to November 9 amounted to $4,507.77, which were charged against this old regular account; that three payments were made by Sluder Brothers to Crane Company between September,8 and November 7, in the aggregate sum of $3,578.09, which were credited by Crane Company against the balance due it prior to the first shipments to the Easley buildings; that on July 12, 1929; the subcontract for the Asheville building was made and materials were shipped therefor by Crane Company to Sluder Brothers during the months of September, October, and November in the sum of $8,479.86; that the account for these materials was separated from the old account on November 7, 1929; and that later, on December 16, 1928; the contractor paid to the subcontractor the sum of $5,465, and out of. the money so received Sluder Brothers paid $4,000 on December 19; 1929; to Crane Company. This payment was not credited to the Asheville account, but to the old account. ■

Sluder Brothers gave no instructions to Crane Company as to the account to which the payment should be applied, although there was circumstantial evidence from which the jury might have inferred that Sluder knew how the money was applied and made no protest. • On the other- hand, evidence on *123 behalf of Sluder Brothers tended to show that they did not know that the money had not been credited against the mateiials shipped to Asheville. The evidence was conflicting also as to whether Crane Company knew the source from which the payment of $4,000 came; but there was substantial evidence tending to show that it did have such knowledge. The District Judge instructed the jury in substance that if Crane Company knew that the payment of $4,000’ had been made to it by Sluder Brothers out of moneys which it had received from the contractor for materials furnished and work done upon the Ashe-ville building, then the application of the payment by Crane Company to the old or regular account was wrongful, and the verdict should be limited to the sum of $2,440'.45, even though the application of the money was made with Sluder Brothers’ knowledge or concurrence; but that if the Crane Company did not know the source of the payment, then the Crane Company had the right to make the application in question and the verdict should be for it in the sum of $6,440.45. The jury found a verdict for the smaller sum.

Exceptions to this ruling form the basis of this appeal. It is contended that the peculiar circumstances of this case do not alter the general rule as to the application of payments ; that the right belongs, in the first instance, to the debtor, and in the absence of a direction from him to the creditor, to apply a payment to any debt which the debtor may owe him, even though a surety is bound on one of the debts involved. See Maryland Casualty Co. v. City of South Norfolk (C. C. A.) 54 F.(2d) 1032, 1038; Grafton Hotel Company v. Walsh (C. C. A.) 228 F. 5; Bankers’ Trust Co. v. T. A. Gillespie Co. (C. C. A.) 181 F. 448, 460; Ross v. Turner (C. C. A.) 259 F. 737, 751.

This rule, however, is not absolute when the surety involved has an equity in the money paid by the debtor, although the authorities are at variance as to the character of the equitable consideration in the surety’s favor which deprives the debtor and creditor of election, and requires an application of the money to the guaranteed debt. Such an equity exists under the admitted facts of this ease, in accordance with the rule announced by decisions in this and other federal circuits.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. St. Paul Fire & Marine Insurance
86 F.3d 332 (Fourth Circuit, 1996)
United States v. Sentry Insurance
774 F.2d 80 (Fourth Circuit, 1985)
Warren Brothers Co. v. Sentry Ins.
433 N.E.2d 1253 (Massachusetts Appeals Court, 1982)
United States v. Wiring, Inc.
646 F.2d 1037 (Fifth Circuit, 1981)
United States v. Wibco, Inc.
396 F. Supp. 1253 (District of Columbia, 1975)
United States v. Transamerica Insurance Company
357 F. Supp. 743 (E.D. Virginia, 1973)
Maryland National Insurance v. Lake Shore Growers Cooperative Ass'n
228 So. 2d 276 (Supreme Court of Florida, 1969)
American Oil Co. v. Brown Paving Co.
298 F. Supp. 528 (D. South Carolina, 1969)
Turner Produce Co. v. Lake Shore Growers Coop. Ass'n
217 So. 2d 856 (District Court of Appeal of Florida, 1969)
United States Casualty Co. v. Noland Co.
286 F. Supp. 333 (M.D. North Carolina, 1968)
United States v. Franchi Bros. Construction Corp.
378 F.2d 134 (Second Circuit, 1967)
United States v. Grubb
358 F.2d 508 (Ninth Circuit, 1966)
United States v. Grubb
358 F.2d 508 (First Circuit, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
67 F.2d 121, 1933 U.S. App. LEXIS 4372, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-johnson-smathers-rollins-ca4-1933.